:-10th Planet
Name of Dept:-O&M(operation)
TEAM LEADER:-MR.R.R.NAIK
MEMBER:-MR.H.K. UDAN
MEMBER:-MR.JADUMANI SAHOO
MEMBER:-MR.N.K.PRADHAN
MEMBER:-MR.SANJAY KU. SAHOO
FACILITATER:- MR.M.K.JANA
DY.FACILITATER:MR.A.K.PASWAN
Formation & Registration
of our Quality Circle
TYPE 08
-A
TYPE-B 32
TYPE-C 18
STEP- 2 :
PROBLEM NO.
1 2 3 4 5 6 7 8 9 10 11 12
MEMBERS
R.R. NAIK 8 8 9 8 5 6 9 6 8 6 7 6
J. SAHOO 9 7 8 7 9 9 10 5 6 5 7 5
N.K. PRADHAN 8 9 8 8 10 6 9 7 8 7 6 7
H.K. UDAN 9 8 7 7 9 4 8 5 7 8 9 6
S.K. SAHOO 8 7 6 6 7 5 9 6 8 6 6 7
TOTAL 42 39 38 36 40 30 45 29 37 32 35 31
RANKS 2 4 5 7 3 11 1 12 6 9 8 10
TIME in weeks
NO. ACTIVITY
1 2 3 4 5 6 7 8 9 10 11
12 13
1 Defining problem
2 Analysing the problem
3 Identifying the cause
4 Finding out root cause
5 Data analysis
6 Developing solutions
Foreseeing probable
7 resistance
Trial implementation and
8 Checking performance
9 Regular implementation
10Follow-up / Review
TARGET (12
WEEKS )
Glass Window
Conveyor Belt
Bunker
Feeder
Drain line
Mill # 1 C
DESIGN BY
MR R.R.NAYAK
COAL BUNKER
Storage of coal .
No need of continuous feeding
through conveyers .
Total capacity is 1600Tone.
FEEDER
NO
IT IS RAINING
MILL # 1C
CLASSIFIER
TEMP LOW
YES
NO
END FLOW CHART FOR
C&I
PROBLE MILL#1C CLASSIFIER
M TEMPERATURE LOW
DATA SHEET BASED ON OPERATION LOG SHEET
STEP- 4 :
MONTH MILL#1C classifier temp lo.
JANUARY 0
FEBRUARY 0
MARCH 3
APRIL 4
MAY 6
JUNE 10
JULY 7
AUGUST 3
SEPT EMBER 4
OCT OBER 1
NOVEMBER 0
DECEMBER 0
TOTAL 38
DATA COLECTED BY
MR.H.K.UDAN &
MR.S.K.SAHOO
STEP- 5 :
MACHINE MAN FACILITY NOT
PROVIDED
PA HEADER MIXED AIR GATE
MISTAKE BY OPERATOR
TEMPERATU OPENING PROBLEM
RE LOW
INSUFFICIENT TRAINING
MALFUNCTIONING OF
HOT PA DAMPER INADQUATE KNOWLEDGE
C&I EQUIPMENT
NOT OPENING
NO BARRIER SURROUNDING
MATERIAL PROCEDURE BUNKER TOP OPENING
MALFUNCTION
3 4
OF C&I EQUIPEMENT.
WATER INGRESS 07 07 41 . 2 41 . 2
1 AT BUNKER
FLOOR.
VERY MUCH 05 12 29 . 4 70 . 6
2 WET COAL.
MALFUNCTION 04 16 23 . 6 94 . 2
3 OF C&I
EQUIPEMENT.
HOT PA DAMPER 01 17 5.8 100
4 NOT OPENING.
TOTAL 17 100
CONTRIBUTION OF CAUSES TO THE
PROBLEM ( SHOWN IN %)
5. 8 %
23. 6 %
CAUSE NO-1
41. 2 % CAUSE NO-2
29. 4 %
CAUSE NO-3
CAUSE NO-4
STEP-8 : DEVELOPING SOLUTIONS
PARETO ANALYSIS
17
94.2 100 %
14.825
87.5%
70.6 75%
12.75
FREQUENCY
62.5%
CUMILATIVE %
10.625
41.2 50 %
8.5
37.5%
6.325
25%
4.25 12.5%
2.125
1 2 3 4
CAUSE NO
OF CAUSE NO.1
( TOOLS USED BRAIN STORMING )
OF CAUSE NO.1
TOOLS USED BRAIN STORMING
OF CAUSE NO.2
TOOLS USED BRAIN
STORMING
OF CAUSE NO.3
TOOLS USED BRAIN STORMING
OF CAUSE NO.4
TOOLS USED BRAIN STORMING
FORSEEING THE
STEP-9 : PROBABLE RESISTANCE
Discussed about the problem, its
causes and analysis with our
HOD (O&C)
The proposed solution was
conveyed to him, got verbal
approval to go ahead for trial
implementation.
COMPARATIVE
MILESTONE
NO. ACTIVITY
CHART
TIME in weeks
1 2 3 4 5 6 7 8 9 10 11
12 13 14
1 Defining problem
2 Analysing the problem TARGET ( 12
WEEKS )
3 Identifying the cause ACTUAL ( 13 WEEKS )