Describe C300 and Series C I/O Configuration

C300 Configuration Describe C300 and Series C I/O Configuration

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Introduction

Honeywell

In this lesson you will learn to configure C300 Controller and Series C I/O PMIO configuration is discussed in a separate lesson The steps for configuration are similar to the C200 configuration with some differences:
Add a new Control Processor Module to the Project hierarchy Control Builder adds the CEE and two IOLINK modules Configure the Controller Configure the CEE Configure the IOLINKs (PMIO or Series C IO) Configure the IOMs Assign the IOMs to the IOLINKs Load the Controller, CEE, IOLINKS, and the IOPs Activate the CEE

C300 Configuration Describe C300 and Series C I/O Configuration

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Topics Configuring the C300 and CEE Configuring IOLINKs Configuring IOMs Loading the C300, IOLINKs, and IOMs Activating the C300

Honeywell

C300 Configuration Describe C300 and Series C I/O Configuration

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Configuring a Controller

Honeywell

Follow these steps to add a new controller from the pull-down menus

C300 Configuration Describe C300 and Series C I/O Configuration

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Configuring a Controller Main Tab


Data entry details will be provided in the lab exercise

Honeywell

Item name

Device index Number of C300

Check for redundant controller

C300 Configuration Describe C300 and Series C I/O Configuration

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Configuring a Controller Server History Tab

Honeywell

History parameters and control level required to operate this C300

C300 Configuration Describe C300 and Series C I/O Configuration

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Configuring a Controller Group and Trend Assignment

Honeywell

Point, group, trend and associated displays (residing on the server) are defined on the Server Displays tab

Select OK to close and save the new controller

C300 Configuration Describe C300 and Series C I/O Configuration

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

C300 View in Control Builder

Honeywell

C300, CEE, and IOLINKs

Redundancy

C300 Configuration Describe C300 and Series C I/O Configuration

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Configuring a CEE

Honeywell

Data entry details will be provided in the Lab exercise

C300 Configuration Describe C300 and Series C I/O Configuration

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Question 1: C300 Configuration


A) Device Index number specified on the C300 IOTA needs to be specified B) 2 IOLINKs are automatically created C) Only one IOLINK is automatically created for Series C I/O

Honeywell

Which of the following statements is not true for C300 configuration?

D) 5ms Base Execution Period is supported for non-redundant C300 configuration


The answer is: Yourcorrect answer: Incorrect. The falsethe statement isbefore "Only one You must answer question Incorrect Click anywhere to continue You did You not answer answered this this question correctly! completely Correct Click anywhere to continue Correct! IOLINK is When automatically acontinuing C300 controller created for is created Series C in Control I/O". I/O".When When Builder a a C300 C300 2 IOLINKS controller controller are is automatically is created created in in Control Builder 2 IOLINKS added. are automatically added. Click anywhere to continue. Click anywhere to continue.

Submit

Clear

C300 Configuration Describe C300 and Series C I/O Configuration

10

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Topics Configuring the C300 and CEE Configuring IOLINKs Configuring IOMs Loading the C300, IOLINKs, and IOMs

Honeywell

Activating the C300

C300 Configuration Describe C300 and Series C I/O Configuration

11

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

IOLINK Configuration Link 1

Honeywell

I/O family selection

I/O Link number 1 Cable - Gray

C300 Configuration Describe C300 and Series C I/O Configuration

12

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

IOLINK Configuration Link 2

Honeywell

I/O Link number 2 Cable - Violet

C300 Configuration Describe C300 and Series C I/O Configuration

13

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Configuring C300 Hardware

Honeywell

The Control Processor Module (CPM) and its Control Execution Environment (CEE) are now configured but not yet downloaded

C300 Configuration Describe C300 and Series C I/O Configuration

14

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Question 2: IOLINK Configuration

Honeywell

Which of the following items are specified during IOLINK configuration?


