Академический Документы
Профессиональный Документы
Культура Документы
Project Management Theory Project Value Rolled Throughput Yield Cost of Poor Quality
Instructor: Brian Edelman
Philosophy
Stop me immediately when a concept is unclearodds are, if you are confused about something, at least one other person in the room is also. I will either:
Try to rephrase/clarify the point Ask you to hold on for a few moments until we get to a downstream slide Defer it to 1:1 discussion.
Project Closure
Deliverables
Problem StatementA single paragraph that captures the pain the organization feels from the problem and what the Six Sigma project will do to improve it. ObjectiveThis lists the primary metric and the degree to which the project will improve the metric. As a baseline, improvement is typically targeted at 70% improvement from current status. After the completion of the Define phase, this is the contract for successful project completion.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
Deliverables (continued)
BenefitsThis item is not the primary metric and goal of the project, but instead is a listing of the benefits that will accrue from achieving the goal.
Financial ImpactsWhat is the bottom line improvement to the organization? OthersMay include floor space, goodwill, TGW reductions, or other soft savings. Memo: Hard savings are generally things that will hit the bottom line. As a rule of thumb they can be entered into the Cost Savings System (CSS). Soft savings are those things that may enable savings later but do not immediately affect the bottom line.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
Deliverables (continued)
TeamTo successfully complete the Define phase of a Six Sigma project requires that a preliminary team be identified. This team must include a representative from the local controllers office, as well as all key stakeholders in the process.
Deliverables (continued)
Process Sponsor/Process OwnerThe manager who will own the process once the project is complete. He/she is responsible for making sure Visteon sustains the gain from the Six Sigma project once the project team completes its work.
10
Problem Statement
A well-crafted problem statement is key to successful project completion. It must align with the project objectives and metrics. Example:
Problem Statement: Defects on Line 1 have averaged 121,000 ppm for the last four months. This does not allow us to meet our corporate cost and quality objectives Objective: Reduce ppm on Line 1 from an average of 121,000 ppm to 50,000 ppm by July 1, 2002.
11
12
Project Closure
The project can be closed when it is verified that the goals/objectives for the project have been achieved. The most recent closure procedures are available on the Six Sigma website. (Home page: http://hub.visteon.com/6sigma/) Project closure requires approval of the Black Belt, the Project Champion, the responsible Finance Analyst/Controller, and the divisional Deployment Director. Certification requires two successfully closed projects, demonstrated competency in a statistical proficiency examination, and recommendation of the divisional Deployment Director.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
13
14
Project Scheduling
Once a project scope has been established, a schedule of work can be developed. Typically, a series of tasks is identified, along with the precedence relationships, constraints, and who is responsible This list of tasks needed to accomplish the project is sometimes called the Work Breakdown Structure (WBS).
15
16
w4 27-Aug
17
18
19
20
21
22
23
24
+ + +
0 0 0
= = =
6 2 4
28
The latest early finish date of a predecessor is the early start date of the successor
29
30
+ +
7 8
= =
8 9
31
The late finish is the latest time a task can finish without slipping the project.
33
9-1=8
9 8
34
35
8-1=7
36
37
Float (or Slack) = Late Finish 6 7 Early Finish 7 6 = Late Start Early Start
7 8 8 9 8 9 7 8
38
39
0
4 2
2 0 Tasks with zero float 4 are on the Arrange 0 Personnel critical path. If they Hold Event slip, the 1 project 6 completion slips.
Select Candidates
Follow Up
1
1
7
8
8
9
8
9
7
8
0 0 0
40
Reserve facility (6 weeks) Start Get brochures, etc. (2 weeks) Hold event (1 week) Select Candidates (1 week) Follow Up (1 week) Done
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
41
42
PERT (continued)
PERT assumes a probability distribution for possible durations. As a practical matter, PERT uses optimistic, pessimistic, and most-likely durations as inputs to the calculation.
Best way to get these estimates is simply to talk with people who have completed similar projects.
