Академический Документы
Профессиональный Документы
Культура Документы
PERT/CPM
MANAGEMENT SCIENCE
By
K. Venkaiah Babu MBA., (Ph D)
Science & Humanities Dept.,
Sri Sarathi
Institute of Engineering & Technology
LECTURE OUT LINE
Introduction to Project Management
To understand the project Life Cycle
1. Project Planning 2. W B S
3. Project Scheduling 4. Project Control
To apply tools and technique's
Gantt chart /& Mail stone chart
CPM
PERT & Probabilistic Activity Times
Project Crashing and Time-Cost Trade-off
Describe how CPM / PERT have developed
and merged together to provide a useful
technique for managing projects.
What is Project?
Definition:
“Set of inter-related activities”
Unique, one-time operation activity or effort
to plan, implement, and control the management of
large, one time projects
Application:
Used in Construction, Shipbuilding, Weapons,
Systems Development, etc.
Applies to uncertain technology projects
Applies to variable cost resource allocation
Project Characteristics
Set of Activities
Single unit
General purpose
Building construction
✿
✿
Examples
Examples of
of Projects
Projects
Building construction
New product introduction New!
New!
Improved!
Improved!
9” Nude Sandalfoot
Medium to Tall (B)
No nonsense
Sheer
to
waisthos
panty
e
Examples
Examples of
of Projects
Projects
Building construction
New product introduction
Training seminar
Examples
Examples of
of Projects
Projects
Building construction
New product introduction
Training seminar
Research project
Examples of Projects
Building construction
New product introduction
Training seminar
Research project
S/W development
Planning concert, football games, or basketball
tournaments
Project Scope
Scope statement
A document that provides an understanding,
justification, and expected result of a project
Statement of work
written description of objectives of a project
Work breakdown structure
breaks down a project into components,
subcomponents, and activities
What is Project Management? (PM)
PM is the application of knowledge, skills,
tools and techniques to project activities in
order to meet project requirements.
Project Management…
is an art.
is a science.
Project Control
Project Team
made up of individuals from various areas and
departments within a company
Matrix Organization
a team structure with members from functional
areas, depending on skills required
Mechanism of Planning
Define project objective (SMART)
Define work breakdown structure (WBS)
Identify tasks and subtasks -- deliverables
Lowest element – stand alone work package
Identify tasks relationship
Identify possible risks
Estimate work packages (people, time, etc.)
Create initial schedule
Iterate plan (Procedure)
Document
Benefits of the Planning
without delay
To complete a project with a minimum of capital
investment.
PROJECT MANAGEMENT
PROCESS
Project Management Process
Planning
● Objectives
● Resources
● Work break-
down sched.
● Organization
Project Management Process
Planning Scheduling
● Objectives ● Project
● Resources activities
● Work break- ● Start &
Planning Scheduling
● Objectives ● Project
● Resources activities
● Work break- ● Start &
Controlling
● Monitor, compare,
revise, action
PROJECT PLANNING
Project Planning
Establishing objectives
Defining project
Creating work breakdown
structure (WBS)
Determining resources
Forming organization
Work Breakdown Structure
(WBS)
First Step in Project Management
Begins with a Work Breakdown
Lists the “WHAT’ of a Project
Begins with Finished Project
Consists of Tree Chart, with Each Branch Listing the “WHAT’s” at that Level
Then List Each Task that Must Be Completed to Accomplish the
“WHAT”
Start at top, progressively break work down into work packages
Roll up the packages for bottom up estimating
Packages give clear work assignments
Splits work into manageable, logical packages
Make sure packages can be tested for completeness
Ex: WBS Buy a House
` BUY A HOUSE
FIND
LOCATION FINANCING
HOUSE
- Determine - Type of
1 - Criteria 3 6
affordability House
- Lockup
- Look for
5 mortgage 8
House
commitment
- Make
9 Offer, P&S
Agreem't
10 - Closing
Top
Top Down
Down Decomposition,
Decomposition, Elemental
Elemental Tasks
Tasks
Project Organization
Project Organization
Often temporary structure
Uses specialists from entire company
Headed by project manager
Coordinates activities
Monitors schedule
& costs
Eng. Eng.
Permanent Mkt.
structure called Acct.
‘matrix organization’
Mgr.
PROJECT SCHEDULING
Project Scheduling
Sequencing activities
Identifying precedence
relationships
Determining activity times
& costs
Estimating material &
worker requirements
Determining critical PERT
activities Des
Tes
Buil
ign
d
t
J
Mo
A
nth
M
M
F
J
J
Acti
vity
Project
Project Scheduling
Scheduling Techniques
Techniques
Gantt chart
Critical Path Method
(CPM)
Program Evaluation &
Cost management
Quality management
Performance management
Earned Value Analysis
a standard procedure for numerically measuring
a project’s progress, forecasting its completion
date and cost and measuring schedule and
budget variation
Communication
Enterprise project management
GANTT CHART
Gantt Chart
Gantt Chart was developed by…
Henry Laurence Gantt (1861-1919) was a mechanical
engineer and management consultant who is most famous
for developing the ‘Gantt chart’ in the 1910s. These
Gantt charts were employed on major infrastructure
projects including the Hoover Dam and Interstate
highway system. He refined production control and cost
control techniques.
