Action plan for CNCRP Working Team-2

Md. Rafiqul Islam Executive Engineer PWD Design Division-III & Team Leader Working Team-2, CNCRP

Objectives of working Team -2 in the current Japan tour under CNCRP


Condition of Existing Buildings Various techniques for retrofitting Research work on retrofitting Selection/Categorization of Building for Retrofitting Seismic vulnerability assessment and retrofitting design Design of earthquake resistant new building Precaution about public safety and security during retrofitting design and works

Condition of Existing Buildings


Present condition in Bangladesh

Most of the existing buildings were not built by considering

seismic forces.

Without seismic detailing. Small column size.

Plain rebar is used.


Weak Beam Column joint. Infill masonry wall is used in frame structure. Most of the buildings are not durable due to poor concreting. Mixed frame structures.

Condition of Existing Buildings


Observation in Japan

Seismic force is considered to design the building. Large column size is observed. No deterioration of concrete and rebar of the existing building.

Item of activity to be considered for CNCRP

Strength of the existing building material to be tested.


Capacity of the existing building to be estimated by analytically and experimentally.

Condition of Existing Buildings


Way of Implementation

List of martial strength to be tested by period wise. Experimental facility to be established.

Long term goal/ achievements

We have to prepare the existing building inventory for the whole

country by following the test result.

Depending on the test result we need to retrofit or demolish the structure.

Remarks

No

Various techniques for retrofitting


Present condition in Bangladesh

No retrofitting work

Observation in Japan
Retrofitting by

Steel frame bracing.

Base Isolation.
RCC Column Jacketing. Insertion of shear wall. Seismic Slit. Wing Wall. Steel Column Jacketing.

Various techniques for retrofitting


Item of activity to be considered for CNCRP

Suitability of the different seismic retrofitting techniques should

be explored for Bangladesh .

Way of Implementation

Pilot project should be considered as retrofitting test work.

Long term goal/ achievements

We have to retrofit the existing building depending on the seismic vulnerability.

Remarks

No

Research work on retrofitting

Present condition in Bangladesh

There is no research work on retrofitting techniques.

Observation in Japan

Research work is enduring in private and public sector.

Item of activity to be considered for CNCRP

Some research work need to be implemented.

Research work on retrofitting


Way of Implementation

Under the supervision of JICA expert, working team-2 will do some research work by analytically and experimentally .

Long term goal/ achievements

PWD will establish a research laboratory with the help of JICA expert.

Remarks

No

Selection/Categorization of Building for Retrofitting


Present condition in Bangladesh

There is no guideline for seismic retrofitting.

Observation in Japan

No specific categorization procedure in Japan.

Some top down selection procedure exist.

Item of activity to be considered for CNCRP

We have to prepare a categorization guide line for seismic retrofitting as per direction of JET.

Selection/Categorization of Building for Retrofitting


Way of Implementation

CNCRP together with JET need to find out suitable technique for implementation.

Long term goal/ achievements

We have to prepare the building inventory for the whole country


by following this categorization guideline.

Remarks

Seismic vulnerability assessment and retrofitting design


Present condition in Bangladesh

Almost no such capacity.

Observation in Japan

There are specialized group of structural designer capable for seismic assessment and retrofitting design.

Item of activity to be considered for CNCRP


Need to prepare seismic vulnerability assessment manual. Need to retrofitting design manual. Need to learn the way of pushover analysis. Need to learn dynamic time history analysis.

Seismic vulnerability assessment and retrofitting design


Way of Implementation

Manual should be prepared with the help of JICA Expert Team. JET will help to learn these analysis properly.

Long term goal/ achievements

PWD engineer will disseminate these knowledge to the public and private sector.

Licensing system should be developed for retrofitting design.

Remarks

No

Design of earthquake resistant new building


Present condition in Bangladesh

There is a lack of capable structural design engineer. Building construction regulation is not strictly followed.

Observation in Japan

Building code is strictly followed by consultant and construction agency.

Item of activity to be considered for CNCRP


Need to prepare seismic design manual for new building. Need to learn the way of pushover analysis for the design of new building.

Need to learn dynamic time history analysis for the design of new

building.

Design of earthquake resistant new building


Way of Implementation

PWD engineer will prepare this design manual with the help of JICA Expert Team. PWD engineer will learn these analysis procedure with the help of JICA Expert Team.

Long term goal/ achievements

PWD engineer will disseminate these knowledge to the public and private sector. Licensing system for the professional engineer for design and construction of building should be followed strictly.

Remarks

No

Precaution about public safety and security during retrofitting design and works
Present condition in Bangladesh

Since there is no retrofitting works in Bangladesh so there is no guideline for public safety and security.

Observation in Japan

Various steps are considered to ensure public safety and security.

Item of activity to be considered for CNCRP

Public safety and security guide line need to be prepared.

Precaution about public safety and security during retrofitting design and works.
Way of Implementation

Need to explore Japanese as well as other international guide line to prepare the guide line.

Long term goal/ achievements

Public safety need to ensure.


Need to increase Public awareness .

Remarks