Академический Документы
Профессиональный Документы
Культура Документы
Purpose
This presentation is intended to be a general outline of utility forecasting and planning techniques not specific to any one company. It is, however, intended to represent a utility that is a PJM member, and is following a process that works with the PJM planning regime.
Planning Criteria
A utilitys planning criteria are intended to be a guide to provide for the safe, reliable and low cost development of the utilitys electrical system as loads increase and reinforcements and/or new facilities are required.
Basic Principles
With all facilities in service: Load must be within normal equipment ratings
Must provide acceptable voltages
Basic Principles
With the outage of any single piece of equipment (N-1 Criteria Violation): Affected load must be within the emergency rating of the remaining facilities System must provide minimum emergency voltages
Basic Principles
N-1 criteria are applied in a similar fashion to: Substations Distribution Facilities Subtransmission Facilities Transmission Facilities
Basic Principles
Transmission Planning Criteria Goes beyond N-1 N-2 (After the N-1 outage and readjustment, loss of an additional element.) Towerline outages Stuck breakers Transmission planning criteria are more restrictive than operating criteria to account for potential new generation, and network facilities forecasted and unplanned outages.
7
Distribution Planning
Load Forecasting Substation Feeder Distribution Circuit Reinforcement Ratings N-1 Criteria New Business Connected vs. Estimated Loads Load Build-up Schedules Load Shifting
8
10
MV-90 Remote Metering Substation Data Concentrators Inspection Data Data Scrubbing
12
14
16
Coincidence Factor
Substations feed a number of different types of load Not all of the load will peak at the same time (diversity) Expect any implementation of time-of-use or RTP tariffs to cause interval customers to change/modify load patterns
17
18
19
Interstation Capacity Ties Station Reinforcement New Station Generation (As Permitted)
20
23
New Business
Division Planners are typically concerned with new business projects 300-kVA and greater Voltage / Service characteristics can range from secondary to sub-transmission (277/480 volts up to 69-kV) Types of New Business can vary from Network Service to Substation / High Tension service
24
Transmission Planning
Entity Load Forecast Regional Transmission Expansion Planning (RTEP) Process Lead by PJM and coordinated with Transmission Owners Incorporation of utilitys T&D Planning results into PJMs RTEP Process, PJM will begin zonal forecasting utility loads this year Baseline Reinforcements Merchant Generation/Transmission Interconnections & Reinforcements Analyses & Tools Short Circuit Load Flow System Stability LOLP (Loss of Load Probability) Operations Support
25
Any Questions?
27