31 July 2008
ECSS Secretariat ESA-ESTEC Requirements & Standards Division Noordwijk, The Netherlands
ECSSMST80C 31July2008
Foreword This Standard is one of the series of ECSS Standards intended to be applied together for the management, engineering and product assurance in space projects and applications. ECSS is a cooperative effort of the European Space Agency, national space agencies and European industry associationsforthepurposeofdevelopingandmaintainingcommonstandards.Requirementsinthis Standardaredefinedintermsofwhatshallbeaccomplished,ratherthanintermsofhowtoorganize and perform the necessary work. This allows existing organizational structures and methods to be appliedwheretheyareeffective,andforthestructuresandmethodstoevolveasnecessarywithout rewritingthestandards. This Standard has been prepared by the ECSSMST80 Working Group, reviewed by the ECSS ExecutiveSecretariatandapprovedbytheECSSTechnicalAuthority.
Disclaimer ECSSdoesnotprovideanywarrantywhatsoever,whetherexpressed,implied,orstatutory,including, butnotlimitedto,anywarrantyofmerchantabilityorfitnessforaparticularpurposeoranywarranty that the contents of the item are errorfree. In no respect shall ECSS incur any liability for any damages,including,butnotlimitedto,direct,indirect,special,orconsequentialdamagesarisingout of, resulting from, or in any way connected to the use of this Standard, whether or not based upon warranty,businessagreement,tort,orotherwise;whetherornotinjurywassustainedbypersonsor propertyorotherwise;andwhetherornotlosswassustainedfrom,oraroseoutof,theresultsof,the item,oranyservicesthatmaybeprovidedbyECSS.
Publishedby:
Copyright:
ESARequirementsandStandardsDivision ESTEC, P.O. Box 299, 2200 AG Noordwijk The Netherlands 2008 by the European Space Agency for the members of ECSS
ECSSMST80C 31July2008
Change log
Firstissue
Secondissue
Thirdissue MaindifferencesbetweenECSSM0003B(16August2004)andthis versionare: RenumberingfromECSSM0003toECSSMST80. Deletionofthedefinitionsfor:.risk,residualrisk,riskmanagement,risk managementpolicybecauseidenticallydefinedinECSSSST0001 Update of descriptive text in clause 4.4, 5.1, 5.2.1.2f, 5.2.1.2h, 5.2.2.1, 6.5c, In clause 7, former text contained in AIM converted into notes and former text from EXPECTED OUTPUT deleted or converted into requirementswhennormative.
ECSSMST80C 31July2008
Table of contents
Change log .................................................................................................................3 Introduction................................................................................................................6 1 Scope.......................................................................................................................7 2 Normative references .............................................................................................8 3 Terms, definitions and abbreviated terms............................................................9
3.1 3.2 3.3 Terms from other standards ....................................................................................... 9 Terms specific to the present standard ...................................................................... 9 Abbreviated terms .................................................................................................... 10
ECSSMST80C 31July2008
Annex A (normative) Risk management policy document - DRD........................30 Annex B (normative) Risk management plan - DRD.............................................33 Annex C (normative) Risk assessment report - DRD ...........................................36 Annex D (informative) Risk register example and ranked risk log example ......38 Annex E (informative) Contribution of ECSS Standards to the risk management process .........................................................................................41 Bibliography.............................................................................................................43 Figures
Figure 5-1: The steps and cycles in the risk management process ....................................... 14 Figure 5-2: The tasks associated with the steps of the risk management process within the risk management cycle .................................................................................. 14 Figure 5-3: Example of a severityofconsequence scoring scheme .................................... 15 Figure 5-4: Example of a likelihood scoring scheme.............................................................. 16 Figure 5-5: Example of risk index and magnitude scheme .................................................... 17 Figure 5-6: Example of risk magnitude designations and proposed actions for individual risks ..................................................................................................................... 17 Figure 5-7: Example of a risk trend ........................................................................................ 21
ECSSMST80C 31July2008
Introduction
Risks are a threat to project success because they have negative effects on the project cost, schedule and technical performance, but appropriate practices of controllingriskscanalsopresentnewopportunitieswithpositiveimpact. The objective of project risk management is to identify, assess, reduce, accept, and control space project risks in a systematic, proactive, comprehensive and cost effective manner, taking into account the projects technical and programmaticconstraints.Riskisconsideredtradableagainsttheconventional known project resources within the management, programmatic (e.g. cost, schedule)andtechnical(e.g.mass,power,dependability,safety)domains.The overall risk management in a project is an iterative process throughout the project life cycle, with iterations being determined by the project progress throughthedifferentprojectphases,andbychangestoagivenprojectbaseline influencingprojectresources. Risk management is implemented at each level of the customersupplier network. Known project practices for dealing with project risks, such as system and engineering analyses, analyses of safety, critical items, dependability, critical path,andcost,areanintegralpartofprojectriskmanagement.Rankingofrisks accordingtotheircriticalityforprojectsuccess,allowingmanagementattention tobedirectedtotheessentialissues,isamajorobjectiveofriskmanagement. The project actors agree on the extent of the risk management to be implemented in a given project depending on the project definition and characterization.
