Академический Документы
Профессиональный Документы
Культура Документы
Concept of Management
GENERAL MANAGEMENT
PROJECT MANAGEMENT
Introduction
Definition
of Management
Management is an art of getting work done by other through the process of planning, organizing, leading, controlling, forecasting, coordinating, directing, communication and motivating to achieve the goal and objective of an organization.
Procurement
Creating project plan : 1. Project Charter or Business Case 2. Project scope 3. Functional specification 4. Requirements baseline 5. Contract documentation 6. Plans and drawings 7. Project execution plan 8. Contracting and purchasing plan 9. Equipment lists 10. Installation plan 11. Testing plan
Construction
leader.
8. COORDINATION 1. PLANNING 2. ORGANIZATION
7. DIRECTING
6. STAFFING
CONTRACT CRITERIA
4. CONTROLLING & MONITORING
3. COMMUNICATION
5. MOTIVATION
Time
Cost
Quality
Introduction
Why
1. 2. 3.
Planning ??
4.
5. 6.
Reduce risks and uncertainty to a minimum. Ensure a clear understanding of the objectives. Establish adequate standards of performance. Provide a structured basis for carrying out the work. Derive procedures to control the work effectively. Obtain the top optimum result with minimum effort in minimum time.
Introduction
Components
1. 2.
of all planning.
3.
4.
5.
6.
7.
Establishing the decider results the objectives. Determining the strategy to be followed to achieve or exceed result. A budget to establish expenditure to achieve the results. Projections of what will happen at certain specific points in the time. Organizational structure and policies or empowerment. Establishing procedures for control and communication. Setting standards of performance and methods of measurement.
Introduction
Components
Planning
Comes first Estimating, sequencing, time analysis Importance of network analysis
Scheduling
Follows on, and extends, the plan Allocates resources The working details to implement the plan
1. 2. 3. 4.
Planning of activities normally includes time, money, machines, materials and manpower schedule. Planning tools available include bar chart, linked bar chart, Critical Path Method (CPM), Precedence Diagram, PERT, etc The planning of activities for a project can be very complicated due to the complexity of a project Planning evolve from several main activities which were then breakdown into smeller activities.
Introduction
Planning
1.
2. 3.
Types of Network Arrow Diagramming Method Precedence Diagramming Method Network Rules Activity Durations
GANTT
Overview
Bar Chart is one of the oldest scheduling technique Wide acceptance because it is readily understood by almost every one It is very easy to develop and used Useful technique for a small project Task schedule can be graphically presented on the time-scale. The main weakness is that relationship that exist between the task cannot be shown.
Bar Chart
Example 1 Time on each activity.
: 1 week , started in 1 Okt 11 : 2 weeks , 5 Okt 11 : 3 weeks , 15 Okt 11 : 2 weeks , 25 Okt 11 : 2 weeks , 29 Okt 11 : 1 weeks , 5 Nov11
12
Bar Chart
Table 1 Solution : Example 1 Bar Chart
No
Activity
Duration 1
1/10
8/10
Time 2
15/10
3
22/10
4
29/10
5
5/11
1 2 3 4 5 6
1 2 3 2 2 1
13
A predecessor
14
B successor
Float
15
GANTT
GANTT Advantages
Easy to prepare Easily understood by all parties It shows the total plan in impact form. Good communication tool
Disadvantages.
Do not show interrelationships between activities Managing projects becomes difficult without those relationships between activities It is difficult to judge the impact of an unexpected event on the rest of the construction process
PERT
view
Advantages
PERT
view
Accounts for uncertainty Critical path on PERT chart allows focus of resources and effort to reduce risk. Allows visibility into possible extreme delivery dates using PERT estimation as a result of potential opportunities to be exploited or risks which to mitigate.
Disadvantages.
Time and labor intensive Assumption of unlimited resources is big issue Lack of functional ownership of estimates Mostly only used on large, complex project : Can become confusing for the uninitiated or when projects have complex task relationships. If some activities take longer than expected, the critical path originally being managed to might end up being wrong : If other paths are near the critical path, they, too should be managed diligently to prevent project overruns.