PERT-type algorithms then use a weighted average duration. (optimistic 4 * most _ likely pessimistic) duration 6
43
Examples
Assume were in charge of building the new Visteon headquarters.
We have a series of high-level tasks and weve identified their precedence relationships. We have also determined what a best-case, realistic, and worst-case duration for each step is.
44
Examples (cont.)
Task ID Description Predecessors Best-case duration 0.2 years 1 year 0.1 years 0.3 years 0.1 years 0.7 years 0.3 years Likely Duration 0.75 years 1.5 years 0.1 years 0.4 years 0.3 years 0.9years 0.4 years Worst-case Duration 2 years 2.5 years 0.3 years 0.5 years 0.4 years 1.0 years 1.0 years Weighted Average Duration Std. Dev (Worst Best) / 6
A B C D E F G
Select Site Design building Obtain permits Contract builders Arrange financing Build headquarters Pay contractors
none A B B B C, D, E F
45
Examples (cont.)
Task ID Description Predecessors Best-case duration 0.2 years 1 year 0.1 years 0.3 years 0.1 years 0.7 years 0.3 years Likely Duration 0.75 years 1.5 years 0.1 years 0.4 years 0.3 years 0.9years 0.4 years Worst-case Duration 2 years 2.5 years 0.3 years 0.5 years 0.4 years 1.0 years 1.0 years Weighted Average Duration Std. Dev (Worst Best) / 6
A B C D E F G
none A B B B
0.87 yr.
Arrange financing
0.2 4*0.75 2 6
C, D, E F
0.87
46
Examples (cont.)
Task ID Description Predecessors Best-case duration 0.2 years 1 year 0.1 years Likely Duration 0.75 years 1.5 years 0.1 years Worst-case Duration 2 years 2.5 years 0.3 years 0.5 years 0.4 years 1.0 years 1.0 years Weighted Average Duration Std. Dev (Worst Best) / 6
A B C D E F G
Select Site Design building Obtain permits Contract builders Arrange financing Build headquarters Pay contractors
none A B B B C, D, E F
0.87 yr. 1.58 yr. 0.13 yr. 0.4 yr. 0.28 yr. 0.88 yr. 0.48 yr.
47
Exercise
Task ID Description Predecessors Best-case duration 0.2 years 1 year 0.1 years 0.3 years 0.1 years 0.7 years 0.3 years Likely Duration 0.75 years 1.5 years 0.1 years 0.4 years 0.3 years 0.9years 0.4 years Worst-case Duration 2 years 2.5 years 0.3 years 0.5 years 0.4 years 1.0 years 1.0 years Weighted Average Duration 0.87 yr. 1.58 yr. 0.13 yr. 0.4 yr. 0.28 yr. 0.88 yr. 0.48 yr. Std. Dev (Worst Best) / 6
A B C D E F G
Select Site Design building Obtain permits Contract builders Arrange financing Build headquarters Pay contractors
none A B B B C, D, E F
Exercise: Draw the network diagram and find the critical path.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
48
ExerciseNetwork Diagram
Obtain Permits
Select Site
Design Building
Contract Builders
Build HQ
Pay Contractors
Arrange Financing
49
ExercisesCritical Path
Task ID Description Predecessors Weighted Average Duration 0.87 yr. 1.58 yr. 0.13 yr. Early Start Early Finish 0.87 2.45 2.58 Late Finish Late Start Float
A B C
Select Site Design building Obtain permits Contract builders Arrange financing Build headquarters Pay contractors
none A B
0 0.87 2.45
0 0.87 2.72
0 0 0.27
D E F G
B B C, D, E F
0 0.12 0 0
50
ExercisesCritical Path
Task ID Description Predecessors Weighted Average Duration 0.87 yr. 1.58 yr. 0.13 yr. Early Start Early Finish 0.87 2.45 2.58 Late Finish Late Start Float
A B C
Select Site Design building Obtain permits Contract builders Arrange financing Build headquarters Pay contractors
none A B
0 0.87 2.45
0 0.87 2.72
0 0 0.27
D E F G
B B C, D, E F
0 0.12 0 0
51
ExerciseCritical Path
Obtain Permits
Select Site
Design Building
Contract Builders
Build HQ
Pay Contractors
Arrange Financing
52
Examples (cont.)