ECSSMST80C 31July2008
1 Scope
This Standard defines the principles and requirements for integrated risk management on a space project; it explains what is needed to implement a projectintegratedriskmanagementpolicybyanyprojectactor,atanylevel(i.e. customer,firstlevelsupplier,orlowerlevelsuppliers). This Standard contains a summary of the general risk management process, whichissubdividedintofour(4)basicstepsandnine(9)tasks. Theriskmanagementprocessrequiresinformationexchangeamongallproject domains, and provides visibility over risks, with a ranking according to their criticalityfortheproject;theserisksaremonitoredandcontrolledaccordingto therulesdefinedforthedomainstowhichtheybelong. The fields of application of this Standard are all the activities of all the space projectphases.AdefinitionofprojectphasingisgiveninECSSMST10. Thisstandardmaybetailoredforthespecificcharacteristicsandconstraintsofa spaceprojectinconformancewithECSSSST00.
ECSSMST80C 31July2008
2 Normative references
The following normative documents contain provisions which, through reference in this text, constitute provisions of this ECSS Standard. For dated references,subsequentamendmentsto,orrevisionsofanyofthesepublications donotapply.However,partiestoagreementsbasedonthisECSSStandardare encouragedtoinvestigatethepossibilityofapplyingthemostrecenteditionsof the normative documents indicated below. For undated references the latest editionofthepublicationreferredtoapplies. ECSSST0001 ECSSMST10 ECSSsystemGlossaryofterms SpaceprojectmanagementProjectplanningand implementation
ECSSMST80C 31July2008
3.2
3.2.2
(risk) communication
all information and data necessary for risk management addressed to a decisionmakerandtorelevantactorswithintheprojecthierarchy
3.2.3
(risk) index
score used to measure the magnitude of the risk; it is a combination of the likelihoodofoccurrenceandtheseverityofconsequence,wherescoresareused tomeasurelikelihoodandseverity
3.2.4
individual (risk)
riskidentified,assessed,andmitigatedasadistinctriskitemsinaproject
consists of all the project activities related to the identification, assessment, reduction,acceptance,andfeedbackofrisks
3.2.6
overall (risk)
risk resulting from the assessment of the combination of individual risks and theirimpactoneachother,inthecontextofthewholeproject NOTE Overall risk can be expressed as a combination of qualitativeandquantitativeassessment.
3.2.7
(risk) reduction
implementationofmeasuresthatleadstoreductionofthelikelihoodorseverity ofrisk NOTE Preventive measures aim at eliminating the cause of a problem situation, and mitigation measures aim at preventing the propagation of the cause to the consequence or reducing the severity of the consequenceorthelikelihoodoftheoccurrence.
3.2.8
resolved (risk)
riskthathasbeenrenderedacceptable
3.2.9
(risk) scenario
sequence or combination of events leading from the initial cause to the unwantedconsequence NOTE The cause can be a single event or something activatingadormantproblem.
3.2.10
(risk) trend
evolutionofrisksthroughoutthelifecycleofaproject
3.2.11
unresolved (risk)
risk for which risk reduction attempts are not feasible, cannot be verified, or haveprovedunsuccessful:ariskremainingunacceptable
3.3
Abbreviated terms
Forthepurposeofthisstandard,theabbreviatedtermsofECSSSST0001and thefollowingapply:
Abbreviation
IEC
Meaning
InternationalElectrotechnicalCommission
10
ECSSMST80C 31July2008
4.2
4.3
11
ECSSMST80C 31July2008
Independent validation of data ensures the objectiveness of risk assessment, performedaspartoftheriskmanagementprocess. Risk management is a continuous, iterative process. It constitutes an integral part of normal project activity and is embedded within the existing management processes. It utilizes the existing elements of the project managementprocessestothemaximumpossibleextent.
4.4
In addition to the risk management policy document, two key documents are established: risk management plan describing the implementation of the risk managementprocess(seeAnnexB),and risk assessment report for communicating the identified and assessed risks as well as the subsequent followup actions and their results (see AnnexC).
