Академический Документы
Профессиональный Документы
Культура Документы
Admeasurement
Target Cost Reimbursable 0% Direct Labour 100%
risks. Reliance on unforeseen ground conditions Clause 12 (or now FIDIC Clause 4.12) Potentially adversarial for the winning / successful contractor if conditions different Often bespoke conditions or amended standard form. Issues Factual Data (plus requirement that Contractor provides any additional for his purposes)
Practices
GBR
GIR GDR Risk Compensation Dispute Resolution Courts
Insurance Requirements
A GBR/GIR is an insurance requirement and without
such a document insurance premiums may be higher or a project may require self insurance. A GBR is required to provide a realistic interpretation of the anticipated subsurface conditions. Realistic? The GBR includes for the mean but also the expected range. If risks are less than baseline or consistent with baseline they belong to the Contractor If risks are more adverse the Owner/ Client accepts the risks and compensates the Contractor accordingly.
Expert Views
Although a consistent and fair view is required
Owners are conservative. Risk is overpriced and dows not need to be. Contingency eaten up
Conservatism / Protectionism
GBRs do not represent the ground. Ground is not
described realistically.
what may be expected resulting in risk shifting and Contractor taking risk anyway.
& a HK perspective
Ranges of Values
Baseline Conditions??
Results
Reallocation of Risk
Risk Compensation
Payment for differing Ground Conditions
Time Compensation Payment for differing Water Conditions
Other Mechanisms
Payment (Remeasurement)
Measurement and payment for tunnel excavation
will be made according to the excavation classes where set out in the Bill of Quantities. The estimated quantities for each excavation class given in the Bill of Quantities are not ...an accurate indication of the quantity of work...the predicted and the actual length of each excavation class may differ due to geological conditions encountered in the course of Works.
conditions and/or an unexpected influx of water severely in excess of the capacity of the facilities envisaged in this Specification, ...leaving no possibility of further advance by the construction methods reasonably provided for by the Contract... No EGO will be acknowledged or accepted in the rear zones If an EGO occurs, the Contractor shall without delay propose a method ...to overcome the situation and undertake, with the approval of the Engineer, all the necessary steps to expeditiously resume the tunnel excavation The EGO provisions do not in any way release the Contractor from his responsibility to excavate with caution
reimbursed according to the relevant unit prices and other price determination procedures provided for in the Contract. The Contractors programme shall include allowances for EGO, and shall advise the allowance in the Schedule. The Contractor shall have no claim to an extension of time due to an EGO
4.12
In this Sub-Clause, physical conditions means natural physical
conditions and manmade and other physical obstructions and pollutants, which the Contractor encounters at the Site when executing the Works, including sub-surface and hydrological conditions but excluding climatic conditions. If the Contractor encounters adverse physical conditions which he considers to have been Unforeseeable, the Contractor shall give notice to the Engineer as soon as practicable. This notice shall describe the physical conditions, so that they can be inspected by the Engineer, and shall set out the reasons why the Contractor considers them to be Unforeseeable. The Contractor shall continue executing the Works
shall encounter physical conditions, other than weather conditions and effects due to weather conditions on the Site, or artificial obstructions, which conditions or obstructions could not have been reasonably foreseen by an experienced contractor, the Contractor shall forthwith give written notice thereof to the Engineer and if, in the opinion of the Engineer, such conditions or artificial obstructions could not have been reasonably foreseen by an experienced contractor, then the Engineer may grant such time extension as is reasonable ...such sums as may be reasonable...
Information
Geotechnical Data
11.2 The Factual Geotechnical Report is not intended to
represent to the Contractor the nature of the soil conditions he will encounter in executing the Works. The use of the information and the interpretation of it is entirely the Contractors responsibility. The Authority makes no warranty for the accuracy or otherwise of the Report and shall not be responsible for any loss, expense or damage suffered by the Contractor arising from the results of geotechnical data made available to the Contractor.
Private Developer
Baseline
Rates
Time
Water
Recent Example
2000 holes
Several months of study 12 boreholes Bid in 28 days
OUTPUTS
DESIGN CONSIDERATIONS
PROCESS
INTERPRETATION
SITE INVESTIGATION DATA SITE INVESTIGATION EXECUTION INPUTS SITE INVESTIGATION PROCUREMENT SITE INVESTIGATION DESIGN DESIGN / CONSTRUCTION REQUIREMENTS
Data opt
LEVEL OF DATA
Report Dependencies
The GBR and GIR are the end product of a process.
The quality of both depend on the initial requirements
definition and site investigations. This is often not a one stop shop. What if geological / geotechnical data/information is not realised? In any event somebody will do an interpretation. The owner, the owners consultant, the contractor, the investigating team.
is contract certainty maintained. ISO 9000 requires continuing improvement but a baseline is fixed.
Changes
What if GBR is wrong / inappropriate due to data/draughting? How is an EGO incorporated if it happens more than once? What are the consequences if the ground blows the budget Changes to baselines and contractual / governance implications Cost / Contract Certainty wishful thinking or stark reality, comfort factor, hope.
Summary
Geotechnical baselines
Geotechnical Interpretative reports Contact Conditions up front Payment mechanisms Being straight about ground conditions Time for process no matter what mechanism is used What about changing the contract?