Scott Chapman American Electric Power

Paper 9015
Session 331
Agenda
What I mean by critical path
My simple way of finding it
Review some sample code
Questions
Bonus Material
Geek-required xkcd reference
HTTP://XKCD.COM/399/

Critical path
Simple definition: how long is this going
to take?
Longest sequence of activities
In a project
In a batch schedule
Need to look at:
Predecessor-successor relationships
Durations
Time dependencies
Ideas originated in Project Management
Project Management History
Critical Path Method (CPM) originated at DuPont
in 1950s
Used to manage chemical plant maintenance
projects
Critical path is the sequence of events which
determines the duration of the project
Delays in tasks on the CP delay the entire
project
CP must be managed to stay on schedule
To finish project earlier, tasks on CP must be
somehow shortened
CPM process
Identify activities
Identify sequence and dependencies
Draw network diagram of activities
Estimate duration of activities
Identify the longest path in the network
(critical path)
Monitor & update as project progresses
Delays in tasks not on CP may change
the CP!
Batch Windows & CP
Business runs on cycles
Daily, weekly, monthly processes
Large applications have large batch
schedules
Batch schedules can be drawn as a
network diagram
Predecessor Successor
relationships between jobs
Like projects, we like our batch windows
to finish on time!
Like a project, a batch schedule has a CP
CP Calculation
Formally:
CP is path with no slack for any task
Slack = difference between earliest & latest start
or finish time of task
Latest finish = latest time task can finish
without delaying project
And how do you figure that???
Informally:
Find all the paths through the network
diagram
Add up task duration on each path
Select the longest path

Simple example
Five paths through this simple example
Task A
Task D
Task B
Task C
Task E
Task F
Start End
Simple example
Five paths through this simple example
Task A
Task D
Task B
Task C
Task E
Task F
Start End
Simple example
Five paths through this simple example
Task A
Task D
Task B
Task C
Task E
Task F
Start End
Simple example
Five paths through this simple example
Task A
Task D
Task B
Task C
Task E
Task F
Start End
Simple example
Five paths through this simple example
Task A
Task D
Task B
Task C
Task E
Task F
Start End
Simple example
Five paths through this simple example
Task A
Task D
Task B
Task C
Task E
Task F
Start End
Simple example
Calculate path durations from task durations
Task A
Task D
Task B
Task C
Task E
Task F
Start End
15 mins
30 mins
20 mins
15 mins
10 mins
5 mins
A+B+E = 45
A+C+E = 40
A+C+F = 35
D+C+E = 55
D+C+F = 50
Simple example
Calculate path durations from task durations
Task A
Task D
Task B
Task C
Task E
Task F
Start End
15 mins
30 mins
20 mins
15 mins
10 mins
5 mins
A+B+E = 45
A+C+E = 40
A+C+F = 35
D+C+E = 55
D+C+F = 50
So thats simple enough!
Everybody ready to leave?
Real world complications
Hundreds or thousands of batch jobs
Managed by a batch scheduler
package
Time-of-day dependencies
Extraneous dependencies
New jobs added without cleaning up obsolete
dependencies
Variable execution times
Variation in data to be processed
Contention with other processes
External waits
Job failures
What that might look like
Winding your way through that mess is a bit more complicated!
Tooling Options
Package from scheduler vendor
+ Should be well integrated
- Cost?
Microsoft Project
- Not really meant for this purpose
+ See CMG Proceedings: Schwarz/Aurand, 1999 and
Zaslavsky, 2001
SAS/OR
- Cost and effort?
Roll your own
+ Can make output exactly what you want
- Time / effort
+ Sample code on your CD!

What is the real question?
1. What is the longest path through the
schedule?
- prediction of the critical path
- usually one-time analysis
2. Why did job X finish late last night?
- an ongoing question / process
- requires the CP for job X

Fortunately, #2 is much easier!
Use what you know
Predecessors
(from batch scheduler)
End times
(from actual executions)

We are answering a question, not
predicting the future
We just need to explain what happened
Look at the jobs in the critical path for job
X for anomalies

Critical path simplified
Start at job X
Find the predecessor that ended last
that was the critical predecessor to X
Call that job W
Find last predecessor of W, call it V
Repeat until:
You go back some number of levels or
You reach a time dependency
Resulting list is the critical path, for
the day under study, for job X
Simple example
Task A
Task D
Task B
Task C
Task E
Task F
Start
19:00
End
15 mins
30 mins
20 mins
15 mins
10 mins
5 mins
19:15
19:30
19:35
19:45
19:55
19:50
Working backwards
Task A
Task D
Task B
Task C
Task E
Task F
Start
19:00
End
19:15
19:30
19:35
19:45
19:55
19:50
E ended last
What is Es last predecessor?
Task A
Task D
Task B
Task C
Task E
Task F
Start
19:00
End
19:15
19:30
19:35
19:45
19:55
19:50
E ended last
C ended after B
What is Cs last predecessor?
Task A
Task D
Task B
Task C
Task E
Task F
Start
19:00
End
19:15
19:30
19:35
19:45
19:55
19:50
E ended last
C ended after B
D ended after A

Critical Path is E C D
Task A
Task D
Task B
Task C
Task E
Task F
Start
19:00
End
19:15
19:30
19:35
19:45
19:55
19:50
Tasks A, B, F had no direct bearing on the end time
Complicating simplicity
Schedule changes every day
Weekly / monthly processing
Application changes
Schedule relationships may not be
pristine
Jobs may be run multiple timesbe
sure to use the correct instance
If you want to graph the entire
schedule it gets more complicated

