Agenda
Review Project Objectives Milestone status & Earned Value Tracking Summary of Results Details of Task Activity Plan Changes Updated Gantt Chart
4/01/2003
Project Objectives
Search for project management templates from the Internet and/or literature. Provide an organized list of templates grouped by web site, process group, and knowledge area. Provide a qualitative evaluation of web sites. Provide recommendations for the list of templates to be included in an appendix of the 3rd edition of the textbook.
Tempting Templates - Status Report #2 3
4/01/2003
Milestones
Status
Task_Name
Kickoff meeting Charter Signed Present Status Report 1 First Version of Report Delivered to Author Present mid-project sponsor status report Present Status Report 2 Final Version of Report Delivered to Author Class Presentation - Remote Teamwork Present final project
Date
2/11/03 2/14/03 2/18/03 3/24/03 3/26/03 4/1/03 4/14/03 4/15/03 4/29/03
4/01/2003
Saved project baseline at beginning of project. Assumed $30/hour labor rate for all team members. Earned value chart shows us as late/over-budget. Real story not that bad.
Have achieved milestones on schedule. We underestimated time commitment We have used all project buffer.
4/01/2003
Tempting Templates Earned Value $9,000 $8,000 $7,000 $6,000 $5,000 Planned Value (PV) $4,000 $3,000 $2,000 $1,000 $0 Earned Value (EV) CV=($2,365) SV=($470) CPI=0.58 SPI=0.87 Actual Cost (AC) EAC $7,745
BAC $5,364
Cost
4/ 03
1/ 03
8/ 03
11 /0
18 /0
25 /0
11 /0
18 /0
25 /0
15 /0
22 /0
29 /0
6/ 03
3/
4/
4/
2/
2/
2/
3/
3/
3/
4/
4/
4/
5/
Days
4/01/2003 Tempting Templates - Status Report #2 6
5/
13 /0
Human Resources
Communications Risk Procurement Total
4/01/2003
13
12 38 4 35 140
4
11 35 12 1 37 106 0 15 15
17
73 50 5 333
7
Distribution of Templates
By Process Group
11% 5% 32% 41% 11%
Closing Planning
4/01/2003
By Knowledge Area
Integration Scope Time Cost Quality Human Resources Communications Risk Procurement
52 70 18 18 30 17 73 50 5 0 50 100
Controlling Initiation
Executing
New York State Office for Technology: Tasmanian State Government: U.S. Department of Energy:
http://www.oft.state.ny.us/pmmp/templates/index.htm
http://www.projectmanagement.tas.gov.au/index.htm http://cio.doe.gov/ITReform/sqse/pm_main.htm
Method 123: http://www.method123.com ProjectWare: http://www.projectware.com.au/pw030.html State of Texas Department of Information Resources:
http://www.dir.state.tx.us/eod/qa/template.htm
Complete details are available from the Tempting Templates web site:
http://webpages.charter.net/hafox/pm/docs/TemptingTemplatesPreliminaryReport.htm 4/01/2003 Tempting Templates - Status Report #2 9
2.
4/01/2003
Goals Individual
1.
Results Individual
1.
2.
Find at least 10 web sites with free templates Find the most number of unique sites not found by other team members
2.
Team
Find at least 20 unique web sites having free templates
Team
35 of 54 web sites had free templates
11
4/01/2003
12 34
4/01/2003
12
15
6 3 2 2
1.
2.
Gather information on at least 100 templates (25 per team member) Find at least 1 template for each valid process group / knowledge area combination
2.
Results 333 free templates examined. Average of 83 per team member. Only 3 processes with no templates found:
4/01/2003
14
Plan Changes
Search activities produced better that expected results. (3x more templates) The contingency plan for additional refocused searches was unnecessary. Redirect activities to focus on a qualitative evaluation of the web sites and review the templates to be included in an appendix of the 3rd edition of the textbook.
Tempting Templates - Status Report #2 15
4/01/2003
4/01/2003
16
4/01/2003
17