Вы находитесь на странице: 1из 52

Overpressure Scenarios and Required Relief Rates PART I

Required Data
Procure latest PIDs Heat and Mass Balance Report Rotating Equipment Datasheet (performance curves, etc.) Vessel and Heat Exchanger Datasheets (drawings) Operating/Emergency procedures Review current project specific document-Relief & Blowdown Philosophy

Overpressure Scenario Identification


Start with PIDs and PFDs Analyze on equipment-by-equipment basis Typically start at front end of process Identify sources of feed & its maximum pressure Identify all heat input sources including external fire No credit for favorable instrument or operator response Include comments to explain rationale

Industry Guidelines
API RP 521 API 2000

Project Specific Guidelines

API RP 521
1. Fire 2. Closed outlets (Vapor BO or Liquid BO) 3. Failure Opening/closing of Control Valve

4. Thermal Expansion
5. Tube rupture 6. Check Valve Leakage 7. Reflux failure 8. Abnormal heat input 9. Power Failure 10. Utility failure (CW+IA+FG+Steam)

External Fire

Causes: 1.Explosion caused by the ignition of a flammable leaking gas 2. Leakage of flammable hydrocarbon inventory

Applicability Guidelines
Equipment must be located with in a fire zone Some portion of the equipment must be located below the maximum fire height (API RP 521 uses 25 feet) In some cases, the time required to reach relief pressure may render the scenario not credible

Sizing EquationQ=21000*F*A^0.82 (Btu/hr) Q=34500*F*A^0.82 (Btu/hr) Wetted Surface Area Liquid full such as Treaters: 100%

Surge Drums, KO drums, Process vessels: NLL


Fractionating Columns: NLL + Hold up Working storage (MAWP >15 psig): Max level up to 25 ft

Spheres: Up to max horizontal diameter or 25 ft whichever is greater


Heat Of Vaporization-Latent heats will be based on the heat required to vaporize the first 10% by mass. Q = m * Hv@ relief

Shell and Tube Exchangers


Individual exchangers often not individually protected for fire Often rely on downstream vessels for protection If downstream relief is used, check if loads should be additive (e.g., exchanger and vessel are in same fire zone) Shell side and tube side may be treated differently (many companies neglect tube side due to small surface area)

Air Coolers
Condensing versus liquid cooling services may be treated differently (see API RP 521 Section 3.15.7) Many air coolers are located above the maximum fire height API has special equations for air coolers Exact treatment of fire case for air coolers should be defined in the Project Guidelines

Filters, Strainers, etc.


Equipment less than 24 OD is exempt from ASME VIII (and typically fire relief requirement) Many companies have additional exclusions for small filters Equipment fabricated from pipe may be treated differently than ASME stamped equipment Often rely on downstream equipment for relief check Project Guidelines on rules to use

Inlet Control Valve Failure:Causes-

Instrumentation failure may occur due to


-Transmission signal failure -Process Measuring element failure Mechanical failure may occur due to -Stem breakage -Plug jamming -Misoperation May result in control valve opening or to move in opposite direction of its design failure position.

Determining Applicability
Trace all inlet lines to vessel to identify inlet control devices Trace upstream from any control devices to determine maximum expected upstream pressure Upstream pressure will be normal or maximum operating pressure Can selected upstream pressure exceed downstream equipment design pressure? Consider relative vessel volumes when the upstream volume is much less than the downstream volume

Glycol Contactor
PSV-1 @ 750 psig Dry Gas

Glycol Flash Tank

HC Vapors 200 psig Lean Glycol

Wet Gas 675 psig

Vapor

Vapor
LC

Liquid
LC

Liquid
LV
LV

Rich Glycol

Glycol Contactor
PSV-1 @ 750 psig Dry Gas

Glycol Flash Tank

HC Vapors 200 psig Lean Glycol

Wet Gas 675 psig

Vapor

Vapor
LC

LC

Liquid
LV

Fails Open

Liquid

LV

Rich Glycol

Glycol Contactor
PSV-1 @ 750 psig Dry Gas

Glycol Flash Tank

HC Vapors 200 psig Lean Glycol

Wet Gas 675 psig

Vapor

Vapor
LC

LC

Liquid
LV

Fails Open

Liquid

LV

Rich Glycol

API RP 521 Section 3.10.3

The scenario to consider is that one inlet valve will be in a fully opened position regardless of the control valve failure position. Therefore, the required relief capacity is the difference between the maximum expected inlet flow and the normal outlet flow adjusted for relieving conditions and considering unit turndown

Determining Required Relief Rate


Use control valve manufacturers calculations Determine valve flow coefficients Consider partially or fully open bypass Calculate flow across control valve at downstream relief pressure

Take credit for normal outflow in volumetric terms

Gas Blowby Special Considerations


Potential for Two Phase Relief in Downstream Vessel Perform relative inventory check to determine how much downstream vessel will fill

Assume downstream level control remains in normal position


Relief behavior depends on liquid level Below inlet nozzle all vapor relief Between inlet nozzle and full, perform disengagement calculation vapor or two phase Full liquid displacement equal to volume of incoming vapor

Check Downstream Fill Level


Overfill Liquid Displacement

Inlet from LC Valve

Potential Two Phase Vapor


All Vapor Venting
LC

Normal Level

LV

Gas Blowby Special Considerations


Calculating Flow Across Level Control Valve Consider assuming two phase flow across valve to reduce relief requirement

Heat Exchanger Tube Rupture


Causes:
Vibration, corrosion, erosion, thermal shock, differential shell side to tube side expansion (fixed tube sheet exchanger), brittle fracture potential, tube to baffle chafing, degradation of tubes and tube sheets.

