Академический Документы
Профессиональный Документы
Культура Документы
Managing Projects
Projects are usually large & infrequent or one-time.
No two projects are the same. Projects are usually fairly long.
Several months to many years
Even though a project may be under the overall purview of a single department or group, other departments are often involved.
2013 Lew Hofmann
Projects
The three main goals of project management are 1. Complete the project on time or earlier. 2. Complete the project on or under budget. 3. Meet the specifications to the satisfaction of the customer.
Project Structures
Functional Structure: The team is housed in a
CPM (Critical Path Method) is used when activity times are known and certain.
Rarely used, and then only in very complex projects. It overcomes many of the limitations of PERT and CPM Provides much more project flexibility.
Task Ownership: Each activity must have an owner who is responsible for seeing that the work is accomplished.
2013 Lew Hofmann
Except for the beginning activity/activities, every activity in a project has one or more activities that must be done immediately prior. These are called Precedent (Pre-cee-ent) activities
They must be defined before the project begins.
EG: In order to bury a body you must first dig a hole.
2013 Lew Hofmann
Activity-on-Node (AON)
Activity
Activity
D
Link
2013 Lew Hofmann
Slack
The earliest you can complete an activity--determined by adding the activity time (duration) to the early start time.
Start
Finish
This is the latest you can finish an activity without delaying project completion. It is the same as the Late Start time of the next activity. If there are two or more subsequent activities, this time is the same as the earliest of those Late Start times.
The earliest you can start this assignment it is immediately after this class ends.
Slack
If it takes one hour, the earliest you can complete this assignment is one hour after class ends.
Precedent Relationships
Precedent relationships determine the sequence for accomplishing activities. They specify that any given activity cannot start until its preceding activity or activities have been completed.
Activity On Node approach
In our AON approach, the nodes (circles) represent activities, and the arcs (arrows) represent the sequential relationships between them.
Nodes are simplified in the following examples. 2013 Lew Hofmann
AON
Activity Relationships
Activity Relationships
U cannot begin until S & T have been completed. V cannot begin until T has been completed.
S U
Activity Relationships
T & U cannot begin until S has been completed; V cannot begin until both T & U have been completed.
S T V
Logic Errors
This is a logic error. C cannot be an immediate predecessor of both G &H if G is also an immediate predecessor of H.
Logic errors are hard to identify except on the network diagrams. If you see a triangle, then it is a logic error. Eliminate the short cut.
2013 Lew Hofmann
A B C D E F
G H I J K
Select administrative and medical staff. Select site and do site survey. Select equipment. Prepare final construction plans and layout. Bring utilities to the site. Interview applicants and fill positions in nursing, support staff, maintenance, and security. Purchase and take delivery of equipment. Construct the hospital. Develop an information system. Install the equipment. Train nurses and support staff.
A B C D E F
G H I J K
Select administrative and medical staff. Select site and do site survey. Select equipment. Prepare final construction plans & layout. Bring utilities to the site. Interview applicants and fill positions in nursing, support staff, maintenance, and security. Purchase and take delivery of equipment. Construct the hospital. Develop an information system. Install the equipment. Train nurses and support staff.
12 9 10 10 24 10
C D A E,G,H F,I,J
35 40 15 4 6
Immediate Predecessors
A B C D E F G H I J K A B B A C D A E,G,H F,I,J 12 9 10 10 24 10 35 40 15 4 6
Start
Finish
Time (wks) 33 28 67 69 43
Start
Finish
Start
Finish
PERT (Program Evaluation and Review Technique) is used when activity times are uncertain. (Decision making under risk)
It requires three time estimates for each activity.
(Best case, most likely time, and worst case)
2013 Lew Hofmann
In this example, the most likely time is given a weight of four, and the other two times (pessimistic and optimistic) are each given weights of one. Risky activity times make the project length risky, so there is a need for risk assessment based on the probability distribution of times. (Standard deviation and variance are computed by the software.)
2013 Lew Hofmann
Activity Slack
Activity slack is the maximum length of time that an activity can be delayed without delaying the entire project. It is the difference between the earliest time we can start an activity and the latest time we can start the activity without delaying the project.
Latest Start Time (LS) is the latest you can finish the activity
minus the activitys estimated duration.
Latest Finish Time (LF) is the latest start time plus the activity
time.
