Академический Документы
Профессиональный Документы
Культура Документы
PRESENTATION NAME
Pre-commissioning means preparation for commissioning. commissioning of various equipments and systems are pre-commissioning for commissioning of the power plant. It is a pre-requisite for commissioning.
Commissioning means to put the equipment into operation as envisaged. For a thermal power plant commissioning means to set up and optimise all its equipments and systems to get output, efficiency, auxiliary power consumption and emission on sustained basis as envisaged to drive the benefit. For super critical and ultra supercritical plant commissioning would mean higher efficiency of the plant with lower emission level and lower auxiliary power consumption(as compared to sub critical plants ) on sustained basis in order to drive the benefit of elevated steam parameters.
Out put Heat Rate ( Efficiency ) Auxiliary power consumption Emission level Sustained generation
Material
Infrastructure Expertise
ANNEX-1
36 units UMPP
32units SCPP
27960MW
21540MW
Lower pressure drop means lower feed-pump power and lower. through-life energy consumption Other advantages include better turn-down, simpler construction and improved availability.
9Cr-1Mo steel
Overlay coating
HP HP internal casing
9Cr-1Mo steel
9Cr-1Mo steel
Control valves
HIP Rotor
12Cr steel
TECHNOLOGY ISSUES
OTHER ISSUES
Water-wall Cracking
Higher metal temperatures and the use of low alloy steel. Thermal fatigue cracking is caused by the combined action of elevated metal temperatures and thermal cycling. Growth of internal tube deposits, high heat flux, deterioration of fluid-side cooling or external fireside coatings. Slagging and shedding, Soot blowing, water cleaning or other factors may cause thermal cycling
A FLOW RESPONSE CALCULATED FOR VARIOUS HEAT ABSORPTIONS FOR A BOILER WALL CIRCUIT WITH A HIGH MASS FLUX
Slagging
Slagging refers to deposition of solid layers on the boiler tube, formed by sintering. Slagging is quite hard to remove and also (although it is sintered material) the slagging material is usually still a good insulator.
Due to Spiral tube configuration. Inclination of the tubes is thought to increase the propensity of slag and clinker. The higher fireside metal temperatures of supercritical boilers may also contribute to increased slagging.
Welding of dis-similar pieces i.e. two pieces fabricated out of different materials is a difficult process. The difficulty increases when the metals, out of which the pieces to be welded are fabricated, are newly developed and not conventional.
Height of Structure
Convenient and economical height of the boiler structure. The height of the boiler governed, however, by design considerations. The height of the (Chimney) is governed by environmental considerations.
Skilled Manpower
Shortage of enough experience and skill available for the erection and commissioning of a 660 MW/ 800 MW.
G coal is available for thermal power plants. The quality of coal available from domestic sources compares very unfavorably with the quality of coals imported from other countries such as Australia, Indonesia or South Africa.
Problems associated with Indian coal are: Indian coal typically has higher moisture content. This can lead to lower boiler efficiencies than with imported coal. Low volatile matter in Indian coal leads to high-un-burnt carbon loses. Low boiler efficiency due to low CV and high ash content in Indian coals High ash and coal handling costs and milling power lead to high auxiliary power consumption High ash and high silica in the coal leads to higher erosion. Though lower flue gas velocities and provision of shielding plates can reduce erosion, it leads to higher capital costs for the boiler. Indian ambient condition High ambient temperature leads to higher cooling water temperature reducing the achievable condenser vacuum to a maximum of 0.13 bars. This in turn leads to higher steam consumption and a poorer turbine heat rate. High relative humidity leads to more losses in cooling tower
Chemical Cleaning Oil flushing Steam blowing Restoration of system Barring gear Vacuum system check Commissioning of gland sealing system Commissioning of HP/LP bypass system
Steam dumping
OBJECTIVE The objective of this procedure is to chemically clean and passivate the internal surfaces of the steam generating portion (water touched surfaces) and heating surfaces (Economizer) using specified chemicals employing a single step process. This will render the above mentioned surfaces free of mill scale, and other deposits and form uniform & smooth protective layer of magnetite. With this protective layer, the generating surfaces are rendered passive to generate adequate negative potential under the operating pH to resist corrosion.