12
ECSSMST80C 31July2008
13
ECSSMST80C 31July2008
Step1 Defineriskmanagement implementation requirements Step2 Identifyandassessthe risks Step2 Identifyandassessthe risks Step2 Identifyandassess therisks
Step3 Decideandact
Step3 Decideandact
Step3 Decideandact
Riskmanagementprocess
Projectphases0toFperECSSMST10
Figure51:Thestepsandcyclesintheriskmanagementprocess
Task1:Definetheriskmanagementpolicy Task2:Preparetheriskmanagementplan
R I S K M A N A G E M E N T C Y C L E
Step2 Identifyandassesstherisks
Task3:Identifyriskscenarios Task4:Assesstherisks
Step3 Decideandact
Figure52:Thetasksassociatedwiththestepsoftheriskmanagementprocess withintheriskmanagementcycle
14
ECSSMST80C 31July2008
5.2
5.2.1.1
To initiate the risk management process by defining the project risk managementpolicyandpreparingtheprojectriskmanagementplan.
5.2.1.2
a. b. c.
Thefollowingactivitiesareincludedinthistask: Identificationofthesetofresourceswithimpactonrisks. Identificationoftheprojectgoalsandresourceconstraints. Description of the project strategy for dealing with risks, such as the definition of margins and the apportionment of risk between customer andsupplier. Definition of scheme for ranking the risk goals according to the requirementsoftheproject. Establishment of scoring schemes for the severity of consequences and likelihood ofoccurrencefor the relevant tradable resourcesasshown in theexamplesgiveninFigure53andFigure54. NOTE In the examples, five categories are used for illustration only; more or fewer categories or designationsarealsopossible.
d. e.
f.
Establishment of a risk index scheme to denote the magnitudes of the risksofthevariousriskscenariosasshown,forexampleinFigure55. NOTE1 Establishmentofscoringandriskindexschemasis performed with the full coordination between the differentprojectdisciplinestoensurecompleteand consistentinterpretation. NOTE2 In the example, risk magnitude categorization (Red,Yellow,Green)isusedforillustration only.Differentdesignationsarealsopossible
Score
5 4 3 2 1
Severity
Catastrophic Critical Major Significant Negligible
Severityofconsequence:impacton(forexample)cost
Leadstoterminationoftheproject Projectcostincrease>tbd% Projectcostincrease>tbd% Projectcostincrease<tbd% Minimalornoimpact
Figure53:Exampleofaseverityofconsequencescoringscheme
15
Likelihood
Maximum High Medium Low Minimum
Likelihoodofoccurrence
Certaintooccur,willoccuroneormoretimesperproject Willoccurfrequently,about1in10projects Willoccursometimes,about1in100projects Willseldomoccur,about1in1000projects Willalmostneveroccur,1of10000ormoreprojects
Figure54:Exampleofalikelihoodscoringscheme
g. Establishmentofcriteriatodeterminetheactionstobetakenonrisksof various risk magnitudes and the associated risk decision levels in the projectstructure(asintheexampleinFigure56). NOTE In the example, risk magnitude designation, acceptability, and proposed actions are used for illustration only. Projectspecific policy definitions canbedifferent.
h.
Definitionofriskacceptancecriteriaforindividualrisks. NOTE The acceptability of likelihood of occurrence and severity of consequence are both programme dependent. For example, when a programme is advancing new research, technology development or management, a high probability of a consequence that quickly increase the cost can be acceptable.
i. j. k. l.
m.
16
E D C B A
VeryLow VeryLow
4 Yellow
Figure55:Exampleofriskindexandmagnitudescheme
Riskindex
E4,E5,D5
Riskmagnitude
VeryHighrisk
Proposedactions
Unacceptablerisk:implementnewteamprocessorchange baselineseekprojectmanagementattentionatappropriate highmanagementlevelasdefinedintheriskmanagementplan. Unacceptablerisk:seeabove. Unacceptablerisk:aggressivelymanage,consideralternative teamprocessorbaselineseekattentionatappropriate managementlevelasdefinedintheriskmanagementplan. Acceptablerisk:control,monitorseekresponsiblework packagemanagementattention. Acceptablerisk:seeabove.
E3,D4,C5 E2,D3,C4,B5
Highrisk Mediumrisk
Lowrisk VeryLowrisk
Theriskmanagementplantypicallycontainsthefollowingdata: Description of the project risk management organization including its roleandresponsibility. Summaryoftheriskmanagementpolicy. Theriskmanagementrelateddocumentationandfollowupconcept. Thescopeofriskmanagementovertheprojectduration.
17
ECSSMST80C 31July2008
5.2.2
5.2.2.1
Toidentifyeachoftheriskscenarios,todeterminethen,basedontheoutputs from Step 1, the magnitude of the individual risks and, finally, to rank them. Datafromallprojectdomainsareused(managerial,programmatic,technical). NOTE Listofexamplesofpossibleriskitems: Technical: Technology maturity; definition status of requirements, internal/external interfaces, payloads, operations; availability of margins,supportteam,projectteam;etc. Cost:Overallprojectcostdefinitionstatus;cost margins; insurance costs; availability of funding, independent cost assessment, industrialoffers;humanresourcesaspects;etc. Schedule: Procurement planning; availability ofplanningofphasesandactivitiesinterfacing withthirdparties;etc. Others: Internal organisational aspects; public image; political constraints; risk sharing betweenactors;etc.