The latest finish time is the same as the latest start time of the activity activity which follows it. (Latest start and finish times for each activity are computed starting at the projects last activity completion time and working forward.)
Slack is the difference between the Earliest Start and Latest start
2013 Lew Hofmann
times for an activity (or earliest finish and latest finish times.)
I 27 15
12 F 22
12
10 C 22 10 G 57 35
Start
12
22
Finish
B 9 9
D 19
10
19
H 59 40
59
J 63 4
9 E 33
24
2013 Lew Hofmann
Time (wks)
12
I 27 15
33 28 67 69 43
A 12
12
12 F 22
10 C 22 10 G 57 35
Start
12
22
Finish
Critical Path
B 9 9
D 19
10
19
H 59 40
59
J 63 4
9 E 33
24
2013 Lew Hofmann
12
12 F 22 53 10 63
2 12 14
63 K 69 63 6 69
Start
12 22 14 10 24
35
B 9
0 9 9
9 19 9 10 19
19 19
H 59
59
J 63
40 59
59 4 63
Node A B C D E F G H I J K
Duration 12 9 10 10 24 10 35 40 15 4 6
ES 0 0 12 9 9 12 22 19 12 59 63
LS 2 0 14 9 35 53 24 19 48 59 63
Slack 2 0 2 0 26 41 2 0 36 0 0
12 27 48 15 63
12
12 F 22 53 10 63
2 12 14
63 K 69 63 6 69
Start
12 22 14 10 24
22 G 57 24 59
35
Finish
B 9
0 9 9
9 19 9 10 19
19 59 19 40 59
59
J 63
59 4 63
9 E 33 35 24 59
Crashing a project means finishing the project early by expediting one or more activities.
Not all activities can be shortened.
2013 Lew Hofmann
Project Costs
Total Project Costs = direct costs + indirect costs + penalty costs Direct costs include labor, materials, and any other costs directly related to project activities.
Indirect costs include administration, depreciation, financial, and other variable overhead costs. These can be reduced by reducing total project time.
The shorter the duration of the project, the lower the indirect costs will be.
Penalty costs are essentially late fees incurred for going over the projected due date.
2013 Lew Hofmann
Minimizing Costs
We do cost analysis to determine the project schedule that minimizes total project costs.
When crashing an activity or project, extra money is spent on direct costs, but money is saved on indirect costs and possible penalties. A minimum-cost schedule is determined by starting with the normal project time schedule and shortening activities along the critical path until the costs of crashing (direct costs) start to exceed the savings in indirect costs and penalty costs.
New critical paths usually appears while doing this.
2013 Lew Hofmann
d. Repeat this process until the total project costs are no longer decreasing.
12 27 48 15 63
Of the five critical-path activities, the contractor says D and H cannot be shortened. J is the least costly to shorten at $1000 a week. Contractor says it can be shortened to 1 week.
63 K 69 63 6 69
12
12 F 22 53
2 12 14
10 63 C
22 G 57 24 59
Start
12 22 14 10 24
35
Finish
B 9 0
0 9 9
9 19 9 10 19
19 19
H 59 40 59
59
J 63
59 4 63
9 E 33 35 24 59
The project manager must now compare the cost of shortening J by 3 weeks ($3,000 in additional direct costs) with savings in indirect costs, to see if the total cost is lower.
Assessing Risks
Risk is a measure of the probability (and consequences) of not completing a project on time. A major responsibility of the project manager at the start of a project is to develop a riskmanagement plan. A Risk-Management Plan identifies the key risks to a projects success and prescribes ways to circumvent them.
2013 Lew Hofmann
2. Project Team Problems: Poor member selections and inexperience, lack of cooperation, etc. 3. Operations Risk: Information inaccuracy, misscommunications, bad project timing, weather
2013 Lew Hofmann
ANALYZING PROBABILITIES
What is the probability that our sample project will finish in 69 weeks as scheduled?
100% (Why?)
Because we used CPM!
(This means we were certain of all of our activity times.)
Normal distributions are needed for probabilities. A distribution of activity-means is a normal distribution, even though each activity time may be a beta distribution.
Beta Distribution
Each activity may have its three time estimates skewed (Beta Distribution), but the path along which this activities lie has a normal distribution and thus a mean and variance.
