SPC as tool to achieve reduced variability at each stage of operations for improved clinker / cement quality.
ACC Limited
Nov2012
Each stage Quality Parameters set for which Cpk value to be measured monthly
Raw Material LSF Preparation R90 Mic/ R212 Mic
Clinker
Free Lime
LSF
Cement
ACC Limited
Nov2012
2. Stratification/
2. Observation
3. Analysis 4. Action (Action plan with date/Resp.) 5. Check (*Saving validation by FICO )
Classification
6. Standardization
7. Conclusion & final
submission
For each SPC project:a) Adherence of Project methodology is mandatory. b) Data base support is mandatory for a Valid cause in Analysis step. c) Project saving must be validated by Plant FICO.
3
ACC Limited
Nov2012
ACC Limited
Nov2012
Out come from Feed back. a) Project saving must be validated by Plant FICO. b) Cross functional team involvement in SPC Project for next year. c) All these projects report are uploaded and now are available on shared folder for Reference at all plants. Path For access SPC- Projects folder: \\10.234.3.10\SPC- Projects. - Folder SPC Batch wise (Region wise folder)
ACC Limited Statistical Process Control
5
Nov2012
9 Projects are related to improvement in Cement grinding & Clinker factor. Saving through Cement grinding & CF is Rs 5 Cr.
S No 1 2 3 4 5 6 7 8 9 Name Sumersingh Tata Arvind K Dixit Asit Parui Vivek Gupta Anil Popuri P K Sharma Hemant Sahu Sanjeev Prasad Pintoo Sarkar CMU Lakheri Tikaria Kymore Wadi 2 Thondebhavi Bargarh Kudithini Sindri Damodhar Department Process Quality Process Process Process Process Quality Mechanical Process Project - Grinding section & CF Minimizing the flushing of fly ash in close circuit Cement mill no. 6 Maximization of phospho gypsum percentage in cement Improvement in Cpk of % residue on 45 micron of kymore cement mill 1 product ppc (from 0.32 to 0.80) To improve the process capability of SO3 in cement mill -06 To minimize the variation in cement residue on 45 mic Improvement in Res-45 of Cement mill-3 Minimization of variation of 1 Day compressive strength in PSC Improvement in cpk value of cement mill # 4 residue To improve the cpk of cement mill 45 micron residue by maintaining consistency of cement mill feed by reducing feed cut of CM-1 Annual Saving 36 432 44.9 3 5 10.8
6
Nov2012
ACC Limited
Total
50
ACC Limited
Nov2012
Mr. Sudipta Sinha Reduction in SO3 variation in Cement Mill # 1 . Mr. Basudev Chakrabarty Improvement of Cpk value of So3 in cement from 0.04 to 0.5 .
8
Nov2012
ACC Limited
Optimization of Cement Residue Improve CpK in Mr.Deepak Jasuja G-2 Cement Mills Process and capacity optimization of wobbler from 260 tph to 320 tph Reduction in cube to cube variation in cement strength Mr.Rajesh Kushwaha Mr.Rishikant Baghel
Second
Kudithini
Mr.Ajoykumar Deka
74.46
Third
Madukkarai Improvement in CpK of% Free lime in Clinker by process optimization of the system
Mr.SP Rameshbabu
14.08
Region: East
First
Second Third Third
Jamul
Jamul Chaibasa Chaibasa
Mr.Pinaki Samanta
Mr.Devendra Kumar Mr.Amlan Shyam Mr.Krishna Ram
67.80
48.76 47.54 47.54
9
Nov2012
ACC Limited
2009 to 2011
Project Saving from SPC project Cement Grinding & CF saving (Rs. Cr ) (Rs. Cr) 2.7 1.6 11 5 17.05 7.8 30.75 14.4
10
Nov2012
SPC Project2012
79 SPC Developmental projects identified for 2012, to be executed by Systematic Methodology of Problem solving. Necessary Training for new participants and project leaders being arranged through MIQNasik in March & April for 50 Persons in two batches.
Create Forum for cross learning thru SPC implementation (Safety, Logistics, Environment,
FICO & Sales-RO). 75 SPC project were reviewed in Aug-Sep12 (Region-wise) through MIQ and RO-coordinator. All developmental Project are completed by 15th of Nov12.
Section Safety Quality Productivity/Quality Energy/Power Packing/ Logistics Quarry Logistics Cost/Finance Lubricant Environment HR Procurement AFR HR-Thane Sales-RO Delhi Other/ Maintenance Total
North 0 4 5 3
3
South West 2 7 3 4 2 1 3 2 1 3 2 2 1
East 1 9 6 3 3 1 1
1
RO/Thane
1 1 1
1 18 33 26 2
Total 3 20 14 10 5 5 4 2 4 3 2 2 2 1 1 1
79
11
Nov2012
ACC Limited
SPC Project- CM Grinding & CF To improve Clinker factor by using low purity gypsum & increase in Fly ash % in Cement Mill Gagal II.
Plant
Dept. Process
To Improve the Specific Power Consumption of Gagal 1 Cement Mills (CM#1, CM#2, CM#5)
Increasing Fly ash absorption up to 35 %". Reduce specific energy consumption up to 32.0 KWH/T Establishing the +R45 of PPC in CM #03 Cpk : 0.84 Minimize the variation of % SO3 in PPC grinding to achieve the CpK value >= 0.70 Reduce Cement Mills Process Power from 42.65 to 40.51 KWh/T of Cement Reduction of the Specific power consumption in VRM grinding from 48 kwh/MT to 45 kwh/MT Reduction in oil consumption Lit. / Tn of cement. Improvement in Hourly TPH Reduction in clinker factor of PSC from 44% to 41%. Improving flyash absorption in PPC from 22% to 25%. Reducing PPC 3 days strength COV from 8.4 to 4.9 Complying 100% internal quality norms for F2R. Improvement in cement SO3 cpk from 0.13 to 0.3 Additives consumption optimization & hence reduction by Rs3/t cemt. Reduction in strength variation in 1 Day and 3 Day strength Reduction in clinker factor by optimizing PSC quality
Gagal
Power Quality Power Quality Quality Power Power Lubricant Productivity Productivity Productivity Quality Quality Quality Productivity Quality Productivity
Bargarh
Jamul
Sindri
Damodhar
12
ACC Limited
Nov2012
2011
Sustainability of of Performance by involvement of 2009 batch Plant SPC Champion for coordinating development project. Reward & recognition for Best project (Region- wise) SAP system hookup with Excel Breakthrough improvements. Multiplication of projects by all yet trained participants Expand to Process parameters like BZT, Separator RPM
2008
SAP Implementation Expand the horizon of SPC (Mines, Maint , E& I Added) SPC plant champion & Regional coordinator. Breakthrough improvements. Development of Control Plan 2009 SPC Project share folder (Region- wise) Performance analysis based on Cpk achieved Review of Specification limits & Target setting Synergy between PQM and SPC Analysis of control charts Shift wise , Development of trainers at plant level Multiplication of projects at all stages, Implementation of SPC at extraction stage Implementation of MSA and SSP (statistical sampling plan)
2010
Flavor to Top Management on the Concept Team Formation , Training & Project assign Projects review and support with MIQ (Nasik )
13
Nov2012
ACC Limited
SPC Champion at each Plant & RO-Coordinator to support the Project Leader
& his Team for pursuing of sectional developmental project.
Monthly SPC report for sectional review & improvement. Tangible benefit: Cpk improvements by reduced variability at each stage of operation.