Академический Документы
Профессиональный Документы
Культура Документы
INTEROPERABILITY Tests
IEC 61850 INTEROPERABILITY BETWEEN ABB, ALSTOM and SIEMENS STATUS REVIEW November 2002
IEC 61850
INTEROPERABILITY Tests
IOP11/2002
IEC 61850
INTEROPERABILITY Tests
Best practice used for the implementation with respect to the standard. Phase 1 (P1): Basic functions GOOSE* Phase 2 (P2): Advanced functions
*GOOSE: Generic Object Oriented Substation Event
IOP11/2002 3
IEC 61850
INTEROPERABILITY Tests
Schedule of activities
IEC
Committee draft Committee draft for vote Final draft International Standard International Standard
2000
2001
2002
2003
2004
IEC 61850
2004
2000
2001
2002
2003
Test P2b
Test P2a
IEC 61850
INTEROPERABILITY Tests
What is GOOSE?
GOOSE (Generic Object Oriented Substation Event)
It is a mechanism for the fast transmission of substation events, such as commands, alarms, indications, as messages
A single GOOSE message sent by an IED * can be received and used by several receivers GOOSE takes advantage of the powerful Ethernet and supports real-time behaviour It is used for e.g. tripping of switchgear starting of disturbance recorder providing position indication for interlocking
* IED: Intelligent Electronic Device
IOP11/2002 5
IEC 61850
INTEROPERABILITY Tests
EXAMPLE:
GOOSE message
Ethernet GOOSE Sender Device X
IOP11/2002
IEC 61850
INTEROPERABILITY Tests
GOOSE messages
Network Analyser
IEC 61850
INTEROPERABILITY Tests
IEC 61850
INTEROPERABILITY Tests
Fault Simulation
CB* off
* CB = Circuit Breaker
IOP11/2002
IEC 61850
INTEROPERABILITY Tests
Negative tests
GOOSE message with commands for CB tripping and disturbance recorder starting Configuration: sender Y --> receiver Z not configured
Injection test device
GOOSE Sender Device Y GOOSE Sender Device X Ethernet GOOSE Receiver Device Z
Fault simulation
no reaction
IOP11/2002
10
IEC 61850
INTEROPERABILITY Tests
Positive tests
GOOSE message with commands for CB tripping and disturbance recorder starting Configuration: sender Y --> receiver Z
Injection test device
GOOSE Sender Device Y GOOSE Sender Device X Ethernet GOOSE Receiver Device Z
Fault simulation
CB off
IOP11/2002
11
IEC 61850
INTEROPERABILITY Tests
measured time
Fault CB off
IOP11/2002 12
IEC 61850
INTEROPERABILITY Tests
measured time
Fault CB off
IOP11/2002 13
IEC 61850
INTEROPERABILITY Tests
Optimised
Average
10
15
20
25
30
The transmission time was dependent of today`s software implementation. Bus load or device load had no major effect.
IOP11/2002 14
IEC 61850
INTEROPERABILITY Tests
9
10
11
IOP11/2002
15
IEC 61850
INTEROPERABILITY Tests
Test results
Total tests
Experience from the rejected resp. dismissed test cases was used to improve the IEC 61850 specification and implementation.
IOP11/2002 16
rejected (implementation)
accepted
40 35 30 25 20 15 10 5 0
IEC 61850
INTEROPERABILITY Tests
IEC 61850
INTEROPERABILITY Tests
Conclusion
An important part of the standard was tested successfully 39 cases have been tested within one week The standardisation documents are well defined Three major companies in the substation and substation automation business are on track with their implementation of IEC 61850
IOP11/2002
18