Probability
a
Optimistic
2013 Lew Hofmann
m Mean
b
Pessimistic
Time
Figuring Probabilities
Assume a PERT project critical path takes 40 days, and that the variance of the critical path is 2.147
You wish to know the probability of the project going over 42 days.
Compute the Z value: Z = (absolute time difference) / Std. Dev. In this example, Z = (42 days - 40 days) / 1.465 = 1.365 Look up the Z value of 1.365 in a Normal Distribution table to get the probability of the project taking 42 days. Subtract it from 100% to get the probability of going over 42.
2013 Lew Hofmann
.9139
.9139 or 91.39% is the probability of the project taking 42 days. Thus the probability of going over 42 days is 100 - 91.39 = 8.61%
Project Length (critical path) is 40 weeks Probability of completing the project in 42 weeks is 91.39%
Normal distribution of variances along the critical path. Sum of its variances = 2.147 Std. Dev. = 1.465 weeks
z=
2013 Lew Hofmann
72 69 11.89
z=
3 3.44818
Z = 0.870
Look up the Z value (0.870) in the table of normal distribution. .8078 or 80.78% is the probability of the project taking 72 wks. Going over 72 weeks would be 100 80.78 = 19.22%
69 72
Resource-Related Problems
Padded Time Estimates: Many timeestimates come with a built-in cushion that management may not realize. Latest Date Mentality: The tendency for employees (and students) to procrastinate until the last moment before starting. Failure to Deliver Early, even if the work is completed before the latest finish date.
2013 Lew Hofmann
Resource-Related Problems
Path Mergers occur when two or more activity
paths combine at a particular node. Both paths must be completed up to this point, which will eliminate any built-up slack.
GERT
(Graphical Evaluation and Review Technique) Gives more flexibility to project planning than PERT/CPM
Allows any individual activity to either be completed or not completed (Succeed or fail)
PERT & CPM both require all activities be successfully completed. GERT does not require this. GERT Allows looping back (redoing an activity) or skipping an activity entirely. There are computerized GERT packages.
2013 Lew Hofmann
Solved Problem
What is the probability of completing the project in 23 weeks?
Solved Problem
Solved Problem
4.0 8.0 0.0 4.0 A 4.0 8.0 D 12.0 16.0 20.0 9.0 9.0 E 15.5 15.5
Finish
4.0
6.5
Start
C 3.5
9.0 9.0 G
0.0 0.0
5.5 5.5
F 9.0
15.5 15.5
4.5
20.0 20.0
5.5 6.5
2013 Lew Hofmann
14.5 15.5
Solved Problem
Using the Normal Distribution appendix, we find that the probability of completing the project in 23 weeks or less is 0.9357.
Problem 1
Do manually (no computer)
A project has the following precedence relationships and activity times. Draw the network diagram and calculate the total slack for each activity. Which activities are on the critical path?
Activity A B C D E F G H
2013 Lew Hofmann
Time 3 2
Precedents None A
C
D E F G H
2
3 2 1 3 3
B
C C D,E E D,E
I
J
3
3
D,E,F
I
Homework, Problem 3
(next slide)
This is a PERT problem so it has three time estimates. Use the POM/OM package. Answer the following questions: a. Identify the critical path(s). b. How long is the path nearest to the critical path? c. What is the probability that the project will take longer than 38 days? (Table of Normal Probabilities is on the last slide.)
d. What is the probability that the near critical path will take longer than 38 days? e. Include 5 printouts: Input screen, PERT/CPM results table, Precedence graph, Task time computations, and the Gantt chart of early & late times.
2013 Lew Hofmann
Problem #3
Activity Precedent Optimistic Most Likely Pessimistic
B C
D E
A A
B B
4 5
8 7
4 6
10 10
4 8
10 15
F G
H I J
C C
D E, F G
9 7
4 6 8
9 7
6 9 9
13 7
8 11 10
K
2013 Lew Hofmann 2013 Lew Hofmann
H, I, J
Sample PERT/CPM
Precedence Graph Printout
Note that the software does not add start blocks or end blocks. In your homework computer problem, you will have more than one ending node. This is not an error. Connect them to an End Block if it will help you visualize it.
Note also that there is a logic error. D should not be an immediate predecessor of F.
http://www.techsmith.com/jing.html