From the exercise, the overall duration is the sum of the expected durations on the critical path.
Overall duration = 0.87 + 1.58 + 0.4 + 0.88 + 0.48 = 4.21 years.
To determine the variability in the critical path estimate, we assume that the durations of each task are statistically independent of the durations of the others.
53
Examples (cont.)
Because variances (2) of independent random events are additive,
2 overallproject
Variance is the square of the standard deviation, which, for each event, is calculated as:
54
Examples (cont.)
Task ID Description Predecessors Best-case duration 0.2 years 1 year 0.1 years 0.3 years 0.1 years 0.7 years 0.3 years
Worst-case Duration 2 years 2.5 years 0.3 years 0.5 years 0.4 years 1.0 years 1.0 years
Weighted Average Duration 0.87 yr. 1.58 yr. 0.13 yr. 0.4 yr. 0.28 yr. 0.88 yr. 0.48 yr.
Std. Dev (Worst Best) / 6 0.3 yr. 0.25 yr. 0.03 yr 0.03 yr. 0.05 yr. 0.05 yr. 0.12 yr.
A B C D E F G
Select Site Design building Obtain permits Contract builders Arrange financing Build headquarters Pay contractors
none A B B B C, D, E F
55
Examples (cont.)
Because variances (2) of independent random events are additive,
2 overallproject
2 overallproject 2 overallproject
0.17
overallproject 0.41
Note: Be careful to add the variances, not the standard deviations.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
56
Examples (cont.)
With the expected value and standard deviation of the critical path, one can use basic statistics to determine the probability that a project will be completed within a certain length of time.
Well cover Continuous Distributions in Week Two. Well practice this application in Week Four.
57
Compression
Compression involves finding ways to shorten the duration of a project without changing its scope.
Crashing: Compressing timing by looking at cost and schedule tradeoffs to determine how to reduce the most time for the least money. Fast tracking: Doing activities in parallel that are normally done sequentially. This reduces timing at a significant risk of rework.
58
Crashing
By spending extra money to reduce timing on critical path items, overall project completion timing can be reduced. For purposes of the exam, it will be necessary to know the cost per unit time to crash each activity.
ID Predecessors Normal Time Crash Time Cost per Week to Crash
$8,000 $10,000 $1,000 $3,500 $25,000
59
A B C D E
none A A B C and D
Crashing (cont.)
Questions asked typically include:
Project cost and duration without crashing. Project cost and duration at maximum crashing. Project cost and duration for minimum cost project.
For non-crash situations, the critical path analysis will give project duration, and the cost per unit time of the project can be used to determine its total cost.
60
Exampleno crashing
Assume it costs $15,000 per week for a given project. Also, assume the information below. Find the non-crashed duration and cost.
ID Predecessors Normal Time
4 weeks 5 weeks 3 weeks 6 weeks 8 weeks
Crash Time
1 week 2 weeks 2 weeks 4 weeks 3 weeks
A B C D E
none A A B C and D
ExampleNetwork Diagram
B A C
62
Exampleno crashing
ID Normal Time
4 weeks 5 weeks 3 weeks 6 weeks 8 weeks
Early Start
0 4 4 9 15
Early Finish
4 9 7 15 23
Late Finish
4 9 15 15 23
Late Start
0 4 12 9 15
Float
A B C D E
0 0 8 0 0
63
Exampleno crashing
Duration is 23 weeks without crashing. Cost is $15,000 per week x 23 weeks = $345,000
64
Crashing
For a maximum crashing situation, it is necessary to determine which critical path task has the least crash cost per unit time.
This task is crashed to the maximum it can be until the critical path changes. If the critical path has not changed, the next least expensive crash cost on the critical path is chosen and the above step is repeated. If the critical path changes, the new critical paths are identified. The least expensive crash costs for each critical path are identified. These are reduced to the point the critical path changes. Note that if one task is on both critical paths, it is not counted twice when tallying crash costs.
