MOU WITH GoMP SIGNED : 23rd May06 LAND (1310 Ha) APPLICATION MADE : 29TH Nov06 MOEF CLEARNACE : 18th Mar09 HEARING OF 4 VILLAGES : 14TH MAY09 AWARD/LAND COMPENSATION (TWO VILLAGES)TO VILLAGERS : 20TH MAY & 4TH JUN09 EARTH WORK STARTED : 9TH JUL09 (65% Achieved) CIVIL WORK STARTED IN BTG AREA : 25TH AUG09 (50% Achieved) STRUCTURAL ERECTION STARTED IN BTG AREA : 22TH FEB10 (IN PROGRESS) SEZ REQUIREMENT (>100 Ha CONTIGUOUS LAND) ACCEPTED : 1ST OCT09 PRIVATE LAND UNDER POSSESSION - 753 Ha : AS ON TODAY TOTAL GOVT LAND - 197 Ha : 137 Ha.,POSSESION CLEARED LAND POSSESSION FOR GIDHER & ORGARI : BY IIND WEEK OF NOV.10 FIVE INFRASTRUCTURAL PROJECTS : UNDER PROGRESS RAIL NETWORK : 30 KM. : WORK STARTED OUTSIDE PLANT ALSO 220 KV TRANSMISSION LINE : 75 KM : MATERIALS BEING RECEICVED 4600 CUM/Hr. WATER DRAWL & TRANSPORT.SCH.( 39 KM): PIPE LAYING IS IN PROGRESS APPROACH ROADS : 2 NOS. : SECTION - 17 COMPLETED TOWNSHIP PROJECT : CONSULTANT FINALISED/ WORK START OCT10 ZERO DATE FOR CPP( LOI ON BHEL) : 19TH MAR09 TARGET DATE FOR 1ST UNIT COMMISSIONING : 18TH MAR11
4
Transfer of Govt. land in favour of HINDALCO of two villages i.e. Bareniya & Dhaurar (137.82 Ha), including a Waterbody, have been cleared on 29.06.10 & 05.08.10 respectively by Cabinet Committee, Bhopal (M.P.).
Land required for Rail Corridor, Approach Road and Intake Well aprox. 28 Ha ( 23.77 Ha Pvt. + 5 Ha Govt.) of 5 Villages ( Second Set of Application): Advanced possession clearance received ob 13.07.10. For Coal loading siding at Jamgari, near mines, application for land acquisition is under progress with Chief Secretary, Bhopal for clearance of Section 4 & Section 17. Requirement of Private Land is 25.96 Ha & Govt. Land is 9.10 Ha.
Balance Govt. land possession of Village Gidher & Orgari (55.66 Ha) to be over by end of Nov.10.
5
CONTD..
FOR WATER PIPE LINE & 33kV T/L CORRIDOR- 15m wide (10 Km.
FOREST AND 30Km GOVT. AND PRIVATE LAND) B. APPROX. 270 Ha LAND (77 KM. IN LENGTH) OF 49 VILLAGES IS REQUIRED
TG FOUNDATION
BOILER FOUNDATION TG FOUNDATION
30.06.10
13.02.10 YET TO BE DONE
BOILER FOUNDATION
TG FOUNDATION BOILER FOUNDATION
28.04.10
01.06.10 19.06.10
TG FOUNDATION
BOILER FOUNDATION CHIMNEY CHIMNEY CHIMNEY
YET TO BE DONE
YET TO BE DONE 86 Mtrs. 52 Mtrs. RAFT CASTING DONE
7
Activity
Boiler erection starts Drum Lifting
Actual Start
22.02.10 Not achieved
delay
More than 1 month More than 2 months
Progress of erection done (upto Drum Lifting)by BHEL Till date : 40.78%
SN o. Activity 22nd Feb -Mar10 Plan Actual Apr10 Plan Actual Plan May10 Actual Jun10 Plan Actual Plan Jul10 Actual Plan 5th Aug10 Actual
1.