When the iron concentration in the cleaning solution is constant, it indicates that all the oxides have been dissolved. However, a minimum EDTA(Ethelene Diamine Tetra Acid ) contact period of 6 hours from the time of attaining the required temperature (110 deg. C) shall be allowed.
Completion of pickling process once the EDTA strength and iron concentration level out and reach equilibrium. The system shall be allowed to cool with the ID & FD fans in operation. Open the drum air vents when the pressure reaches to 1 kg / sq.cm.
When the temperature comes down to 95 deg. C, the system shall be drained completely in hot condition to the effluent pit by opening all the drain valves .
The drum surface shall be visually inspected for uniform smooth coating of protective layer. The low point header will be inspected and loose debris if any, will be removed
Hot DM water flushings shall be drained into plant normal drain. The organic spent EDTA chemical solution after the cleaning process is drained into a pit. The pH of the effluent will be in the range of 8.5 to 9.0 and hence no treatment for pH adjustment is required as it would meet the pH requirement for disposal. Compressed air shall be used to destroy the residual Hydrazine & organics and the effluent shall be disposed after aeration for 10 days. (The organic chemical is completely bio-degradable).
To clean and remove any foreign material from the oil system
Completion of oil piping Installation of temporary piping after proper cleaning Cleaning of main oil tank and bearing pedestal Oil throttles in the bearing supply lines must be removed and dummy
provided
Duplex filter element in oil supply line to thrust bearing should be removed initially however it may be installed during final stage of flushing
Use of cotton waste is prohibited for cleaning the oil system. Markin cloth to
be used. For checking the direction of rotation of the oil pumps oil must be filled in the oil tank Provision must be made for stopping the oil pumps from local as well as from UCB Fire fighting arrangement must be available during flushing Arrangement for cleaning the spilled oil should be available before starting the oil flushing. Motor current of the oil pumps specially the auxiliary oil pump should not exceed the rated value.
Oil flushing is considered complete when there is no mechanical impurities and traces of moisture as catched from oil sample. Duplex filter remains clean after 24 hours of flushing. Particle count is also some time used to declare completion of oil flushing.
The function of barring gear is to rotate the shaft at low speed to remove the temporary bend during start up and after shut down to prevent hogging. Barring gear are :
Alignment of rotor train completed Rotors coupled Oil flushing completed Instrumentation inside the bearing pedestals completed. Bearing pedestals boxed up Generator work is completed and generator boxed up. Exciter is coupled. Insulation of generator bearing is checked before generator bearing
ESTABLISH THE LUBE OIL SYSTEM ENSURE LUBE OIL TEMPERATURE AFTER OIL COOLER IS >35 C ENSURE PRESSURE IN ALL BEARING OIL SUPPLY LINE AND FLOW IS SITE GLASSES ENSURE PRESSURE IN SEAL OIL SUPPLY LINE AND FLOW IN SITE GLASSES. ENSURE DIFFERENTIAL PRESSURE REGULATOR IS FUNCTIONING. DC SEAL AND DC LUBE OIL PUMPS ARE ON AUTO START MODE AN CASE OF AC FAILURE SWITCH ON THE SUPPLY TO SUPPLY TO TURBOVISORY.
START JACKING OIL PUMP AND CHECK THE JACKING OIL PRESSURE AN ALL THE BEARINGS . TURN THE SHAFT MANUALLY WITH THE HELP OF MANUAL BARRING GEAR AND CHECK THE FREENESS OF THE SHAFT
MOTIVE OIL CAN BE ALLOWED TO ENTER BARRING GEAR WHEEL CHAMBER BY OPENING THE ELECTRICALLY OPERATED MOTIVE OIL VALVE
JACKING OIL PUMP IS KEPT RUNNING AS LONG AS SHAFT IS TURNING.
TURBOVISORY READINGS.