65
Crashing (cont.)
This continues until no further crashing is possible for items on the critical path(s). The result is the maximum crash condition.
66
ExampleMaximum crashing
Find the maximum crash duration and cost for the prior example.
67
ExampleMaximum crashing
ID Normal Time
4 weeks 5 weeks 3 weeks 6 weeks 8 weeks
Early Start
0 4 4 9 15
Early Finish
4 9 7 15 23
Late Finish
4 9 15 15 23
Late Start
0 4 12 9 15
Float
A B C D E
0 0 8 0 0
68
ExampleMax Crash.
B A C
69
ExampleMaximum crashing
ID Predecessors Normal Time
4 weeks 5 weeks 3 weeks 6 weeks 8 weeks
Crash Time
1 week 2 weeks 2 weeks 4 weeks 3 weeks
A B C D E
none A A B C and D
70
ExampleMaximum crashing
ID Predecessors Normal Time
4 weeks 5 weeks 3 weeks 6 weeks 8 weeks
Crash Time
1 week 2 weeks 2 weeks 4 weeks 3 weeks
A B C D E
none A A B C and D
71
ExampleMaximum crashing
ID Normal Early Early Late Late Time Start Finish Finish Start There is eight weeks of float on all of the non-critical path items, so we know the 4 weekspath0will not 4 4 shorted 0 critical change if we 5 weeks 4 4 task D by92 weeks. 9
3 weeks 6 weeks 8 weeks 4 9 15 7 15 23 15 15 23 12 9 15
Float
A B C D E
0 0 8 0 0
72
ExampleMaximum crashing
ID Predecessors Time Crash Time
1 week 2 weeks 2 weeks 4 weeks 3 weeks $25,000
Task D is crashed. The critical path doesnt change. We find the next least expensive critical path item to crash. This is task A.
A B C D E
none A A B C and D
73
ExampleMaximum crashing
ID Predecessors Time Crash Time
1 week 2 weeks 2 weeks 3 weeks
A B C D E
none A A C and D
74
ExampleMax Crash.
B A C
A is on all the paths, so crashing it will not change the critical path.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
75
ExampleMaximum crashing
ID Predecessors Time Crash Time
1 week 2 weeks 2 weeks 4 weeks 3 weeks $25,000 $10,000 $1,000
Task A is crashed 3 weeks.. We find the next least expensive critical path item to crash. This is task B.
A B C D E
none A A B C and D
76
ExampleMaximum crashing
ID Predecessors Time Crash Time
1 week 2 weeks 2 weeks 4 weeks 3 weeks $25,000 $10,000 $1,000
A B C D E
none A A B C and D
77
ExampleMaximum crashing
ID Normal Time
1 week 5 weeks 3 weeks 4 weeks 8 weeks
Early Start
0 1 1 6 10
Early Finish
1 6 4 10 18
Late Finish
1 6 10 10 18
Late Start
0 1 7 6 10
Float
A B C D E
0 0 6 0 0
The only non-critical path task has 6 weeks of float, so crashing task B will not change the critical path.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
78
ExampleMaximum crashing
Task B is fully crashed. The next least ID Predecessors Time Crash expensive task on the critical path is Task E, which can be crashed up to 5 weeks. Time
A B C D E
none A A B C and D
79
ExampleMax Crash.
B A C
E is on all the paths, so crashing it will not change the critical path.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
80
ExampleMaximum crashing
Task E is crashed as much as possible. The ID only task Predecessors Time now is Crash that is able to be crashed Time task C, which is not on the critical path. We are at the maximum crash condition. A B C D E none A A B C and D 1 week 2 weeks 3 weeks 4 weeks 3 weeks 1 week 2 weeks 2 weeks 4 weeks 3 weeks $1,000
81
ExampleMaximum crashing
ID Normal Time
1 week 2 weeks 3 weeks 4 weeks 3 weeks
Early Start
0 1 1 3 7
Early Finish
1 3 4 7 10
Late Finish
1 3 7 7 10
Late Start
0 1 4 3 7
Float
A B C D E
0 0 3 0 0
82
ExampleMaximum crashing
Our project duration is now calculated at 10 weeks. Our project crash costs are:
Task
A B D E
TOTAL:
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
$186,000
83
ExampleMaximum crashing
The crashing costs were $186,000. This is added to our ongoing project costs. Ongoing project costs = 10 weeks duration x $15,000 per week = $150,000 Our total project cost was $336,000. Note that this amount may be more or less than the normal project duration costs.
