Академический Документы
Профессиональный Документы
Культура Документы
Class 13, 14
Learning Objectives
MRP Concept, Master Production Schedule, Material Requirements Planning System Structure, MRP Examples
Inventory transactions
Secondary reports
Primary reports Planned order schedule for inventory and production control Exception reports Planning reports Reports for performance control
MRP is a logical, easily understandable approach to the problem of determining the number of parts, components and material needed to produce the End Item.
Material Requirements Planning Provides schedule for production or ordering of materials, parts and components required for the end item. Based on Dependent demand Based on End Item only
E(1 )
Creates schedules identifying the specific parts and materials required to produce end items Determines exact unit numbers needed
Determines the dates when orders for those materials should be released, based on lead times
Total Unit Demand Day 10 50 nos. of A Day 8 20 nos. of B (Spares) Day 6 15 nos. of D (Spares)
First, the number of units of A are scheduled backwards to allow for their lead time. So, in the materials requirement plan below, we have to place an order for 50 units of A on the 9th day to receive them on day 10.
Day: A Required Order Placem ent 1 2 3 4 5 6 7 8 9 50 10 50
LT = 1 day
Next, we need to start scheduling the components that make up A. In the case of component B we need 4 Bs for each A. Since we need 50 As, that means 200 Bs. And again, we back the schedule up for the necessary 2 days of lead time.
Day: A B R e q u ire d O rd e r P la c e m e n t R e q u ire d O rd e r P la c e m e n t 20 200 20 50 200 1 2 3 4 5 6 7 8 9 10 50
Spares
4x50=200
D(2)
14
Finally, repeating the process for all components, we have the final materials requirements plan:
Day: A LT=1 B LT=2 C LT=1 D LT=3 E LT=4 F LT=1 Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement Required Order Placement 1 2 3 4 5 6 7 8 9 50 200 100 55 55 20 200 200 200 400 300 20 200 400 100 300 10 50
20 20 200
A
Part D: Day 6
C(2) F(2)
40 + 15 spares
Week: Required
1 0 0 0 0 0 0 0 0 0 0 0 0
2 0 0 0 0 0 0 0 0 0 80 0 0
3 0 0 0 0 0 0 0 30 0 800 0 0
4 0 0 0 0 0 0 0 0 0 600 0 0
5 0 0 0 0 0 0 0 0 0 0 0 40
6 0 0 0 40 0 0 30 300 80 0 40 400
10 100 0 0 0 0 0 0 0 0 0 0 0
Order LT=1 Placement B Required Order LT=2 Placement C Required Order LT=1 Placement D Required Order LT=3 Placement E Required Order LT=4 Placement F Required Order LT=1 Placement
Project Work
Synopsis on the Project work undertaken by 23-02-2013 5PM. Weightage 2 marks
19
Inventory transactions
Secondary reports
Primary reports Planned order schedule for inventory and production control Exception reports Planning reports Reports for performance control
derived from engineering and process design. Often called as Product structure file or product tree.
Parent
Any item manufactured from one or more components.
Usage Quantity
The number of units of a component needed to make one unit of its immediate parent.
Sub-Assembly
An intermediate item that is assembled from more than one component.
Purchased Item
An item that has one or more parents, but no component because it comes from supplier.
Pegging
On-Hand Inventory
An estimate of the amount of inventory available each week after gross requirements have been satisfied.
Net Requirement
Total requirement to be executed after considering onhand inventory.
180
30
30
30
140
140
40
150
90
80
230
230
230
Offsetting
MRP Example
X A(2) C(3) C(2) B(1) D(5)
Item X A B C D On-Hand Lead Time (Weeks) 50 2 75 3 25 1 10 2 20 2
Day: X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt
5 50
6 50
7 50
8 50
9 50
50 50
50 50
A(2)
75 75
75 75
75
75
75
45 90 75 15 15 45 25 20 20
15 25 25 25 25 25 25 25
10 10
10 10
35 20 20 20 20
45 10 35 35 40 20
20 40 40 40 100 20 20 80 80
Day: X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt
5 50
6 50
7 50
8 50
9 50
50 50
50 50
A(2)
B(1)
75 75
75 75
75
75
75
45 90 75 15 15 45 25 20 20
15 25 25 25 25 25 25 25
10 10
10 10
35 20 20 20 20
45 10 35 35 40 20
20 40 40 40 100 20 20 80 80
Day: X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt
5 50
6 50
7 50
8 50
9 50
50 50
50 50
A(2)
B(1)
75 75
75 75
75
75
75
45 90 75 15 15 45 25 20 20
C(3)
15 25 25 25 25 25 25 25
10 10
10 10
35 20 20 20 20
45 10 35 35 40 20
20 40 40 40 100 20 20 80 80
Day: X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt
5 50
6 50
7 50
8 50
9 50
50 50
50 50
A(2)
B(1)
75 75
75 75
75
75
75
45 90 75 15 15 45 25 20 20
C(3)
C(2)
15 25 25 25 25 25 25 25
10 10
10 10
35 20 20 20 20
45 10 35 35 40 20
20 40 40 40 100 20 20 80 80
Day: X LT=2 Onhand 50 A LT=3 Onhand 75 B LT=1 Onhand 25 C LT=2 Onhand 10 D LT=2 Onhand Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt Planner order release Gross requirements Proj. avail. balance Net requirements Planned order receipt
5 50
6 50
7 50
8 50
9 50
50 50
50 50
A(2)
B(1)
75 75
75 75
75
75
75
45 90 75 15 15 45 25 20 20
C(3)
C(2)
D(5)
15 25 25 25 25 25 25 25
10 10
10 10
35 20 20 20 20
45 10 35 35 40 20
20 40 40 40 100 20 20 80 80
No Feedback Realistic?
Feedback
Yes
Execute: Capacity Plans Material Plans
Improvement in maintenance
Easy identification of problem areas
Timely Delivery
Improvement in Quality of the Product
performance measure
Provide detail overview of Manufacturing process
Rescheduling Capabilities
Coordination
Confidence in the system
Personnel
Finance Purchasing Top Management
Thank You