5.2.2.2
a. b.
Thefollowingactivitiesareincludedinthistask: Identification of the risk scenarios, including causes and consequences, accordingtotheriskmanagementpolicy. Identification of the means of early warning (detection) for the occurrence of an undesirable event, to prevent propagation of consequences. Identificationoftheprojectobjectivesatrisk.
c.
5.2.2.3
a. b. c. d. e. f.
Thefollowingactivitiesareincludedinthistask: Determinationoftheseverityofconsequencesofeachriskscenario. Determinationofthelikelihoodofeachriskscenario. Determinationoftheriskindexforeachriskscenario. Utilisation of available information sources and application of suitable methodstosupporttheassessmentprocess. Determinationofthemagnitudeofriskofeachriskscenario. Determination of the overall project risk through an evaluation of identified individual risks, their magnitudes and interactions, and resultantimpactontheproject.
18
ECSSMST80C 31July2008
5.2.3
5.2.3.1
Toanalysetheacceptabilityofrisksandriskreductionoptionsaccordingtothe risk management policy, and to determine the appropriate risk reduction strategy.
5.2.3.2
a. b. c.
Thefollowingactivitiesareincludedinthistask: Applicationoftheriskacceptancecriteriatotherisks. Identification of acceptable risks, the risks that will be subjected to risk reduction,anddeterminationofthemanagementdecisionlevel. For accepted risks proceed directly to Step 4; for unacceptable risks proceedtoTask6.
5.2.3.3
a. b. c. d.
Thefollowingactivitiesareincludedinthistask: Determinationofpreventativeandmitigationmeasures/optionsforeach unacceptablerisk. Determinationofriskreductionsuccess,failure,andverificationcriteria. Determination of the risk reduction potential of each measure in conjunctionwiththeoptimizationoftradableresources. Selection of the best risk reduction measures and decision on priorities for implementation, at the appropriate decision making level in the projectaccordingtotheriskmanagementplan. Verificationofriskreduction. Identification of the risks that cannot be reduced to an acceptable level andpresentationtotheappropriatemanagementlevelfordisposition. Identification of the reduced risks for which risk reduction cannot be verified. Identification of the risk reduction potential of all risk reduction efforts withrespecttotheoverallrisk. Documentation of the successfully reduced risks in a resolved risks list; andtheunsuccessfullyreducedrisksinanunresolvedriskslist:present thelattertotheappropriatemanagementlevelfordisposition.
e. f. g. h. i.
5.2.3.4
a. b. c.
19
ECSSMST80C 31July2008
5.2.4
5.2.4.1
To track, monitor, update, iterate, and communicate, and finally accept the risks.
5.2.4.2
a. b. c. d. e.
Thefollowingactivitiesareincludedinthistask: Periodicalassessmentandreviewofallidentifiedrisksandupdatingof theresultsaftereachiterationoftheriskmanagementprocess. Identification of changes to existing risks and initiation of new risk analysisneededinordertodecreaseuncertainties. Verification of the performance and effect of corresponding risk reduction. Illustrationoftherisktrendovertheprojectevolutionbyidentifyinghow themagnitudesofriskhavechangedoverprojecttime. An example of a risk trend for technical risks, which are main risk contributorsatthefirstprojectmilestone,isprovidedinFigure57.S1,S2 andS3arethreeriskscenarios. NOTE In the example, the evolution ofS1shows that, in spite of risk reduction efforts, risk trend can worsenbeforeimprovement.
f. g.
20
ECSSMST80C 31July2008
Risktrendduringprojectphases
S1 S2
S3
Figure57:Exampleofarisktrend 5.2.4.3
a. b.
Thefollowingactivitiesareincludedinthistask: Submission of the risks for formal risk acceptance by the appropriate levelofmanagement. ReturntoTask6forrisksnotaccepted.
21
ECSSMST80C 31July2008
b.
c.
d.
6.2
Responsibilities
The responsibilities for risk management matters within the project organizationaredescribedintheriskmanagementplaninaccordancewiththe riskmanagementpolicy.Thefollowingapproachapplies: a. The project manager acts as the integrator of the risk management function across all concerned project domains. The project manager has overall responsibility for integrated risk management within a project and reports the results of the risk management task to the next higher levelinthecustomer/supplierchain.Theprojectmanagerdefineswhoin the project is responsible for the control of the risks in their respective domains, and what their communication, information and reporting lines,andresponsibilitiesareforriskmanagementmatters. Each project domain (such as engineering, software, verification, and schedulecontrol)managestherisksemanatingfromitsdomainorbeing assignedtoitsdomainfortreatment,underthesupervisionoftheproject manager. Risksareformallyacceptedbythenexthigherlevelresponsibilitywithin thecustomer/supplierchain.
b.
c.
