Академический Документы
Профессиональный Документы
Культура Документы
OPERABILITY STUDY
When to Use?
Optimal from a cost viewpoint
1.when applied to new plants at the point
where the design is nearly firm and
documented or
2.to existing plants where a major redesign is
planned.
It can also be used for existing facilities.
Results
Types: The results are the team findings.
Which include: (1) identification of hazards
and operating problems, (2) recommended
changes in design, procedure, etc., to
improve safety; and (3) recommendations
for follow-on studies where no conclusion
was possible due to lack of information.
Nature: Qualitative.
Requirements
Data: The HazOp requires detailed plant
descriptions, such as drawings, procedures, and
flow charts. A HazOp also requires considerable
knowledge of the process, instrumentation, and
operation, and this information is usually provided
by team members who are experts in these areas.
Staff: The HazOp team is ideally made up of 5 to 7
professionals, with support for recording and
reporting. For a small plant, a team as small as two
or three could be effective.
New Design
Existing Plant
Plant Superintendent
Process Engineer
Commissioning Manager
Maintenance Engineer
Instrument Engineer
Chemist
Technical Engineer
Principles of HAZOP
Concept
Systems work well when operating under design conditions.
PRINCIPLES OF HAZOPS
GUIDE WORDS*
NONE
MORE OF
LESS OF
PART OF
MORE THAN
OTHER
CAUSE
DEVIATION
(from standard
condition
or intention)
CONSEQUENCES
(trivial, important,
catastrophic)
-hazard
-operating difficulties
STUDY NODES
The locations (on P&ID or procedures) at which the process parameters are investigated
for deviations. These nodes are points where the process parameters (P, T, F etc.) have
an identified design intent.
INTENTION
The intention defines how the plant is expected to operate in the absence of deviations at
the study nodes.
DEVIATIONS
These are departures from the intension which can be discovered by systematically
applying the guide words.
Process conditions
activities
substances
time
place
GUIDE WORDS
Guide Words
Meaning
No, None
Negation of Intention
More Of
Quantitative Increase
Less Of
Quantitative Decrease
Qualitative Decrease
Reverse
Other Than
Complete Substitution
Deviations
No forward flow when there should be, i.e. no flow.
More of any relevant physical property than there should
be, e.g. higher flow (rate or total quantity), higher
temperature, higher pressure, higher viscosity, etc.
Less of any relevant physical property than there should be,
e.g. lower flow (rate or total quantity), lower temperature,
lower pressure, etc.
Composition of system different from what it should be,
e.g. change in ratio of components, component missing, ect.
More components present in the system than there should
be, e.g. extra phase present (vapour, solid), impurities (air.
Water, acids, corrosion products), etc.
What else can happen apart from normal operation, e.g.
start-up, shutdown, uprating, low rate running, alternative
operation mode, failure of plant services, maintenance,
catalyst change, etc.
EXAMPLE
C
The flowsheet shows that raw material streams A and B are transferred by
pump to a reactor, where they react to form product C. Assume that the
flow rate of B should not exceed that of A. Otherwise, an explosion may
occur. Lets consider the flow of A in line 1:
FB FA
NONE
MORE
LESS
AS WELL AS
PART OF
REVERSE
OTHER THAN
No flow of A
Flow of A greater than design flow
Flow of A less than design flow
Transfer of some component additional to A
Failure to transfer a component of A
Flow of A in a direction opposite to design direction
Transfer of some material other than A
Beginning
End
Select a vessel
Select a line
Examine consequences
Detect hazards
10
11
Repeat 6-10 for all meaningful deviations derived from first guide words
12
13
14
15
16
17
18
19
20
21
Repeat 5-12
22
23
24
25
HAZOP DISPLAY
Guide Word Deviation Possible Causes
No
More
More
Flow
Excessive
Over-Cooled
Pump Speed
Product
(Control System) (Incomplete
Reaction)
Product
Unacceptable;
Dump
EXAMPLE
An alkene/alkane fraction containing small amounts of
suspended water is continuously pumped from a bulk
intermediate storage tank via a half-mile pipeline into a
buffer/settling tank where the residual water is settled out prior
to passing via a feed/product heat exchanger and preheater to the
reaction, is run off manually from the settling tank at intervals.
Residence time in the reaction section must be held within
closely defined limits to ensure adequate conversion of the
alkene and to avoid excessive formation of polymer.
Deviation
No flow
Possible causes
(1)No hydrocarbon available
at intermediate storage.
Consequences
Loss of feed to reaction section
and reduced output.
Polymer formed in heat exchanger
under no flow conditions.
Action required
(a)Ensure good
communications with
intermediate storage
operator
(b)Install low level alarm
on settling tank LIC.
As for (1)
As for (1)
J1 pump overheats.
Covered by (b)
Covered by (b)
(c)Install kickback on J1
pump.
(d)Check design of J1
pump strainers.
(4)Line fracture
As for (1)
Hydrocarbon discharged into
area adjacent to public highway.
(1)
Covered by (b)
(e)Institute regular
patrolling & inspection
of transfer line.
Deviation
More flow
Possible causes
(5)LCV fails open or LCV
bypass open in error.
Consequences
Settling tank overfills.
Action required
(f)Install high level alarm
on LIC and check
sizing of relief opposite
liquid overfilling.
(g)Institute locking off
procedure for LCV
bypass when not in use.
More pressure
More
temperature
(7)Thermal expansion in an
Line fracture or flange leak.
isolated valved section due
to fire or strong sunlight.
(2)
Deviation
Less flow
Possible causes
(9)Leaking flange of valved
stub not blanked and
leaking.
Consequences
Material loss adjacent to public
highway.
Action required
Covered by (e) and the
checks in (j).
Less
temperature
(10)Winter conditions.
High water
concentration
in stream.
(12)Disturbance on distillation
columns upstream of
intermediate storage.
MORE
THAN
Organic acids
present
(q)Check suitability of
materials of construction.
OTHER
Maintenance
PART OF
(3)