GENERATOR SEAL OIL TEMPERATURE AND LINER METAL TEMPERATURE. COSTING DOWN TIME FROM FULL BARRING SPEED TO ZERO
HOT REHEAT
HP BYPASS LP BY PASS AUXILIARY STEAM AND PRDS HEADER GLAND SEALING OTHER SMALL BORE LINES
The objective of steam blowing is to remove scales, loose material, iron cuttings etc, that might have been entrapped in Super Heaters, Steam piping, reheaters during manufacture, storage, erection at site. Failure to remove the debris may result in damage to turbine blades. Valves etc.
The steam blowing is done in four stages. Viz Stage 1(1a,1b) Stage 2 (2a & 2b), Stage 3 (3a & 3b) & stage 4. Loop pipes from ESV and IV to turbine are to be taken care for cleanliness before erection and not to be steam blown. Steam blowing is carried out by adopting puffing method for stages 1a, 2a 2b,&3a,3b. in which, boiler pressure is raised to 40 Kg/cm2 and released through a quick opening valve and steam blowing done till the Drum pressure drops from 40 Kg/cm2 to 20 Kg/cm2 Steam blowing for stages 1b & 4 are carried out by continuous method. Steam blowing by continuous method shall be done at 4050% of normal operating pressure of the respective system for period of 20 to 30 minutes. Blowing repeated after a time gap of 2 Hrs.
Stage1a: SH, MSL, ESV, temporary line from ESV to EOTV and EOTV to exhaust with temporary piping will be concluded by observing the indents on the target plate. Stage1b:SH,MSL,Aux PRDS, Atomizing Steam lines & FO heating/tracing lines. Stage 2a SH, MSL, ESV, temporary lines from ESV to EOTV, EOTV to CRH line, CRH lines up to boiler end with temporary exhaust pipe. Tap off lines from CRH for deaerator, , auxiliary PRDS, HP heater 6a & 6b, gland sealing, etc. shall be remain closed/isolated. Stage 2a end point will be concluded by observing the indents on the target plate . Stage 2b : 2a plus HP bypass inter connection, hand operated valve mounted in place of HP bypass valve and CRH lines up to Boiler end with temporary exhaust piping. In this stage 6 to 8 blows will be given through HP bypass to ensure cleanliness of the limb. Boiler MS stop valve will be used for stage 2b. EOTV will be kept closed. Manually Operated Isolation Valves in HP bypass lines will be kept opened fully. Stage 3a : 2a plus reheater, HRHL, IV and temporary pipe. CRH line along with attemperator shall be welded with reheater before start of stage 3a. LP bypass lines shall be blanked during stage 3a. Stage 3a end point will be concluded by observing the indents on target plates .
Stage-3b: Stage 3a plus LP Bypass lines. Stage-4 : 4a) APRDS to Gland seal steam 4b) CRH to turbine extraction line (HPHS &LPHS). 4c) CRH to Extraction 4 to Deaerator 4d) CRH to Deaerator / FST 4e) CRH to HP Heaters.
BLANKING DEVICES ARE INSTALLED IN TURBINE MAIN TOP AND CONTROL VALVES AND SIMILARLY IN ESV
The purpose of steam blowing of all critical piping, the steam blowing valve will be opened at 40 kg/Sq.Cm. and closed at 20 kg/sq.cm drum pressure. All the steam lines are purged as per various stages and it is a standard practice to limit number of blows per day to( 8-10) with an interval of 1-1 hours.
Blowing is carried out during the day and system is left cooling during night
While blowing stage 3a, suitable dummies will be put at LPBP outlet temporary line. Required flange provisions are made in these temporary lines for installation of dummies.
All instruments coming in the steam flow are isolated or removed Temporary pipings are properly supported and insulated Steam exhaust is led to outside building to a safer place so as not to cause damage to equipment or person Steam blowing should be done preferably during day time due to noise pollution
Steam blowing is considered complete when target plate remains clean (2-3) small dots in three consecutive steam blows after overnight cooling.
for stages 1, 2a, & 3a Disturbance factor value at selected locations should be greater than unity.