263
91 (8.7%)
263
55
(11.8%)
263
95
(20.8%)
263
114
(31.7%)
59 (37.3%)
I. Non-availability of BHEL site incharge on regular basis. II. Late engagement of erection contractor. III. Delay in jobsiting of cranes. IV. Lack of coordination between Site incharge and Boiler erector needing frequent rework. V. Workmen unrest due to payment issue. VI. Non-sequence of material for erection. VII. Heavy rains restricting movement of heavy machinery
1. Deputation of senior persons. 2. Increase of manpower at site. 3. Jobsiting of wooden sleepers, MS plates for cranes and Tools and Tackles. 4. Improvement in Materials management. 5. Sequential supply of material as per erection need. 6. Speedy resolution of engineering and supply issues. 7. Lifting of Unit #1 drum by 22nd Aug.10. (?) 8. Mobilization of TG contractor by 16th Aug.10. (?)
10
11
Outward material
1. 0.36 MTPA Aluminium Ingots
PHASE-1
45.12 Cusec. Of water from Gopad River to Plant (38.5 KM) Agreement with WRD Design & Engineering DCPL Order placement to M/s Simplex Work Schedule : Detailed Engineering started Supply started Execution started Erection & Construction completion Execution till date
INTAKE WELL
1. Design 2. Construction Start 3. Execution till date : Already completed : 06.06.2010 : 2 Mtrs. Out of 14 Mtrs.
13
14
Concrete S Curve
50 000 45 000 40 000 35 000 30 000 25 000 PLANNED QUANTITY 20 000 15 000 10 000 ACHIEVED QUANTITY 5 000
Sep-09
Planned quantity Actual achieved qty Sep-09 125 96
Oct-09
Oct-09 325 299
Nov-09 Dec-09
Nov-09 1 525 1549 Dec-09 3 525 4580
Jan-10
Jan-10 6 025 7580
Jul-10
Jul-10 33 025 39938
Aug-10
Aug-10 36 525
Sep-10
Sep-10 39 525
Oct-10
Oct-10 42 025
Nov-10
Nov-10 42 925
15
Description
Boilers cum Steam Turbine Generator Package (BTG) Site Grading & Storm Water Drainage system Structural work in Power House & Mill Building RCC Chimney Raw Water Reservoir 220 KV Switch yard Coal Handling Plant Cooling Tower Ash Handling System Station Transformer Generator Transformer Unit Transformer EOT Crane 220 KV Transmission Line DM & Raw PT Plant Civil work in Power House & Mill Building Water Drawl System General Civil, Structural & Architectural work for Auxiliary Building, BHEL
Supplier
Mistry Enterprises Ltd. Larson & Tubro Ltd. Larson & Tubro Ltd. K.N. International ABB Ltd. Larson & Tubro Ltd. Paharpur Cooling Towers Mecawber Beekay Crompton Greaves BHEL Crompton Greaves Anupum Cranes Kailash Constructions Thermax Simplex Infrastructure Simplex Infrastructure Simplex Infrastructure
19
OTHERS
TOTAL
63.10
3710.00
16
KEY ACTIVITIES PLANNED UPTO OCTOBER10 1. CONSTRUCTION OF PH BUILDING ROOF, TG FLOOR ETC. FROM COLUMN 1 TO 13 (UNIT #1). 2. COMMISSIONING OF 2x135 T EOT CRANES. 3. START OF ERECTION OF CONDENSER. 4. BOILER #1 DRUM LIFTING & PRESSURE PART ERECTION. START OF BOILER #2 AND #4 ERECTION 5. INSTALLATION OF CHP CRUSHERS. 6. COMPLETION OF FOUNDATIONS OF 220KV SWITCHYARD. 7. INTERNAL BOUNDARY WALL, ROADS & DRAINS. 8. O&M AND STATION BUILDING COMPLETION (75%) 9. ROB CONSTRUCTION START 10. START TRANSMISSION LINE ERECTION (Ist SEP.10) 11. TOWNSHIP PLAN FINALISATION 12.START YOUNG MANAGERS APPARTMENT CONSTRUCTION
17
18
UNIT #1, TG DECK CASTING COMPLETED ON 23.07.10 TG #6 RCC RAFT COMPLETED ON 30.07.2010
20