PERTvs
GANTT view
CPM
view
Types
of NETWORK
Types AOA
Circles representing Events o Such as start or end of a given task Lines representing Tasks o Thing being done Build UI a.k.a. Arrow Diagramming Method (ADM)
of NETWORK
consists of..
AON
Tasks on Nodes o Nodes can be circles or rectangles (usually latter) o Task information written on node Arrows are dependencies between tasks a.k.a. Precedence Diagramming Method (PDM)
consists of...
NETWORK Advantages
Diagrams
Show precedence well Reveal interdependencies not shown in other techniques Ability to calculate critical path Ability to perform what if exercises
Disadvantages
o You need to incorporate this yourself (Resource Dependencies) when determining the real Critical Path
NETWORK
Networks flow from left to right
Rules
Activity cannot begin until all preceding connected activities have been
completed
Arrows indicate precedence and flow. Arrows can cross over each other Each activity should have a unique identifier
AOA
Arrow Diagramming Method (ADM) or Activity-on-arrow (AOA), Precedence Diagramming Method (PDM) or Activity-on-node (AON),
AOA
[ADM] method
Arrow Diagram
In arrow diagram project task or activities are represented by the arrow and connected by the node to express their logical relationship
Arrow Activity Node Junction to the event - Activity started or end
AON
[PDM] method
Node Diagram
PDM activity is place on the node The arrow used to connect between project task to show their logical relationship
TASK
Finish-to-Start (FS)
Dependency Relationships
Start-to-Start (SS)
Finish-to-Finish (FF)
Start-to-Finish (SF)
Example
Example
Example
2 A 0 0 3D 3 5 E 5D 6 10 G 4D H 8 17 17
3: AOA
3
7
D
8D
11 15 I 6D 9 4D J 21 21
B 5D C 7D
13
7 7
F 5D
12 12
5D
0 0
3 7
Predecessor
Successor
Example
0 A 4
0 0 START 0 0
3: AON
3 3
7 5 E 8 7 F 7 10 5 13 12 5 12
3 D 7
11 8 15
5 0 5 B 3 8 0 7 C 7 0 7
10 14 G 4 13 17 12 H 12 17
11 17 6 I 15 21 17 J 17 21 4 21
0 21 21 FINISH 21 21
5 17
ES LS EF LF
SLACK
EST EFT LFT
/FLOAT/LAG in AON
LST
Slack
LFT EFT
or
LST EST
Slack time Slack /Float/ Lag - is the length of time an activity can be delayed without delaying the entire project
Dummy:
c b d f e g
AOA only
k
j
or
Activity Predecessor _ m _ n m, n r n s
8
Install drywall
11
Pour foundation
9 4
Lay brickwork
10
Lay flooring
12
Paint
5
Finish roof Lay storm drains
Finish carpeting
16
14
Install roof drainage Finish grading
13
Finish floors
18
15
17
Exercise1:
Activity ID A B C D E F G H (successor) B, C D E F G H H -
Calculate & Draw AOA and AON networks ?? Highlight CPM ?? How many weeks ??
Exercise1: AOA
3 B 3 1 0 0 A 2w 2 C G 3 4 E 3 6 D
5
F 2 7 H 1 8
Calculate & Draw AOA and AON networks ?? Highlight CPM ?? How many weeks ??
Exercise1: AON
Node Diagram Method - Table
Event (1) 1-2 2-3 2-4 3-5 4-6 5-7 6-7 7-8
Activity (2) A B C D E F G H
Masa (3) 2 3 2 4 3 2 3 1
ES (4) 0 2 2 5 4 9 7 11
LS (5) 0 2 2 5 5 9 8 11
EF (6) 2 5 4 9 7 11 11 12
LF (7) 2 5 5 9 8 11 11 12
Total float = 0
Exercise1: AOA
Arrow Diagram Method Gantt / Bar Chart No Aktiviti
1 1 2 3 4 5 6 7 8 A B C D E F G H
10
11
12
float
float
Exercise1:
Task a b c d e f g h i j k Pedecessor * * a a b b c,d e f e,g h,i 4 3 3 2 6 4 1 4 5 6 1