Why bother finding the CP?
Limit the data you need to look at to
investigate a late-finishing job
The cause is on the CP
Find changes
If the CP changes day to day: why?
Investigate impact of periodic
schedule differences
Addition of monthly processing
jobs may change the CP

What I do
Capture job stats every day to a
performance database
Standard practice
Extract history daily to XML file
Extract schedule once per day and
store for 45 days
Saved as XML files
Allows historical investigation
JavaScript browser application pulls
both data sources and allows for
investigation
Sample application
Input #1: Schedule XML file
<?xml version='1.0'?><?xml-stylesheet type='text/xsl'?>
<opc>
<app id='#AMCSMISCBILL'>
<op id='87' job='#AMCS331' arr='1930'><wkstn>CPUJ</wkstn>
<desc>Online Bill Image xtract</desc>
<pred><aid>#AMCSMISCBILL</aid><opid>81</opid></pred>

<pred><aid>#AMCSMISCBILL</aid><opid>78</opid></pred>
<succ><aid>#SMCSDAILYRPTS</aid><opid>3</opid></succ>

<succ><aid>#AMCSDLYBKUP</aid><opid>6</opid></succ>
</op>
<op id='90' job='#AMX1358' arr='1930'><wkstn>CPUJ</wkstn>
<desc>Load O/L Bill Image</desc>
<pred><aid>#AMCSMISCBILL</aid><opid>87</opid></pred>
<succ><aid>#AMCSMISCBILL</aid><opid>91</opid></succ>
</op>
</app>
A grouping of
jobs is an
application
A job is an
operation
Each job has
predecessors and
successors
Arrival time is the
earliest the job
can run
Sample application
Input #2: Job Data XML file
<job id="#AMCS331">
<sys>COCJ</sys><cls>0</cls><desc>MCSX4000</desc><cnt>24</cnt>
<acpu>2.18</acpu><aet>13.8</aet><mcpu>2.70</mcpu><met>26.7</met>
<run i="2009-05-09 2:01:55" rse=" 1:59:46, 2:01:56, 2:02:09">
<et>13.7</et><cp>2.16</cp><io>21632</io>
</run>
<run i="2009-05-08 0:51:46" rse=" 0:51:45, 0:51:48, 0:52:02">
<et>16.5</et><cp>2.11</cp><io>21690</io>
</run>
<run i="2009-05-07 1:24:41" rse=" 1:22:04, 1:24:41, 1:24:52">
<et>11.4</et><cp>2.12</cp><io>21740</io><sys>CO1J</sys>
</run>
</job>


Jobs by name
here
Norms, averages,
maximums
May have multiple
runs per day
Read, start, end
times
Note relatively compact format designed to
reduce the file sizeunfortunately that increases
the complexity of interpreting the data
Stats for single
run
Sample application output
Compare days in two windows
Why later on 12/29?
Completely
different CP
here
Critical path
comes back
together here
Heres an ET
difference of >1
hour and CPU
>2x increase!
Sample application details
On CD at back of room
Very simple example coded quickly one
Sunday afternoon
May not be bug free
Will not satisfy all your needs
For illustrative purposes only easier to
understand than the examples in the paper
HTML / JavaScript application
Data is in XML files
Internet Explorer only
Uses XPath & XSLT
Beyond the scope of this presentation

Application flow
When HTML page loads
Calls init() to load the XML files
Selection criteria populated in HTML
When user clicks Find It button
Calls findIt() to find the critical path,
which in turn calls:
getRunsDate(job, date) returns array of
executions of a job on a given batch date
getLatestPred(job, app) returns
predecessor that ran last

getRunsDate is an
example of using DOM
functions to extract
data from XML
Critical parts of the code
findIt()
Get runs for this
job and date
Save stats for this
job to array
Then find preds
and add them to
the array
Loop through
array and build
HTML table
getLatestPred(cjob, capp)
XPath to get array
of preds
Use DOM calls to
get data from
XML
Xpath to find job
name from op id
Get the runs for a
pred job
Check run to see
if it is the latest
pred so far
If it is, save it
Thats essentially it!
getRunsDate(job, date) is nothing
special simply retrieves list of runs
from the XML file
Typical housekeeping code initializing
variables, etc.
Sample in the paper was much more
complicated due to it being pulled
from the application that does the
graphing
Summary
Critical Path Analysis for Performance
Analysis usually involves answering
why, not predicting the future
In such a case, start at the end and
work backwards
That type of analysis is easy to code
Record a snapshot of the schedule
daily as well as the job performance
Questions / comments ?
Bonus material: Export to
Excel!
Sometimes you need to play with your
data
Copy to Excel to
Re-sort
Filter
Pivot tables
Graph
Summarize
Cut and paste HTML tables works well
Even better: automate it

New & improved:
sendExcel() function on CD
If Excel not open, open it
If previous workbook not open
Open a new workbook
Add new sheet to work book with data


Requires IE and Excel
Useful references
XPath, XSLT, XML quick reference
cards
http://www.mulberrytech.com/quickref/index.html
Browser Book for Web Designers
http://www.visibone.com/products/browserbook.html
Humor for geeks
http://xkcd.com/