22
ECSSMST80C 31July2008
6.3
f.
6.4
b.
c.
6.5
b.
c.
23
ECSSMST80C 31July2008
project. The database is a living document, and is maintained current. Extractsfromthedatabasearepresentedatprojectmeetings,reviewsand milestones as required by the risk management plan. Items to be candidatesforlessonslearnedareidentified.Thedatabaseisaccessible toactorsasappropriate. NOTE For example: the risk management database should support the efficient and effective management of critical areas of a program/project by: demonstrating that the risk management process is conducted in accordance with the definedprocessforprojectriskmanagement; providingevidenceofasystematicapproachto riskidentificationandassessment; providingarecordofrisks; providing the decision makers with sufficient plansforapproval; facilitating continuing monitoring and review ofriskstatus; providingtraceability; sharing and communicating informationwithinprojectactors; required
It includes all technical assessment by the various disciplines, as well as programmatic data. Example forms for the registration and ranking/logging of risk items are presented in AnnexDtothisStandard.
24
ECSSMST80C 31July2008
7.2
7.2.2
a. A risk management plan shall be established by each supplier in conformancewiththeDRDinAnnexB. NOTE The aim is to assemble in a single document all elements necessary to ensure implementation of a
25
ECSSMST80C 31July2008
risk management commensurate with the project domains, organization, and management, while meetingcustomerrequirements.
7.2.3
a. Riskscenariosshallbeidentified. NOTE Theaimistoidentifyriskscenariosinastructured way for all domains (such as management, engineering, software, test, and operations), using availableinformationsourcessuchas: previous analysis, historicaldata; dataextrapolation; simulations,testdata,andmodels; detailed safety and dependability analysis (see ECSSQST30andECSSQST40); analysis of all work breakdown structures and levels; comparisonofgoalsandplans; analysisofresources; analysisofsuppliers; analysisofproposedchanges; testresults; nonconformancereports; timeframeconsideration; criticality of technology and availability of backupsolutions. lessons learned, and
expertinterviewsandexperiencedata;
7.2.4
a. Theriskscenariosshallbeassessed. NOTE The aim is to facilitate understanding and comparison of the identified risk scenarios by applying the scoring method and scheme defined intheriskmanagementpolicy.
7.2.5
a. Theriskscenariosshallbeanalysedfortheiracceptability. NOTE1 Inthecontextofriskmanagement,acceptancecan meanthateventhoughariskisnoteliminated,its existence and magnitude are acknowledged and tolerated.
26
ECSSMST80C 31July2008
NOTE2 The aim is to identify acceptable risks, which are not subject to risk reduction, and unacceptable riskssubjecttoriskreduction.
7.2.6
a. Risksshallbereducedinaccordancewiththeriskmanagementpolicy. NOTE The aim is to reduce unacceptable risks to an acceptable level applying methods aiming at reducing the probabilities or severity of risk scenarios, or reducing the uncertainties in risk data,applyingmeasuressuchas: modification of requirements or business agreement; changeofdesign,baseline,orprojectstructure; introduction of failure tolerance in accordance withECSSQSTdocuments; acquisition of additional redirectionofresources; augmentationoftestoranalysis. resources or
7.2.7
a. The overall risk after consideration of the risk reduction shall be determined. NOTE Theaimistogainanunderstandingoftheimpact ofpotentialriskmitigationactions.
7.2.8
a. Optionsforacceptanceofresolved,acceptableandoverallrisksshallbe defined where appropriate and presented to the appropriate management level, as defined in the risk management plan, for disposition. NOTE The aim is determination and implementation of theappropriateriskresolutionoptions.
7.2.9
a. Unresolved risks shall be presented to the appropriate management level,asdefinedintheriskmanagementplan,forfurtherdisposition. NOTE Theaimistoarriveatadispositionofunresolved risks at the management level defined in the risk managementplan.
27
ECSSMST80C 31July2008
7.2.10
a. Residualrisksattheendofariskmanagementcycleshallbesubmitted totheappropriatemanagementlevel,asdefinedintheriskmanagement plan,foracceptance. NOTE The aim is formal acceptance of residual risks at theappropriatemanagementlevel.
7.2.11
a. Risks shall be monitored, communicated, and results shall be displayed inconformancewithriskassessmentreportDRD,AnnexC. NOTE The aim is to ensure complete and systematic controloftheimplementationofriskmanagement activities.