84
CrashingMinimum cost
To determine the minimum cost project, an iterative approach is used. The premise of this technique is that ongoing costs of the project ($x/month) are more than some of the costs to crash tasks ($y/month). By selectively identifying the tasks that reduce total cost, the project cost is optimized.
85
Crashing (continued.)
Procedure for the least cost project:
1. Identify all of the critical paths. 2. Identify the tasks on the critical path(s) that have a lower crash cost than the ongoing cost of the project. 3. Choose the least crash cost task(s) that reduce all of the critical paths (and therefore the project). The total crash cost (per unit time) of these must be less than the ongoing project cost. If not, no further cost reductions are possible. 4. Crash them until they can no longer be crashed or until the critical path changes. 5. Repeat steps 2 through 5.
86
ExampleMinimum cost
Using the prior example, find the minimum cost duration. How much does this cost?
87
ExampleMinimum cost
ID Predecessors Normal Time
4 weeks 5 weeks 3 weeks 6 weeks 8 weeks
Crash Time
1 week 2 weeks 2 weeks 4 weeks 3 weeks
A B C D E
none A A B C and D
88
ExampleMinimum cost
ID Predecessors Normal Crash Time Time It can be crashed 2 weeks, and the critical path (based on the last none 4 weeks 1 week exercise) will not change.
A A B C and D 5 weeks 3 weeks 6 weeks 8 weeks 2 weeks 2 weeks 4 weeks 3 weeks
A B C D E
89
ExampleMinimum cost
ID Predecessors Normal Time
4 weeks 5 weeks 3 weeks 6 weeks 8 weeks
Crash Time
1 week 2 weeks 2 weeks 4 weeks 3 weeks
A B C D E
none A A B C and D
With an ongoing project cost of $15,000 per week, any crash in Task D (as long as Task D remains on the critical path) will reduce total cost.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
90
The next least expensive critical path item is TaskNormal A. ID Predecessors Crash Time Time
A B C D E none A A B C and D 4 weeks 5 weeks 3 weeks 4 weeks 8 weeks 1 week 2 weeks 2 weeks 4 weeks 3 weeks
91
From the prior exercise, we know the critical path Example Minimum cost will not change if task A is crashed. As $8,000
ID
crash cost is less than the $15,000 ongoing costs, we crash task A as much as possible. Predecessors Normal Crash
Time
A B C D E none A A B C and D 4 weeks 5 weeks 3 weeks 4 weeks 8 weeks
Time
1 week 2 weeks 2 weeks 4 weeks 3 weeks
92
ExampleMinimum cost
ID Predecessors Normal Time
1 week 5 weeks 3 weeks 4 weeks 8 weeks
Crash Time
1 week 2 weeks 2 weeks 4 weeks 3 weeks
A B C D E
none A A B C and D
Task B is the next least expensive critical path item. It can be crashed 3 weeks and (from the prior exercise) will not change the critical path.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
93
ExampleMinimum cost
ID Predecessors Normal Time
1 week 5 weeks 3 weeks 4 weeks 8 weeks
Crash Time
1 week 2 weeks 2 weeks 4 weeks 3 weeks
A B C D E
none A A B C and D
Task Bs crash costs are less than the ongoing project costs, so it is crashed as much as possible.
94
The only remaining critical path item is task E, Example Minimum cost which has a crash cost higher than the ongoing cost of the project. Therefore, no further cost ID Predecessors Normal Crash reductions are possible on this project.
