Академический Документы
Профессиональный Документы
Культура Документы
Prensa Presented by Antonio , MBA, PMP, CCP, CSTE for Project Management Institute Puerto Rico Chapter
June 20, 2002 San Juan, Puerto Rico
"I believe that this nation should itself to achieving a commit goal, before this decade is out, of landing a May 27,1961 man on the moon..." - John F. Kennedy,
On July 20, 1969, just eight years after Kennedy's speech, Apollo 11 landed two men on the moon. This achievement was possible only with careful NASA used the critical path method to production planning that included the help determine an critical path efficient schedule for the tasks that method. led to the moon landing.
Discussion Topics
Background Some questions about the project What is the Critical Path Method (CPM)? Why the CPM? How to use the CPM ? Questions and Answers
Background
The critical path method (CPM) was invented by project managers in the early 1950's. The US Navy adapted and improved it to manage the Polaris missile project in the late 1950's
6 8
Task ID
Duration
Dependency
A B C D E F G H
7 3 6 3 3 2 3 2
A B D, F B C E,G
7 13
(7)
13
G
(3 )
16
(6)
S
0
1 6 9
H (2
)
18
B (3)
D
(3 )
(3)
(2 )
S
0 7
(7) 13
7 13 7
7 7
13
G
( 3 ) 6 6 13
16 16 1 6 1 6
(6) 13
H
(2 )
18 18
B
( 3 )
3 10 (3)
3 10
D F
13
9 16
(3)
3 1 1
5 13
( 2 )
A 0
7 7
7 7
(7)
S
0 7
13 13 (6) 13 13
C 0
G 0
6 6 13 ( 3 )
16 16 16
16 (2) 9 16
18
B
( 3 )
3 10
3 1 0 3 1 1
D
( 3 )
13
18
(3)
7
( 2 )
5 13
Summary
Critical Path Analysis is an effective and powerful method of assessing: Tasks which must be carried out Where parallel activity can be carried out The shortest time in which a project can be completed Resources needed to achieve a project The of activities, scheduling, and timings involved sequence Task priorities
Contact me at:
Antonio Prensa
Email: aprensa@bppr.com / tonyprensa@prtc.net Phone: (787) 751-9800 ext. 3725