Example of Gantt Chart
Month
0 | 2 | 4 | 6 | 8 | 10
Activity
Design house
and obtain
financing
Lay foundation
Order and
receive
materials
Build house
Select paint
Select carpet
Finish work
1 3 5 7 9
Month
Gantt Chart
Activities in Buy a House
` BUY A HOUSE
FIND
LOCATION FINANCING
HOUSE TASK PREDECESSOR
1-criteria 3
1 - Criteria 3
- Determine
6
- Type of 2-visit loc. 1
affordability House 3-affordability
4-mortgage co 3
- Determine - Find Real 5-mortg lock 4
- Visit
2 4 mortgage 7 Estate
Locations 6-type of hse 1
provider Agent
7-real est agent 2, 6
- Lockup 8-look for hse 7
- Look for
5 mortgage 8 9-offer, P&S 5, 8
House
commitment
10-closing 9
- Make
9 Offer, P&S
Agreem't
10 - Closing
Gantt Chart
Buy a House
ek 1 Week 2 Week 3 Week 4
ID Task Name M T W T F S S M T W T F S S M T W T F S S M T W T
1 BUY HOUSE TASK PREDECESSOR
2/5
1-criteria 3
2 LOCATION 2/5 2-visit loc. 1
3-affordability
3 Determine location criteria
4-mortgage co 3
4 Visit key locations 5-mortg lock 4
6-type of hse 1
5 FINANCING 2/5 7-real est agent 2, 6
6 Determine affordability 8-look for hse 7
9-offer, P&S 5, 8
7 Assess Mortagg Provider 10-closing 9
8 Secure Mortagg Commitmt 2/14
9 FIND HOUSE 2/5
10 Type of House
14 Closing 2/24
Simple
Simple Gantt
Gantt Chart
Chart View
View
Limitations of Gantt Chart
CPM & PERT
CPM & PERT
• Network techniques
• Developed in 1950’s
• CPM by DuPont for chemical plants In 1957 suitable for
Civil & Mechanical Projects
• PERT by U.S. Navy for Polaris missile in 1958
consulting with M/s Booz, Allen & Hamilton
• Consider precedence relationships &
interdependencies
• Each uses a different estimate of activity times
CPM & PERT Steps
• Identify activities
• Determine sequence
• Create network
• Determine activity times
• Find critical path
• Earliest & Latest start times
• Earliest & Latest finish times
• Slack or Float
Questions Answered by
PERT & CPM
• Completion date?
• On schedule? Within budget?
• Probability of completing by ...? (Duration)
• Critical activities?
• Enough resources available?
• How can the project be finished early at the
least cost?
Constructing Networks
Graphical Representation of
Events and Activities
Flow Charting - Uses Nodes and Arrows
Arrows
An arrow leads from tail to head directionally
Nodes
A node is represented by a circle or any
mathematical symbol
Node Arrow
Activity On Node (AON)
1 2 3
Activity On Arrow (AOA)
1 4
3
Network Terms
Activity
Event (Node) Event (Node)
(Arrow)
Activity
Relationships
Activity Relationships
1
Activity Relationships
2
A
1
B
A & B can occur
3
concurrently
Activity Relationships
A must be done
before C & D can
begin
2 D
A
C
1 4
B
3
Activity Relationships
2 D
A
C
1 4
B
3 E
B & C must be done
before E can begin
Activity Relationships
A must be done
before C & D can
begin
2 D
A
C
1 4
B
A & B can occur
3 E
B & C must be done
concurrently before E can begin
Dummy Activities
Activities are defined often by beginning &
ending events
Example: Activity 2-3
Every activity must have unique pair of
beginning & ending events
It is an imaginary activity
Consume no Time or Resources
Incorrect
2-3
1-2 3-4
11 22 33 44
2-3
Dummy Activities Example
Incorrect 2-3
1-2 3-4
11 22 33 44
2-3
Different activities;
same designation
Dummy Activities Example
Incorrect 2-3
1-2 3-4
11 22 33 44
2-3
Correct
1-2 2-4 4-5
11 22 44 55
2-3 3-4: Dummy
33 activity
Some more Example of Dummy
Activities
Ex – I
A Printing invitation Cards
B Collection of Address
C Dispatching of Cards
A
22
2-3: Dummy
11 activity
B C
33 44
Some more Example of Dummy
Activities
Ex – II
If A & E are concurrent
B
B is after A & E and
F is after E A
E F
Labeling the Events by
Dr. Fulkerson’s Rules:
Numbering the events by DR. Fulkerson’s rules:
There is a single initial event in the net work diagram. This
initial event will have arrows coming out of it and none entering
it. Number this initial event as 1.
Neglect all the arrows emerging out of the initial event
numbered 1. Doing so, it will apparently provide one or more
new initial events.
Number these apparently produced new initial events as 2, 3, 4
… etc.
Again neglect all emerging arrows from these numbered events.
This will create few more initial evens.