Time
Time
A B C D E
none A A B C and D
95
ExampleMinimum cost
ID Normal Time
1 week 2 weeks 3 weeks 4 weeks 8 weeks
Early Start
0 1 1 3 7
Early Finish
1 3 4 7 15
Late Finish
1 3 7 7 15
Late Start
0 1 4 3 7
Float
A B C D E
0 0 3 0 0
96
ExampleMinimum cost
Our project duration is now calculated at 15 weeks. Our project crash costs are:
Task
A B D TOTAL:
97
ExampleMinimum cost
The crashing costs were $61,000. This is added to our ongoing project costs. Ongoing project costs = 15 weeks duration x $15,000 per week = $225,000 Our total project cost was $286,000 (versus $345,000 for the non-crashed project). Note that more complex examples will result in multiple critical paths.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
98
Project Management
That concludes the section on Project Management. Any questions?
99
Project Value
Also known as Finance 101
100
Project Value
Evaluation of a project must take account of the time value of money. The premise behind time value of money is that $1 today is worth more than $1 tomorrow. Why?
Inflation. Lost investment opportunity.
101
102
Value today is generally called the present value or net present value of the decision. Payback period (or simply payback) is the length of time it will take the company to recoup its investment.
103
104
Each years savings get discounted back into todays dollars to determine the value of the project.
Value today Year 1 Savings Year 2 Savings Year 3 Savings 2 3 1 r 1 r 1 r
105
$ (000s)
0 Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 -500 -1000 -1000 -1500
106
A NPV - Investment r
In our example, the net present value is:
107
108
If this was greater than or equal to the organizations hurdle rate, this project would be considered a good investment.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
110
111
Note that both the rate and the number of periods must be in the same time units (in this case, months) as the payment schedule.
112
Project Value
Any questions?
113
114
Where: Where: Y Y= =Yield Yield S S= =Number Numberof ofUnits Unitsthat thatPass Pass U U= =Number Numberof ofUnits UnitsTested Tested
1.01 0.99
Y.
Y.
0.97 0.95 1 4 7 10 13 16 19
115
.09 Data Courtesy of Asea Brown Boveri, Ltd. .09 Each data point is a factory .08 Y.FT = 1- Failure Rate .08 .07 .07 .06 .06 .05 .05 .04 .04 S .03 S .03 .02 .02 .01 .01 0 0 0 .025 .05 .075 .1 .125 .15 .175 .2 .225 -.03 -.03 0 .025 .05 .075 .1 .125 .15 .175 .2 .225 Failure Rate Failure Rate Rate Scrap Rate Scrap
Test Room Failure Rate Test Room Failure Rate
116
A
100 Units
20 Units
65 Units
First Time Yield is Process Yield Without Rework Rework is the Hidden Factory
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
117
Y First Time
Data Courtesy of Texas Instruments, DSEG
1.02 1.00 .98 .96 .94 .92 .90 .88 .86 .84 .82 .80 2.4
2.8
3.2
3.6
(Sigma)
4.0
4.4
Process Capability
118
95.5% Yield
Following Receiving Inspection and Line Fall-out...
