Extension of DLP
The employer may ask extension of DLP if:
The plant or a part of same cannot be used for its
intended purpose due to the defects.
Accept the work with defect but reduce the contract price
in consultation with the engineer for reduction.
10
11
Right of Access
During DLP (until performance certificate is
issued), the contractor has the right of access to
the site but:
Access will be reasonable as may be required to fulfil
the obligation under contract.
Have to be consistent with employers safety
measures established at work place.
12
Contractor to Search
If required by the engineer, contractor shall
search for cause of any defect, 2 possibilities:
If the defect is such that it is to be remedied at
the cost of contractor ?.
13
Performance Certificate
Issued at the end of DLP with contractor
fulfilling his obligations under the contract.
Why is performance certificate so important?.
It is the only document which deems to constitute
the acceptance of work.
Generally Issued within 28 days from end of DLP.
Within this period of 28 days, a joint inspection is
carried out & contractor can fulfil (if) any balance
obligations.
Contracts Management : Prof Ashish Goel,
NICMAR
14
Un-fulfilled obligations
Contractors obligation after issuance of
performance certificate ??.
Site clearance.
Apply for final payment.
Latent defects
certificate.
detected
after
issuance
of
15
Clearance of Site
After issuance of performance certificate the
contractor is supposed to remove following from
the site:
Any remaining equipment, material, rubbish &
temporary works if any.
If such items are not removed within 28 days after PC
then the employer may
Sell/ Dispose off such items
Employer shall get any cost incurred in such process from
contractor.
If any balance amount left out after employers expenses,
same to be handed over to employer.
In case expenses exceed employer cost, contractor is
Contracts
: Prof
Ashish Goel,
supposed to pay
theManagement
balance
outstanding
amount.
16