More than 5 (five) pitting and shall not have any deformed edges. Besides, there shall be no pitting in the rim zone, i.e., area other than central zone Gland steam and other small bore pipings are blown for 1-2 hours and blowing is terminated on visual operation
Disturbance Factor
Steam flow during blowing Steam flow at MCR Sp. Volume of steam during blowing Sp. Volume of steam at MCR Sonic Velocity During blowing x Area x 1 Vb
St. flow in kg/sec KP Vb g Area Vb K P Vb g =M/sec = Sq.M = Cu.m/Kg = Constant = 1.3 = Pressure at the exit pipe = Kg/Sq.m = Sp. Volume =Cu.M/Kg = Acceleration due to gravity = M/Sec2
Sonic Velocity =
normalized
Blanking arrangements are removed and valves restored . Blanks installed during steam blowing for system isolation are
Remote trip from UCB Manual trip from local Low vacuum trip Low vacuum trip -hydraulic Low lube oil pressure Axial shift Over speed striker 1 and 2 Fire protection channel -1 Fire protection channel-2 MOT low level Low lub oil pressure Boiler fire out Main steam temperature low Generator protection
Steam dumping is carried out before steam admission to turbine During steam dumping operation, quality of steam is improved by turbine supplier
Max flow is stabilized through HP/LP by pass with rated steam parameter. Steam dumping is carried out till quality of condensate at CEP discharge is same as inlet to hot well make up.
After steam dumping hot well, deaerator & Boiler drum are drained, clean and inspected before recharging.
GE,s Super Critical/ Ultra Super Critical Steam Turbine. Recommended procedure for commissioning of large steam turbine by BHEL. Analysis of Supercritical technology in Indian Environment and Utilizing Indian coal by Prof: M M Hasan, Mechanical Engineering dept (Jamia Islamiya New Delhi) STEAM TURBINE DESIGN CONSIDERATIONS FOR SUPERCRITICAL CYCLES, Presented by Bechtel Power Corporation, Frederick. Bituminous coal fired large SC Power Plants for the European Market presented by Mr.K. Busekrus(HITACHI) ON 2007 Supercritical technology in Indian presented by NTPC Ltd.
S. No. 1.
No of units 5
2.
3. 4. 5. 6. 7.
UMPP, Sasan
UMPP, Krishnapatnam UMPP, Tilaiya UMPP, Orissa UMPP, Chatisgarh UMPP, Tamilnadu
6
5 5 5 5 5
660
800 800 800 800 800
S. No. 1.
Name/Location Hissar
No of units 2
2. 3.
4. 5. 6. 7. 8.
2 2
2 2 3 3 3
660 660
660 660 660 660 800
Name/Location Solapur Thermal Power Station, Maharashtra Barh Super Thermal Power Station Raghunathpur-II, West Bengal Gidderbaha Station-1, Punjab
No of units 2 3 2 2
Utility M/S. NTPC Ltd M/S. NTPC Ltd. M/S. DVC M/S. PSEB
13.
14.
2
2
660
660
M/S STPCL
M/S Power Company of Karnataka Ltd.
S. No. 1. 2.
Name/Location Dhenknal, Orissa Pussurar Region, Raigarh Chhatisgarh Chutru Region of Jharkhand
No of units 2 3
Utility M/S. Lenco Infratech M/S. Infrastructure Leasing & Financial Service Ltd. M/S. Infrastructure Leasing & Financial Service Ltd.
3.
660
4.
Gondia, Maharashtra
660
5.
660
6.
660
S. No.
Name/Location
No of units
Capacity (MW)
Utility
7.
8. 9. 10.
2
2 2 4
660
660 660 660
11.
12.
2
2
660
660
No of units 2 2
Utility M/S. Amravati Thermal Power Ltd. M/S. Thermal Powertech Corporation(I) Ltd
15.
660
16.
800
17.
800
18.
660
S. No.
Name/Location
No of units
Capacity (MW)
Utility
19.
20.
3
3
660
660
21.
668
2 2 1
S. No.
Name/Location
No of units
Capacity (MW)
Utility
25.
26. 27. 28. 29. 30. 31.
2
2 2 4 4 5 3
660
660 660 800 800 800 660
M/S. Mahagenco
M/S. East Coast Energy M/S. NSL Power Private Ltd M/S. NTPC Ltd M/S. NTPC Ltd M/S. NTPC Ltd M/S. NTPC Ltd. JV with M/S. PCKL