97% Yield
45,000 PPM wasted From Machining Operations
94.4% Yield
At Test Stands on first attempt 21,965 PPM wasted 46,652 PPM wasted
85 units
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
Rev. 1.1 1/99
120
100/100=1
90/100=.9
1 x .9 x .97 x .98
87/90=.97
85 %
85/87=.98 85 units
First Time Yield (YFT) Gives Credit Only for Product not scrapped the First Time
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
121
Step 2
YFT = 70%
Step 3
YFT = 90%
YRT = (.80)(.70)(.90) = .504 = 50.4% Rolled Throughput Yield is the probability that any given part will go through the process with zero defects (no rework)
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
122
83/93=.89 10
Scrap 3
63 %
123
s N
Rework
Scrap
Rolled Throughput Yield can also be stated in terms of average defects per unit (dpu)
124
Op 1
Process Centered
Op 2
Output 98%
Without Inspection or Test
99%
Without Inspection or Test
99%
Without Inspection or Test
Y RT
OR = e
DPU
There are two operations (OPs) for a unit, and each OP has a 0.01 probability of a defect. Therefore: DPU = 2 OPs per unit x .01 defect per OP = .02 defects per unit e
-.02
= .98019 or 98%
125
Complexity
(Distribution Shifted 1.5 )
# of Parts (Steps)
1 7 10 20 40 60 80 100 150 200 300 400 500 600 700 800 900 1000 1200 3000 17000 38000 70000 150000
Process 4 Capability
3
93.32% 61.63 50.08 25.08 6.29 1.58 0.40 0.10 -----------------
5
99.9767% 99.839 99.768 99.536 99.074 98.614 98.156 97.70 96.61 95.45 93.26 91.11 89.02 86.97 84.97 83.02 81.11 79.24 75.88 50.15 0.02 ----
6
99.99966 99.9976 99.9966 99.9932 99.9864 99.9796 99.9728 99.966 99.949 99.932 99.898 99.864 99.830 99.796 99.762 99.729 99.695 99.661 99.593 98.985 94.384 87.880 78.820 60.000
99.379% 95.733 93.96 88.29 77.94 68.81 60.75 53.64 39.38 28.77 15.43 8.28 4.44 2.38 1.28 0.69 0.37 0.20 0.06 ------
Complexity
(part count or process steps)
Rolled Yield
4 capability in each of 100 steps produces a rolled throughput yield of .99379 to the 100th power = 0.5254 or 52.54%
126
Complexity
Is Complexity better?
NO!
The GOAL is to REDUCE the number of opportunities and concurrently INCREASE the capability of each opportunity that remains.
127
Formulas to Know
DPU (Defects per unit) = Defects / Unit TOP (Total Opportunities) = Units * opportunities
DPO (Defects per Opportunity) = Defects / TOP Probability the Opportunity is defective = DPO
Pr(ND) (Probability the Opportunity is Not defective) Pr(ND) = 1 - DPO
Rolled Yield ] (The likelihood that any give unit of product will contain 0 defects)
Y RT= Pr(ND) # of Opportunities Y RT = Pr(ND) * Pr(ND) * Pr(ND) *......Pr(ND)
Recommend using when you know the yield for each process element or opportunity
129
# of Units Produced
500
# of Defects
35
# of Successes
465
Y RT = .93
130
131
Hidden Factory
Hidden Factory What is it? Unnecessary activitiesWe will cover more on this in the Lean Techniques Module. Rework loops.
Learning Exercise ABC Electric has demanded that the quality and timeliness of the invoices received into the Accounts Payable Department be at a 6 level. The CTQ elements for ABC Electric are an invoice where quantity and price match the PO that was submitted. Also, the invoice must be received by ABC Electric within 3 days of shipping for receiving purposes. On the following page are the steps that your invoicing department has put in place to reach the level of quality the customer is expecting.
132
Hidden Factory
No Operator 1 enters the quantity shipped into the data entry system confirmation Pay invoice Does invoice meet CTQ'S? Pay invoice and charge a $10 penalty / invoice No The confirmation is check by Operator 2 for accuracy Was the input accurate? Operator 2 inputs the price of the Product into the system Invoice Yes Customer inspects invoice to determine accuracy of the invoice and if it was received on time. Operator 3 mails invoice to the customer Operator 3 inspects invoice for accuracy Is price correct?
Yes
Yes
No
If no defects were in the system, which activities could be eliminated? How can defects on upstream steps affect downstream steps?
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
133
Hidden Factory
No Operator 1 enters the quantity shipped into the data entry system confirmation Pay invoice Does invoice meet CTQ'S? Pay invoice and charge a $10 penalty / invoice No The confirmation is check by Operator 2 for accuracy Was the input accurate? Operator 2 inputs the price of the Product into the system Invoice Yes Customer inspects invoice to determine accuracy of the invoice and if it was received on time. Operator 3 mails invoice to the customer Operator 3 inspects invoice for accuracy Is price correct?