High Pressure

Low Pressure

High Pressure

Low Pressure

Corrosion of Tube

High Pressure

Low Pressure

Corrosion of Tube Pinhole Leak

High Pressure

Low Pressure

Corrosion of Tube Tube Failure

Low Pressure on Tube Side

Low Pressure

High Pressure

Corrosion of Tube Tube Failure

Determining Applicability
1. Determine maximum high-pressure side pressure (Phi) Design Pressure

relief device set pressure


other mechanical limitation

2. Determine low-pressure side test pressure along with associated equipment and piping (Plow) Compare the two pressures If (Phi) > (Plow) then tube rupture relief is required

Not generally applied to double pipe exchangers or other types of exchangers with schedule pipe for tubes

API 521 Section 3.18.3


The required rate is determined assuming: Single tube has been broken down. The high-pressure side fluid is assumed to flow through the broken tube. This is often simplified by conservatively estimating the flow rate based on two orifices/one orifice. If there is flash across the broken tube then two phase flow needs to consider. Use Cranes equations based on maximum pressure on high pressure side and relief pressure on low side.

Additional Considerations
Relief fluid properties are generally not the same as those upstream of the tube rupture:

- Flashing across tube rupture


- Heating due to contact with hot side fluid - Displacement of low-pressure side fluid For high pressure differentials, dynamic analysis is sometimes applied

Blocked Outlet (Vapor Or Liquid)


CausesInstrumentation System failure may occur -Transmission signal failure -Process Measuring element failure

Mechanical failure may occur due to -Stem breakage -Plug jamming -Manual valve mal operation
May result in control valve/block valve to move in closed position.

Determining Applicability For Blocked Vapor


Identify potential mechanism resulting in blockage Identify sources of overpressure include compressors, high-pressure supply headers, and process heat

Flash Drum-Blocked Vapor


PSV-1 @ 200 psig Dry Gas

HC Liquid 250 psig CV

Fails Close
Vapor

LC

Liquid
LV

Determining Applicability For Blocked Liquid


Identify potential mechanism resulting in blockage Identify sources of overpressure include pumps, highpressure supply headers. Adequate indication and response time may render overfilling not credible Independent high level alarm 20 minutes of retention after alarm prior to overfill

Often not considered for columns and vessels with no normal liquid inflow (suction scrubbers, etc.)

Flash Drum-Blocked Liquid


PSV-1 @ 200 psig Dry Gas

HC Liquid 250 psig CV

Vapor

LC

Liquid
LV

Fails Close

Required Relief Rates


Centrifugal pumps and compressors Performance curves define flow at relief

PD pumps Use design flow rate

Reciprocating compressors Use reduced volumetric efficiency

High pressure supply headers


Normal inlet flow

Thermal Expansion

Causes:
Hydraulic expansion can result from several causes, the most common of which are the following:
a. An exchanger is blocked-in on the cold side with flow in the hot side.

b. Piping or vessels are blocked-in while they are filled with cold liquid and are subsequently heated by heat tracing, coils, ambient heat gain, solar radiation or fire.

Heat Exchanger Thermal Expansion


o 90 F o 120 F

Cold Side

Hot Side

o 220 F

o 110 F

Cold Side Inadvertently Blocked Prior to Hot Side


o 90 F o 120 F

Cold Side

Hot Side

o 220 F

o 110 F

Cold Side Temperature Increases

o 170 F

Cold Side

Hot Side

q=(Cubic Expansion Coeff.*Q)/(1000*sp.gravity* specific heat capacity)

o 220 F

Is a relief device required?


Guidelines on piping from, Decide Whether to Use Thermal Relief Valves, CEP 12/93; Bravo and Beatty
Yes, for lines more than 80 feet long No, for lines with an ID less than 1.5 No, for lines with high operating temperatures

API RP 521 on exchangers

Locking open a block valve and posting signs may be adequate protection

Check Valve Leakage


Causes-Stuck Open -Broken flapper -Check valve seat leakage May result in overpressure due to leakage through check valve if the maximum normal operating pressure of the highpressure system is greater than the design pressure of vessels present upstream of the check valve.

Check Valve Leakage


- Leakage rate can be assumed equal to the 10% of the maximum normal forward flow (vapor or liquid).

-The reverse flow rate through a single check valve can be determined using the normal flow characteristics (i.e., forward-flow Cv) of the check valve. Leakage rate can be assumed to be 10 % forward flow Cv.

Overhead Condenser Failure, Reflux Failure, Abnormal Heat Input Or Power Failure
CausesUtility Failure, Mechanical failure of rotary equipments, Shutting down of utility compressor, Failure opening of control valve, Pumps or fail closure of control valve on supply line may result in complete loss of a utility or the partial loss of a utility, Instrumentation failure or loss of transformer/MCC/Busbar

Condenser
PC

Overhead (V) Reflux (R)

Accumulator
LC

Feed (F)

Column
Heat in (Q)

Reboiler
LC

Bottoms (B)

Condenser
Overhead (V) Reflux (R)

Loss of Coolant to Condenser


PC

Accumulator
LC

Feed (F)

Column
Heat in (Q)

Reboiler
LC

Bottoms (B)

Loss of Reflux Overhead (V)

Condenser
PC

Reflux (R)

Accumulator
LC

Feed (F)

Process

Column
Heat in (Q)

Reboiler
LC

Steam Bottoms (B)

Determining Applicability
In general, loss of cooling (from condenser or pump-around exchanger) will result in overpressure for distillation systems Loss of reflux can also result in flooding of condenser

In Conclusion
Collect information required to perform analysis Review relevant guidelines Determine all overpressure scenarios that apply to each piece of equipment Analyze required relief rates using standard methods Be conservative at first

Thank You

Вам также может понравиться