MBR February 14

LATAM: Key Events - Construction


Inka The COD extension was approved by the Energy Ministry-government in February. The CODs extension are: Talara (July 31, 2014) and Cupisnique (August 31, 2014). The negotiations with Vestas related to a second amendment to the EPC contracts were concluded. This amendment was signed at end of February which considers the COD for Talara on June 10th of 2014 and June 30th of 2014 for Cupisnique, it includes the option to reach the COD one month ahead. This will result in an additional bonus payment to Vestas. The reforestation process in Talara is ongoing. The final report about archaeological activities is almost concluded. To complete this process is require to install signaling (in 03 identified archaeological areas) and review the technical information contained in the annexes of the related report. On February, the WTGs internal installation in Talara was concluded and VESTAS will begin to issue the certification about conclusion of mounting in March. On February 25th, in Cupisnique The mounting of WTGs were concluded. The internal installation will be concluded on next weeks. On both sites, we are waiting the BOP equipments arrival as high voltage cable, breakers, and switch yard equipment, expecting to be on site in March.

MBR February 14
LATAM Scorecard of Projects in Construction: Inka (1/2)

Milestones CUP Int. Roads Finish (6m width) CUP Int. Roads Finish (11m width) CUP Bases Excavation Finish CUP Foundations CUP Internal Transmission Grid Start CUP WTG Manufacturing Finish CUP WTG Assembled CUP Commissioning Start TAL Int. Roads Finish (6m width) TAL Int. Roads Finish (11m width) TAL Bases Excavation Finish TAL Foundations TAL Internal Transmission Grid Start TAL WTG Manufacturing Finish TAL WTG Assembled TAL Commissioning Start CUPISNIQUE COD TALARA COD

Previous Month Forecast Apr-13 Apr-13 Apr-13 Jul/13 Apr-13 Jul/13 Jun/13 Aug-13 Apr-13 Apr-13 Apr-13 Jul/13 Apr-13 Jul/13 Jun/13 Aug-13 Feb-14 Feb-14

Current Forecast Nov-13 Nov-13 Apr-13 Nov-13 May 14 Jun-13 Jan-14 Jun-14 Apr-13 Apr-13 Apr-13 Jul-13 May-14 Jul-13 Dec-13 Apr-14 Jul-14 May-14

% of completation 100.0% 100.0% 100.0% 100.0% 0.0% 100.0% 100.0% 0.0% 100.0% 100.0% 100.0% 100.0% 0.0% 100.0% 100.0% 0.0% -

Risks / Opportunities: The COD was approved by the government. The COD extension is Talara (July 31, 2014) and Cupisnique (August 31, 2014 On February 18, 2014, the Forest and Wildlife Technical Administration located in Piura, Peru (ATTFS-Piura) notified Energia Eolica that they had initiated an administrative sanctioning proceeding in connection with alleged unauthorized deforestation activities observed at the Talara project site. On February 25, 2014, Energia Eolica responded to the ATTFS-Piura, providing background on the issue without admitting liability. EESA will seek to meet with officials from ATTFS-Piura to negotiate a favorable disposition and is receiving legal advice on the matter.