CIVIL ENGINEERING
SCOPE OF WORK
Selection of Pump Station Location Selection of Sewer Route Selection of Pump Selection of Pipe Size Design of Pump Station
DESIGN OF CONSTRAINTS
Economics - Stay within the allotted budget Environmental - Fabric Fencing - Deforestation Sustainability - Limiting the number of pump starts Construction Ability - Thrust Blocks - Wet Well Aesthetic Safety - 100 year flood elevation - authorized access only
DESIGN ALTERNATIVES
Different Routes
Route 1
Pipe Length Total Deforestation 6200 ft 0 ft2
Route 2
5800 ft 7800 ft2
DESIGN ALTERNATIVES
Various Pumps
Kinetic Displacement Positive Displacement
DESIGN CRITERIA
MDEQ Standards:
Minimum pipe size of 4 Minimum depth of 3 for buried pipe Minimum of 2 pumps Minimum velocity of 0.6m/s Maximum of 10 successive starts per hour for each pump 12 continuous exchanges or 30 intermittent exchanges of ventilation
METHODOLOGY
Flow Rate
Fixtures Toilets
Urinals Sinks Showers Fountains
No. of Fixtures 17
4 11 15 7
METHODOLGY
Total Head
Energy Equation
1 1 2 2 2 2 + 1 + 1 + = + 2 + 2 + + 2 2
Friction Head Loss Minor Loss
2 = 2
Pump Head Loss
2 2
= 2 1
2 + 1+ 2
System/Pump Curve
Retention
Successive
DESIGN
Control System
COST ESTIMATE
Pipe Materials Wet Well and Concrete Materials Materials Cost Installation Cost
PIPE MATERIALS
Pipe Diameter
4" 6" 10"
Unit Cost
$5.78 $9.74 $17.72
Total Cost
$36,389 $61,349 $111,636
Description
4" PVC Elbows Clamps Delivery
Unit
ft each each
Quantity
6300 12 350
Unit Price
$5.78 $9.74 $3.73
Total
$36,389 $117 $1,306 $1,891 $39,702
Unit
yd3 yd3 each ft yd3
Quantity
1.57 32.99 1.00 200.00 13.50
Unit Price
$396.00 $396.00 $75.00 $6.75 $396.00
Total
$622 $13,063 $75 $1,350 $5,346 $20,456
MATERIALS
Description
Pump Controls Fabric Fence Sodding Seeding & Mulching
Unit
each each ft yd2 yd2
Quantity
2 1 6500 100 .20
Unit Price
$7500.00 $850.00 $3.50 $7.15 $1781
Total
$15,000 $850 $22,750 $715 $356 $39,671
Unit
hr
hr
Quantity
500
750
Unit Price
$45.00
$25.00
Total
$22,500
$18,750 $41,250
$159,546
PROJECT SCHEDULE
Task Meeting with Tramone at WGK Design Constraint Surveying Design Proposal & Presention Methodoloy Pipe Selection Pump Selection Foundation Design Wet Well Design Design Completion 9/15/2012 10/1/2012 10/15/2012 11/1/2012 11/15/2012 12/1/2012 12/15/2012 1/1/2013 1/15/2013 2/1/2013 2/15/2013 3/1/2013 3/15/2013 4/1/2013
ACKNOWLEDGE
Dr. Yadong Li P.E., Faculty Advisor Mr. Tramone Smith P.E., WGK, Provided of Plans
QUESTIONS ?