7.3
7.3.2
a. Riskmanagementshallbeimplementedinacosteffectivemanner,using theexistingprojectorganizationtothemaximumextent. NOTE Theaimistoestablishacoherentriskmanagement structure, integrated into the project organization, withaviewtoobtainingbenefitsthatoutweighthe costofriskmanagementimplementation.
7.3.3
a. Theriskmanagementprocessshallbemonitored. NOTE The aim is to provide visibility of the risk managementprocesswithintheorganization.
28
ECSSMST80C 31July2008
7.3.4
a. Lessonslearned exercise on the risk management process shall be performed. NOTE The aim is continuous improvement of the risk managementprocess.
7.3.5
a. Recognized improvements to the risk management process shall be implementedwiththeprojectprogress. NOTE The aim is to improve the risk management process.
29
ECSSMST80C 31July2008
ThisDRDiscalledfromECSSMST80,requirement7.2.1a.
A.1.2
The objective of the risk management policy document is to describe the objectivesandprinciplesofriskmanagementinthecontextoftheprojectandto giveahighleveloutlineofhowweperformriskmanagement,andwhatarethe criteriaforclassificationandacceptanceofrisks.
A.2
Expected response
A.2.1
<1>
a.
The introduction shall describe the purpose and objective of the risk managementpolicydocument.
<2>
a.
Applicableandreferencedocuments
The risk management policy document shall list the applicable and referencedocumentsinsupporttothegenerationofthedocument.
<3>
a.
Resources
The risk management policy document shall describe the set of project resources that are affected by risk and thereby have an impact on the projectobjectives.
30
ECSSMST80C 31July2008
<4>
a.
Projectgoalsandresourceconstraints
The risk management policy document shall describe the project objectives and the resource constraints of the project and name the projectscriticalsuccessfactors.
<5>
a.
Riskmanagementstrategyandapproach
Theriskmanagementpolicydocumentshallprovideanoverviewofthe riskmanagementapproach,toincludethestatusoftheriskmanagement effort, and a description of the project risk management strategy consistentlyderivingfromtheprojectsobjectives. Margins should be stated and if relevant the apportionment of risk betweencustomerandsupplier.
b.
<6>
a.
Rankingschemeforriskgoals
The risk management policy document shall contain the definition of a ranking scheme for risk goals according to the requirements of the project.
<7>
a.
Scoringschemes
Theriskmanagementpolicydocumentshallstatethescoringschemesfor the severity of consequences and the likelihood of occurrence for the relevanttradableresources,e.g.asproposedinthestandard.
<8>
a.
Riskindexscheme
The risk management policy document shall contain the description of themethodortoolbywhichthemagnitudesofrisksofthevariousrisk scenariosaredenoted.
<9>
a.
Actioncriteria
The risk management policy document shall state the criteria to determinetheactionstobetakenonrisksofvariousmagnitudesandthe associatedriskdecisionlevelsintheprojectstructuree.g.asproposedin thestandard.
<10>
a.
Individualriskacceptance
The risk management policy document shall describe the acceptance criteriaforindividualrisks.
<11>
a.
Rankingandcomparisonofrisks
Theriskmanagementpolicydocumentshalldescribethemethodforthe ranking and comparison of identified risk items where the ranking reflects on the potential direct consequence and impact of the risk to otherriskareasorprocesses.
31
ECSSMST80C 31July2008
<12>
a.
Overallrisk
The risk management policy document shall state the definition of the overallprojectrisk,itsmeasurementmethodandmethodofacceptance.
<13>
a.
Communication
The risk management policy document shall describe the strategy and the formats for communicating riskdata to the decision makersand for monitoringtherisks. An escalation strategy should be described addressing how the information associated with each element of the risk management process is determined and made available to the participants in the process.
b.
<14>
a.
Riskmanagementprocessandprocedures
The risk management policy document shall describe the risk management process to be employed i.e. the review, decision and implementation flow within the project concerning the risk planning, identification, assessment and identification, handling, monitoring and documentationfunctions. The risk management policy document shall provide application guidance for each of the risk management functions in the process allowing the projects risk management organization flexibility while ensuringacommonandcoordinatedapproachtoriskmanagementand the coherence of the responsibilities and interfaces within the risk managementprocess.
b.
A.2.2
a.
Special remarks
TheresponsetothisDRDmaybecombinedwiththeresponsetotherisk managementplanDRD,ECSSMST80AnnexB.
32
ECSSMST80C 31July2008
ThisDRDiscalledfromECSSMST80,requirement7.2.2a.
B.1.2
Theobjectiveoftheriskmanagementplanistoprovideinasingledocumentall elements necessary to ensure that the implementation of risk management commensuratewiththeproject,organization,andmanagement,whilemeeting customerrequirements.
B.2
Expected response
B.2.1
<1>
a.
The introduction shall describe the purpose and objective of the risk managementplan.
