Вы находитесь на странице: 1из 20

Presented By:

Anusha Bansal Himani Wadhwa Madhav Dixit Priyanka Khatri

Ranjeeta Kumari

CASE SUMMARY
Marriage date: 22 April Start Date: 31st March Remaining Days: 23 days Remaining Days for wedding rehearsal: 21 days So as to complete the activities in given schedule, we have to pay cost, called as crash cost to complete it in given time called crash time.

THE ACTIVITIES AND PRECEDENCE RELATIONSHIPS

Activity Book church & Reception Notice church Decorate church Made of Honour Reach Choose Cake Catering Choose Dress Pattern Dress Material Sewing Dress Final fitting dress Cleaning Dress Choose Invitation Style Invitation print Guest list preparation Addressing Invitation Mailing Invitation Invitation reach to guest Gift for Bridesmaids Wedding Rehearsal Wedding

Name A B C D E F G H I J K L M N O f Q R S T

Precedence A B E G H D,I J L N,M O P C,F,K,Q,S S

Days Crash days Crash cost Per day CC 1 17 10 100 14.28 3 10 2 500 62.5 2 10 3 8 5 25 8.33 11 6 120*5 120 2 2 1 30 30 3 12 5 35 5 4 4 2 25*2 25 1 10 1 1 1

NETWORK DAIGRAM FOR THE WEDDING PLANS

A 10 D
3 2
3

17

B H F
M

C
2

Before Crashing

2 22

K
26

22

21

G E
L N

8 10
12

11

I
1

S
30

12
4 10

Q
1

4 1

A 10 D
3 2
3

17 2

B H F
M

C
2

After Crashing

2 18

K
12

21

G E
L N

8 10
12

5 11

10

21

I
O
2 1

S
21

5 4

10

Q
1

4 1

THE MINIMUM-COST PLAN THAT MEETS THE APRIL 22 DATE


Activity
Invitation Print

Activity Name
M

Crashed Days
5

Total Crash Cost


$35

Material
Cleaner downtown

H
K

5
1

$ 25
$ 30

Using 3rd party


Sewing Dress Total Cost

O
I

2
1

$ 50
$ 120 $ 260

WEDDING PLANS OF EACH INCIDENTS NOTED IN CASE (B)

Question. 1
On April 1 the chairman of the Vestry Committee at the church was left unimpressed by the added donation and sais he would not reduce the notice period from 17 to 10 days.

Answer
There will not be any changes or problem, as this path is of exactly 21 days i.e. the time required for wedding, without crashing any activity.

Ans 1 Path

A 10 D
3 2
3

17 2

B H F
M

C
2

After Crashing

2 18

K
12

21

G E
L N

8 10
12

5 11

10

21

I
O
2 1

S
21

5 4

10

Q
1

4 1

Question. 2
A call to Guatemala revealed that the potential bridesmaid had several commitments and could not possibly leave the country until April 10

Answer
Normally, the bridesmaid requires 10 days to reach. If she cannot leave before April 10, that means 10 + 10 days extra + 2 days dress fitting + 2 days dress cleaning = 24 days. Even if we crash dress cleaning activity (i.e. 1 day crash) still itll be 23 days whereas it should be 21 days before rehearsals. So, no use crashing this activity. Therefore, well have to fly the bridesmaid in 2 days, thus incurring $500 cost.

Ans 2 Path

A B 2 10 +10 loss D
3 2
3

17

C
2

After Crashing

2 18

G E
L N

8 10
12

H F
M

5 11

10

K 14
12 21

21

I
O
2 1

S
Q
1

5 4

10

4 1

Question. 3
Mother came down with four day flu just as she started on the guest list.

Answer
If her mother came down with flu, the guest list preparation activity will require 4 + 4 days extra. Thatll make the total time of the path to be 23 days. The addressing activity will have to be crashed to 2 days instead of 4 days incurring $25 cost. Thus, the path time will become 21 days.

A 10 D
3 2
3

17 2

B H F
M

C
2

After Crashing

2 18

K
12

21

G E
L N

8 10
12

5 11

10

21

I
O
2 1

S
21

5 4

10

Q
1

Ans 3 Path

4 1

+4 loss

Question. 4
The lace and dress materials were lost in transit. Notice of the loss was delivered to the Jackson home early on April 10.

Answer
After April 10, the family has 11 days to complete the remaining activities. If material procuring activity be crashed to 5 days, sewing dress to 6 days, dress cleaning to 1 day, itll still be 5+6+1+2 = 14 days. Therefore, the wedding wont be able to take place by April 22. Eloping is the only option.

A 10 D
Ans 4 Path

17 2

B H F
M

C
2

After Crashing

+10 loss

2 18

3 2
3

G E
L N

8 10
12

5 11

K 27
12 21

21

I
O
2 1

S
Q
1

5 4

10

4 1

Question. 5
There was small fire at the caterer's shop on April 8. It was estimated that the shop would be closed two or three days for repair.

Answer
This path requires 12 days, so a delay of 2-3 days wont affect the proceedings at all.

A 10 D
3 2
3

17 2

B H F
M

C
2

After Crashing

2 18

21

G E
L N

8 10
12

5 11

10

21

I
O
2 1

S
21

Ans 5 Path

+2/3 loss

14/15
10

5 4

Q
1

4 1