Follow rule – 3.
D
oo qq H
B
A J
A G ss tt
m
m nn I
C
F
pp rr
Network Example
You’re a project manager for Bechtel. Construct
the network.
Activity Predecessors
A --
B A
C A
D B
E B
F C
G D
H E, F
Network Example - AON
D
B G
A E Z
C H
F
Network Example - AOA
Activity Predecessors
A --
B A
C A
D B
E B Rough arrow diagram
F C
G D
H E, F
D G
3 6 8
B E
A
1 2 5 H
7 9
C F
4
Network Example - AOA
D
3 6 G
B E
A H 7
1 2 5
C F
4
Ff
Ft
E1 E2
t
1 2
L1 L2
Fid
Example Network Flow Diagram
D
2 5
A G
C I
4
1 H 7
B E 6 J
3
F
Example Activity Characteristics
Activity a m b te Sigmae
A 1-2 10 12 14 12 2/3
B 1-3 9 11 13 11 2/3
C 2-4 1 3 11 4 5/3
D 2-5 1 8 9 7 4/3
E 3-4 1 7 13 7 6/3
F 3-6 5 10 15 10 5/3
G 4-5 8 13 18 13 5/3
H 4-6 1 7 19 8 9/3
I 5-6 6 10 20 11 7/3
J 6-7 6 10 14 10 4/3
Example Network Flow Diagram
te =7
2 5
te =12 te =13
te =4 te =11
4
1 te =8 7
te =7 te =10
te =11 3
6
te =10
Earliest Start Time & Finish
Steps
• Begin at starting event & work forward
• EST = 0 for starting activities
• EST is earliest start
• EFT = EST + Activity time
• EFT is earliest finish
• EST = Maximum EFT of all predecessors for
non-starting activities
Example Network Flow Diagram
ES=12 ES=31
te =7
2 5
te =12
ES=18 ES=52
ES=0 te =4 te =13 te =11
4
1 te =8 7
ES=42
ES=11 te =7
te =11 6 te =10
3
te =10
Latest Start Time &
Finish Steps
• Begin at ending event & work backward
• LFT = Maximum EFT for ending activities
• LFT is latest finish; EFT is earliest finish
• LST = LFT - Activity time
• LST is latest start
• LFT = Minimum LST of all successors for
non-ending activities.
Example Activity Characteristics
to tm tp te Sigmae EST LST EFT LFT
1-2 10 12 14 12 2/3 0 2 12 14
1-3 9 11 13 11 2/3 0 0 11 11
2-4 1 3 11 4 5/3 12 14 16 18
2-5 1 8 9 7 4/3 12 24 19 31
3-4 1 7 13 7 6/3 11 11 18 18
3-6 5 10 15 10 5/3 11 32 21 42
4-5 8 13 18 13 5/3 18 18 31 31
4-6 1 7 19 8 9/3 18 34 26 42
5-6 6 10 20 11 7/3 31 31 42 42
6-7 6 10 14 10 4/3 42 42 52 52
Example Network Flow Diagram
With Critical Path
ES|LS|EF|LF
t2-5 =7
2
12|24|19|31 5
t1-2 =12 t4-5 =13 t5-6 =11
0|2|12|14 t2-4 =4 18|18|31|31 t4-6 =8 31|31|42|42
12|14|16|18
1
4 18|34 |26|42 7
t3-4 =7
t1-3 =11 11|11|18|18 6 t6-7 =10
0|0|11|11 3
t3-6 =10 42|42|52|52
11|32|21|42
Computing the Float value
Ff
Ft
E1 E2
t
1 2
L1 L2
Fid
Distinction between CPM & PERT
CPM PERT
Activity oriented technique. Event oriented technique.
It has one time estimate. It has three time estimation.
Designed for repetitive projects. Suitable for non-repetitive projects.
Not statistically analyzed. Analyzed statistically.
It does not demarcated critical and
It demarcates critical activities. non-critical activities.
It employs words like arrow diagram, It employs words like network
node, floats etc. diagram, events Slack etc.
Dummy activities are not necessary. Use of dummy activities are required
Suitable for industrial settings, plant representing the proper sequence.
maintenance, civil construction projects. Suitable for defense projects and R &
A deterministic model with well known D etc. Where activities cannot be
activities times based on past experience. predicted.
Cost is not directly proportional to time A probabilistic model with uncertainty
and const is the controlling factor. in activities duration
Cost varies directly with time and time
is the controlling factor.
Benefits &
Limitations
of PERT/CPM
Benefits
of PERT/CPM
Useful at many stages of project
management
Mathematically simple
Use graphical displays
Give critical path & slack time
Provide project documentation
Useful in monitoring costs and time
Limitations
of PERT/CPM
Clearly defined, independent, & stable
activities
Specified precedence relationships
Activity times (PERT) follow
beta distribution
Subjective time estimates
Over emphasis on critical path
Conclusion
Explained what a project is
Summarized the CPM / PERT project
activities and their time estimates
Drew project networks
Compared PERT & CPM
Determined slack & critical path
Computed project probabilities
Project Management
PERT/CPM
THE END