<2>
a.
Applicableandreferencedocuments
The risk management plan shall contain the list of applicable and referencedocuments,usedtosupportthegenerationofthedocument.
<3>
a. b.
Organization
The risk management plan shall describe the risk management organizationoftheproject Theriskmanagementplanshalllisttheresponsibilitiesofeachoftherisk managementparticipants.
33
ECSSMST80C 31July2008
<4>
a.
Riskmanagementpolicy
The risk management plan shall contain a link to the applicable risk managementpolicydocument.
<5>
a.
Riskmanagementdocumentationandfollowup
Theriskmanagementplanshalldescribethestructure,therulesandthe proceduresusedtodocumenttheresultsoftheriskmanagementandthe followupprocess.
<6>
a.
Projectsummary
Theriskmanagementplanshallcontainabriefdescriptionoftheproject, includingtheprojectmanagementapproach.
<7>
a.
Descriptionofriskmanagementimplementation
The risk management plan shall describe how the risk management processisimplemented.
<8>
a.
Riskidentificationandassessment
The risk management plan shall describe the identification and assessment process and procedures for examining the critical risk items and domains, and processes to identify and document the associated risks. Theriskmanagementplanshallsummarizetheanalysisprocessforeach of the risk domain leading to the determination of an overall risk assessment. The risk management plan should include the identification of specific metricsforriskassessment. Theriskmanagementplanmayinclude: 1. 2. 3. 4. 5. Overviewandscopeoftheidentificationandassessmentprocess; Sourcesofinformation; Informationtobereportedandformats; Descriptionofhowriskinformationisdocumented; Assessmenttechniquesandtools.
b.
c. d.
<9>
a. b.
Decideandact
Theriskmanagementplanshalldescribetherisktreatment,whichuses theriskassessmentreportasinput. Theriskmanagementplanshouldspecifythecriteriaofriskacceptance beyond the risk management policy document and mitigation actions thatcanbeusedtodetermineandevaluatevariousriskhandlingoptions.
34
ECSSMST80C 31July2008
c. The risk management plan should identify tools (i.e. name, version and date)thatcanassistinimplementingtheriskdecisionandactingprocess.
<10>
a.
Riskmonitoringandcommunication
Theriskmanagementplanshalldescribetheoperationalapproachthatis followedtotrack,monitorupdateiterateandcommunicatethestatusof thevariousrisksidentified. The risk management plan should provide criteria for the selection of risks to be reported on, identify the reports to be prepared; specify the format;andassignresponsibilityfortheirpreparationandthefrequency ofreporting. Operational escalation procedures should be stated in this clause ensuring a sufficient alert system and a structured manner of communication.
b.
c.
B.2.2
a. b.
Special remarks
TheresponsetothisDRDmaybecombinedwiththeresponsetotherisk managementpolicydocumentDRD,ECSSMST80AnnexA The response to this DRD may be combined with the response to the projectmanagementplan,asinECSSMST10.
35
ECSSMST80C 31July2008
ThisDRDiscalledfromECSSMST80,requirement7.2.11a.
C.1.2
The risk assessment report is the basis for communicating the identified and assessedrisks,aswellasthesubsequentfollowupactionsandtheirresults.
C.2
Expected response
C.2.1
<1>
a. 1. 2. 3.
Theassessmentreportshallintroducethefollowingitems: Thepurposeandobjectiveoftheriskassessmentreport; Abriefdescriptionofwhatwasdoneduringtheidentificationand assessmentexercise,anditsoutcome; Identification of organizations that contributed to the preparation ofthedocument.
<2>
a.
Applicableandreferencedocuments
The risk assessment report shall contain the list of applicable and referencedocuments,usedtosupportthegenerationofthedocument.
<3>
a.
Overview
The assessment report shall briefly describe what was done during the identificationandassessmentexercise.
36
ECSSMST80C 31July2008
<4>
a.
Methodofassessment
The assessment report shall describe how the risks in question were identified, which inputs, method, tool(s) were used, and which people wereinvolved.
<5>
a.
Principle
The assessment report shall describe the basics of the identification and assessmentmethod(e.g.interviewingmethod),includingthejustification forthemethod(s)selected.
<6>
a. b.
Consolidation
The assessment report shall describe the consolidation approach for the overallriskassessment. Theassessmentreportshallemphasizeitemsofconflictandhighlightthe decisionsthatweretakenforconsiderationintheoverallassessment.
<7>
a.
Assessment
The assessment report shall give an appraisal of identified individual risksandtheoverallprojectrisk.
<8>
a.
Comparisonwithearlierassessments
Theassessmentreportshalldescriberesultsofthefollowupactionsthat weretakenincomparisonwithearlierassessment(s).
<9>
a.