A) Series C or PM IO, one type on each IOLINK B) Series A I/O type C) Whether Series C and PM IO is to be used on the same IOLINK

The correct Your answer: answer is: Correct! When configuring an only Incorrect. When configuring anIOLINK IOLINK onlyone one You must answer the question before You Incorrect Correct did You not answer answered Click Click anywhere anywhere this this question correctly! to to continue continue completely type of IO family can be connected to each continuing IOLINK i.e. Series C or PM IO, one type on each link. Click anywhere to continue.

Submit

Clear

C300 Configuration Describe C300 and Series C I/O Configuration

15

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Topics Configuring the C300 and CEE Configuring IOLINKs Configuring IOMs Loading the C300, IOLINKs, and IOMs

Honeywell

Activating the C300

C300 Configuration Describe C300 and Series C I/O Configuration

16

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Configuring Series_C_IO

Honeywell

Menu method

C300 Configuration Describe C300 and Series C I/O Configuration

17

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Configuring Series_C_IO, contd.

Honeywell

Control Builder automatically names the IOM

C300 Configuration Describe C300 and Series C I/O Configuration

18

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Configuring Series_C_IO, contd.

Honeywell

IOM number

C300 Configuration Describe C300 and Series C I/O Configuration

19

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Assigning Series_C_IO

Honeywell

1 3

Assigned to CEE

C300 Configuration Describe C300 and Series C I/O Configuration

20

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Topics Configuring the C300 and CEE Configuring IOLINKs Configuring IOMs Loading the C300, IOLINKs, and IOMs

Honeywell

Activating the C300

C300 Configuration Describe C300 and Series C I/O Configuration

21

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Loading the Controller, CEE, and IOMs

Honeywell

Not yet loaded

C300 Configuration Describe C300 and Series C I/O Configuration

22

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Loading the Controller, CEE, and IOMs, contd.

Honeywell

Verify that the items to load are checked Note: You can decide to have the modules go to the active state automatically by clicking this checkbox with the Post Load State selected to be Active

C300 Configuration Describe C300 and Series C I/O Configuration

23

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Question 3: IOP Configuration Assigned I/O modules appear under:


A) Unassigned tree in Project tab B) IOLINK tree in Project tab C) Directly under the CEE tree in Project tab

Honeywell

The correct answer is: Your answer: Correct! The assigned I/O modules appear You must answer the question before Incorrect -Click Click anywhere to continue You answered this correctly! Incorrect. The assigned I/O modules appear Correct anywhere to continue You did notthe answer this question completely under IOLINK tree in Project tab. continuing under the IOLINK tree in Project tab. Click anywhere to continue. Click anywhere to continue.

Submit

Clear

C300 Configuration Describe C300 and Series C I/O Configuration

24

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Topics Configuring the C300 and CEE Configuring IOLINKs Configuring IOMs Loading the C300, IOLINKs, and IOMs

Honeywell

Activating the C300

C300 Configuration Describe C300 and Series C I/O Configuration

25

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Activating a Control Strategy

Honeywell

Select LASTCOLD

C300 Configuration Describe C300 and Series C I/O Configuration

26

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Activating a Control Strategy, contd.

Honeywell

Click Yes

Blue: The object is not running (inactive) Green: The object is running (active)

Red: Communication failure

C300 Configuration Describe C300 and Series C I/O Configuration

27

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Other C300 Configuration A Control Module is configured like a C200 Control Module, a sample is shown For more detail, please refer to the sample lab procedure

Honeywell

Series C I/O Channels

C300 Configuration Describe C300 and Series C I/O Configuration

28

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Summary

Honeywell

When you configure and load C300 hardware and I/O in Control Builder, remember:
Series C IOM number is set on the IOTA of the corresponding IOM using a numbered jumper plug The device index of C300 can be found on the rotary switches located in front of the C300 board Before loading the C300 controller, its Control Execution Environment (CEE) and IOLINKs: Configure the Controller, its CEE, and IOLINKs Define the I/O Family type on each IOLINK Assign the IOMs to the respective IOLINKs Activate the C300 from the CEE

C300 Configuration Describe C300 and Series C I/O Configuration

29

EXP20R300 - EPKS CEE C200/C300/ACE 11/29/2013

Conclusion

Honeywell

Describe C300 and Series C I/O Configuration

Completion Certificate

Proceed to the next lesson in your course material