Agenda
RF Optimisation
Services Testing & Parameters Optimisation Regular Reference Routes & Stats Analysis Summary
process
Agenda
RF Optimisation
Services Testing & Parameters Optimisation Regular Reference Routes & Stats Analysis Summary
[2] RF Optimisation:
Once clusters of sites are ready, RF Optimisation can be started in order to and minimise interference and pilot
pollution.
Causes of any failures must be identified and whenever necessary relevant parameters should be optimised.
No
RF Optimisation
Re-optimisation Needed?
No
Agenda
RF Optimisation
Services Testing & Parameters Optimisation Regular Reference Routes & Stats Analysis Summary
No
RF Optimisation
Re-optimisation Needed?
No
Objectives:
Tools:
Scanner + UE
Process:
A detailed check list of various tests must be conducted. Tests will include: call setups, reselection, handover, LA/RA
If unusual low signal strength should check wrong feeder connection (Tx/Rx main antenna, Rx diversity antenna), etc.
Site Name: Site Connected to RNC: Site Expanded from: Site Migrated from RNC: Activity/Process New
Frequency and Scrambling Code correctly defined Cell selection and reselection parameters are as planned ( SIB 3 ) The LAC/RAC is correctly defined ( SIB 1 ) The neighbor list and parameters are as planned ( SIB 11 ) LA update proceduce is checked Cell reselection from 3G to 2G is checked Cell reselection from 2G to 3G is checked MO-SMS and MT-SMS CPICH_RSCP > -85 dBm near site CPICH_EcIo > -8 dB near site Mobile terminating calls and mobile originating calls for voice service is checked The voice service quality is good by the engineer feeling Mobile terminating calls and mobile originating calls for VP service is checked The VP service quality is good by the engineer feeling PS attach is checked PS detach is checked PS PDP activation and deactivation is checked The PS service quality is good by the engineer feeling RA update proceduce is checked Soft handover for voice service to and from the 3G cells checked OK Soft handover for VP service to and from the 3G cells checked OK Soft handover for PS service to and from the 3G cells checked OK Inter-system handover for voice service to the 2G cells checked OK Installed antenna is of the planned type Overall performance and coverage area as expected by a brief drive test Antenna Swapping Test
Others
Remarks
Gen
Handover
PS
Connection Mode
Idle Mode
Signature: Signature:
Data: Data:
Notes: If the item is OK, mark the '' on the ''; If the item is not OK, mark the '' on the ''; If the item is not checked, mark the '' on the ''.
Agenda
RF Optimisation
Services Testing & Parameters Optimisation Regular Reference Routes & Stats Analysis Summary
RF Optimisation
New Sites Integrated
No
RF Optimisation
Services Testing &
Parameter Optimisation
Re-optimisation Needed?
No
Objectives:
1. Optimize CPICH and service coverage & cell dominance 2. Minimize interference & pilot pollution 3. Optimize neighbor list 4. Resolve any RF-related drop calls
Tools:
Process:
Drive survey with a UE initially in a continuous AMR call. Drop calls should be analyzed to determine if the causes are RF related.
Solutions:
Process Flow:
Start Drive Test Identify any RF Issues Identify candidate cells for changes Identify nature of required changes
Data Analysis
No
Problem Resolved?
Yes
End
Pilot Pollution (Pilot pollution table & Estimated Active set size)
Neighbour list verification SHO Performance
Drop Calls
To identify:
To identify:
Areas of poor coverage (i.e. poor RSCP & Ec/Io) Areas of high interference (i.e. high RSCP but low Ec/Io)
Analysis of UL Coverage:
To identify:
UE Tx power.
To identify:
SC 8 9 10 11 12 13 16 17 18 19 20 21 32 35 37 43 48 53 67 80 130
% in Pollution Set 12.9% 10.3% 9.8% 9.7% 9.2% 8.4% 5.9% 5.9% 4.7% 4.6% 4.6% 3.5% 3.4% 2.4% 2.1% 1.2% 0.5% 0.4% 0.2% 0.1% 0.1%
To identify:
Cell
70548
Site
Ajman Central
Latitude
25.41204
Longitude
55.447
%
14.2% 8.0% 5.4% 3.5% 3.1% 3.0% 3.0% 2.1% 1.0% 0.9% 0.3% 0.0% 0.0% 0.0% 0.0% 0.0% 0.0%
Any missing neighbours though analysis scanner data & RNC neighbour list
To identify:
Drop calls
RF Optimisation Solutions
Antenna location
Antenna height Antenna type Site location New site
Analysis
Drive test data (scanner + UE)
Best server scrambling code CPICH RSCP & Ec/Io CPICH Ec/Io UE Tx power Scanner vs. RNC neighbours Scanner active set size Causes analysis
Neighbour list
Agenda
RF Optimisation
Services Testing & Parameters Optimisation Regular Reference Routes & Stats Analysis Summary
No
RF Optimisation
Re-optimisation Needed?
No
Any failures (e.g. call set-up, drop calls, etc) MUST be analysed to determine exact causes
Appropriate
parameters
should
be
identified
for
Raise Defect
Optimise Parameters
No
End
Execute tests Perform detailed analysis (logs as well as network stats) Conclude parameters values that provide optimum trade-offs
Parameters Ranges
Perform Tests
Trade Offs
Analysis Metrics
Agenda
RF Optimisation
Services Testing & Parameters Optimisation Regular Reference Routes & Stats Analysis Summary
No
RF Optimisation
Re-optimisation Needed?
No
Regular drive tests of designated routes should be carried out (e.g. on monthly basis)
To benchmark network performance and user experience (e.g. call setup SR, call drop rate, PS throughputs, etc)
To assess impact of newly introduced RAN features. To monitor the progress of on-going optimisation activities.
To identify poorly performing cells that need investigation to establish underlying cause of poor performance.
Agenda
RF Optimisation
Services Testing & Parameters Optimisation Regular Reference Routes & Stats Analysis Summary
No
RF Optimisation
Re-optimisation Needed?
No