Conclusions
The assessment report shall describe the conclusions drawn from the identification and assessment, including any statements for future assessmentsandfollowupactions.
<10>
a. 1. 2. 3. 4. 5.
Annexes
Theassessmentreportshallcontainthefollowinginformation: riskregister(seeECSSMST80,AnnexD); rankedrisklog; ratingscheme; overallriskrating; otheranalysis.
C.2.2
None.
Special remarks
37
ECSSMST80C 31July2008
Annex D (informative) Risk register example and ranked risk log example
38
RISKSCENARIOandMAGNITUDE
No. Riskscenariotitle:
Causeandconsequence:
Severity(S)
Negligible 1 Significant 2 Major 3 Critical 4 Catastrophic 5 Minimum A Low B
Likelihood(L)
Medium C High D Maximum E
Riskindex
RED
(*)
YELLOW
(*)
GREEN
(*)
Riskdomain
(**)
RISKDECISIONandACTION
Acceptrisk Riskreductionmeasures: Action: Agreedbyprojectmanagement: Name:Signature: Date: Notes
(*)MarkboxasappropriateforthevalueofR(riskindex),accordingtothecriteriadefinedintheriskmanagementpolicy. (**)Indicateriskdomain(e.g.technical,costorschedule).
39
ECSSMST80C 31July2008
Project: Rank No. Organization: Riskscenariotitle
Red (*) Yellow (*) Green (*)
Actionsandstatus
40
ECSSMST80C 31July2008
E.2
ECSS-M ST-Standards
ECSSMST10,:
Partitioning the project into technical and manageable elements ensuresthatitemsortasksatriskcanbeunambiguouslyidentified andallocated,andinterfacescontributingtoriskidentified. Partitioningtheprojectintophaseswithreviewsatcriticalproject stagesprovidessignificanteventsforreviewingtheidentifiedrisks and eventually assessing new risk scenarios evolving with the project progress, applying the risk assessment policy adopted for theproject.
ECSSMST40:Theconfigurationandinformationmanagementensures that all documentation and data of relevance for the risk management processareavailableandcontrolledinasystematicmanner. ECSSMST60: Controlling the schedule and cost of the project ensures that deviations with a bearing on identified risks are detected and remedied,orthatriskscanbereassessedinthelightofthesedeviations. ECSSMST70: The logistics support analysis contributes to risk management by providing the data underlying the assessment of risks influenced by operations, maintenance and disposal of the project hardwareandsoftwareitems.
E.3
ECSS-Q Standards
ECSSQST10, ECSSQST20: The control over product quality ensures that the products affected by risk management are controlled to meet theirspecifications.
41
ECSSMST80C 31July2008
ECSSQST30, ECSSQST40: The dependability and safety related activitiesapplywhererisksarelinkedtodependabilityandsafety. ECSSQST60, ECSSQST70: The choice of EEE components, material, mechanicalpartsandprocessesinfluencethefunctionanddependability ofthedesignandhavethereforeanimpactonrisks. ECSSQST80: The correct functioning of software has an influence on risksrelatedtothefunctioningofthesystem.
E.4
ECSS-E Standards
ECSSEST10: The engineering and system engineering processes provide a breakdown of engineering activities into manageable and controllable entities, and the demonstration of achievement of the customerstechnicalrequirements.Theyareessentialforidentifyingand assessing technical risks, and the verification of requirements with a bearingonrisk. ECSSEST20 to ECSSEST70: The design of electronic and electrical, mechanical, communications, control and ground support systems and theirsoftwareaswellasoftheoverallsystemsoftwarehasaninfluence onrisksrelatedtothefunctioningofthesystem.
42
ECSSMST80C 31July2008
Bibliography
ECSSSST00 ECSSMST40 ECSSMST60 ECSSMST70 ECSSQST10 ECSSQST20 ECSSQST30 ECSSQST40 ECSSQST60 ECSSQST70 ECSSQST80 ECSSEST10 ECSSEST20 ECSSEST40 ECSSEST50 ECSSEST70
ECSSsystemDescription,implementationand generalrequirements SpaceprojectmanagementConfigurationand informationmanagement SpaceprojectmanagementCostandschedule management SpaceprojectmanagementIntegratedlogistic support SpaceproductassuranceProductassurance management SpaceproductassuranceQualityassurance SpaceproductassuranceDependability SpaceproductassuranceSafety SpaceproductassuranceElectrical,electronicand electromechanical(EEE)components SpaceproductassuranceMaterials,mechanical partsandprocesses SpaceproductassuranceSoftwareproduct assurance SpaceengineeringSystemengineeringgeneral requirements SpaceengineeringElectricalandelectronic SpaceengineeringSoftwaregeneralrequirements SpaceengineeringCommunications SpaceengineeringGroundsystemsandoperations
43