Yes
Yes
No
If no defects were in the system, which activities could be eliminated? How can defects on upstream steps affect downstream steps?
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
134
Rework
Hidden Factory
Scrap
Each defect must be detected, repaired and placed back in the process. This results in Wasted: Time Money Resources Floor Space
Six Sigma is about identifying/quantifying and eliminating the Hidden Factory through Defect Reduction and ultimately Design for 6 Sigma
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
135
Inputs
Operation Rework
Hidden Factory
Inspect
NOT OK
Scrap
Process
A B
Final Test D
90% Yield
Rolled Yield
90% Yield
81 %
90% Yield
73 %
90% Yield
66 %
Rolled-Throughput Yield
Using final test (or first time) yield ignores the hidden factory. Final test performance is a function of inspection & test not actual defect data.
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
136
Six Sigmas primary metric is Defects per Unit, which is directly related to Rolled Throughput Yield (Yrt) Yrt = e-dpu Cost of Poor Quality and Cycle Time (Throughput) are two other key metrics
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
137
138
Hidden factory costs are insidiousthey become part of the day-to-day business and go unnoticed. Tracking COPQ is not easy with traditional cost accounting systems.
139
those costs incurred because of poor quality that would not have been incurred if every aspect of a product or service were perfectly correct the first time and every time no deficiencies.
-- J. Juran (1989)
140
The hidden cost of failing to meet customer expectations the first time The hidden opportunity for increased efficiency The hidden potential for higher profits The hidden loss in market share The hidden increase in production cycle time The hidden labor associated with ordering replacement material
141
External Failure
Prevention Cost
The modern COPQ model depicted here shows failure costs going to zero at 100% conformance (zero defects). Accordingly, appraisal and prevention costs reach a maximum at zero defects. The total COPQ is obtained by adding the two sets of costs at a given conformance level. Adapted from Jurans Quality Control Handbook (p.4.19), by J.M. Juran and F.M. Gryna (Eds.), 1998, New York: McGray-Hill
0 (100% Defective)
Quality of Conformance, %
143
Visteon
Revenue
Customers
Revenue
Materials, Equipment
waste
waste
waste
COPQ
144
Scrap
Quality Rejects
145
COPQ Data
Waste, Spoilage, Rejects & Rework As Percent of Sales
Manufacturing Industry
Poor Quality Cost as Percent of Sales Low High Median Profits as Percent of Sales
Aluminum Die Castings Aluminum Extruded Products Bolts, Nuts, Rivets & Washers Foundries: Aluminum Forgings-Nonferrous Metal Stampings Steel Wire & Related Products Automotive Stampings Electronic Components Industrial Machinery Metal-Cutting Machine Tools Motor Vehicles, Parts Plastics Products Screw Machine Products
Visteon Corporation BB Mod #2 Program Management Rev 3.1 9/03.
4.3 4.4 5.2 5.2 5.9 5.9 5.9 4.3 6.3 7.0 6.1 6.1 6.9 5.3
7.1 7.0 7.1 7.3 6.9 7.2 7.2 7.0 8.2 8.2 7.2 8.1 7.8 7.0
2.3 1.2 2.2 2.9 1.6 3.0 2.9 2.1 4.1 3.6 3.3 2.7 1.5 2.2
Yes
Hidden Factory
148
149
150
Visteon Opportunities
Visteon 4% of sales = $740 Million
10 5 0
Materials
Mfg.
1 0
Materials
Mfg.
152
153
154
155
$1 Billion
$1.2 Billion $0.4 Billion
156
Improvement Initiatives
157
2002 Profits
Volume/Exdhange/Pricing/Econ.
Information Technology
Material Efficiencies
Manufacturing Efficiencies
Restructuring Saving Admin, Selling, Mkt, & Eng. Efficiencies Priceable Design
158
159
Identify/prioritize specific improvement opportunities Initiate improvement projects Keep track of improvement projects
Results as expected? Further opportunities?
160
161
In house:
Supply base:
162
163