Вы находитесь на странице: 1из 42

Assembly Line Balance

Balance

Assembly analysis
Assembly Chart
It shows the sequence of operations in putting the
product together. Using the exploded drawing and
the parts list, the layout designer will diagram the
assembly process.

The sequence of assembly may have several


alternatives.
Time standards are required to decide which
sequence is best. This process is known as assembly
line balancing.
Balance

The Assembly Chart

The assembly chart


of a toolbox

Balance

Time Standards Are Required for Every Task

Balance

Plant Rate and Conveyor Speed


Conveyor speed is dependent on the number and
units needed per minute, the size of the unit, the
space between units. Conveyor belt speed is
recorded in feet per minute.
Example:
Charcoal grill are in cartons 30X30X24 inches
high. A total of 2,400 grills are required every day.

Balance

Plant Rate and Conveyor Speed

Balance

Assembly line balancing


The purpose of the assembly line balancing technique is:
1.
2.
3.
4.
5.
6.
7.
8.

To equalize the work load among the assemblers


To identify the bottleneck operation
To establish the speed of the assembly line
To determine the number of workstations
To determine the labor cost of assembly and packout
To establish the percentage workload of each operator
To assist in plant layout
To reduce production cost

The assembly line balancing technique builds on:


The assembly chart;
Time standards;
Takt time (minutes/piece)
(Plant rate, R value,
Pieces/minutes).
Balance

Initial assembly line balancing of toolbox

Takt time (for 2,000 units per shift, considering 10%


downtime and 80% efficiency) = .173 minutes per unit.
Balance

Assembly line balancing


1.Cost of balancing
Subassemblies that cost too high can be taken off the
line.
SA3 could be taken off the assembly line and handled
completely separate from the main line and we can save money.
SA3 .250 = 240 pieces per hour and .00417 hour each. If balanced,
the standard would be 180 pieces per hour and .00557 hour each.
.0057 balanced cost
.00417 by itself cost
.00140 savings hour per unit
X
500,000 units per year
700
hours per year
@ $15.00 per hour
=
$10,500.00 per year savings
Balance

Assembly line balancing


Subassemblies that can be taken off the line must be:
1.

2.
3.

Poorly loaded. The less percent that is loaded.


For example, a 60 percent load on the assembly
line balance would indicate 40 percent lost time.
If we take this job off the assembly line (not tied
to the other operators), we could save 40 percent
of the cost.
Small parts that are easily stacked and stored.
Easily moved. The cost of transportation and the
inventory cost will go up, but because of better
labor utilization, total cost must go down.
Balance

10

Assembly line balancing


2. Improvement of assembly line
Improve the busiest (100 percent) workstation first.

(a) The busiest workstation is P.O. It has .167 minute of work to do


per packer. The next closest station is A1 with .155 minute of
work. As soon as we identify the busiest workstation, we identify
it as the 100 percent station, and communicate that this time
standard is the only time standard used on this line from now
on. Every other workstation is limited to 360 pieces per hour.
Even though other workstations could work faster, the 100
percent station limits the output of the whole assembly line.
(b) The total hours required to assemble one finished toolbox is
.06960 hour. The average hourly wage rate times .06960 hour
per unit gives us the assembly and packout labor cost. Again,
the lower this cost is the better the line balance is.

Balance

11

Assembly line balancing

Balance

12

Assembly line balancing

Balance

13

Assembly line balancing


2. Improvement of assembly line
Improve the busiest (100 percent) workstation first.
Look at the 100 percent station (P.O.).
If we add a fourth packer, we will eliminate the 100 percent station
at P.O.
Now the new 100 percent (bottleneck station) is A1 (93 percent).
By adding this person, we will save 7 percent of 25 people or 1.75
people and increase the percent load of everyone on the
assembly line (except P.O.). We might now combine A1 and A2,
and further reduce the 100 percent.
The best answer to an assembly line balance problem is the
lowest total number of hours per unit. If we add an additional
person, that persons time is in the
total hours.
Balance

14

Step-by-step procedure for completing the


assembly line balancing form

Balance

15

Step-by-step procedure for completing the


assembly line balancing form
9. R value
The R value goes behind each operation. The plant rate is the
goal of each workstation, and by putting the R value on each
line (operation), one keeps that goal clearly in focus.
10. Cycle time
The time standard.
11. Number of stations

cycle time
number of stations
R
12. Average cycle time

cycle time
ave. cycle time
# of stations
Balance

16

Step-by-step procedure for completing the


assembly line balancing form
13. Percentage load:
The percentage load tells how busy each workstation is
compared to the busiest workstation.
The highest number in the average cycle time column 12 is
the busiest workstation and, therefore, is called the 100 percent
station.
Now every other station is compared to this 100 percent
station by dividing the 100 percent average station time into
every other average station time. The percent load is an
indication of where more work is needed or where cost
reduction efforts will be most fruitful. if the 100 percent station
can be reduced by 1 percent, then we will save 1 percent for
every workstation on the line.
Balance

17

Step-by-step procedure for completing the


assembly line balancing form
13. Percentage load:
Example: percent load of the toolbox assembly line balance
In Figure 4-11, the average cycle times reveals that .167 is the
largest number and is designated the 100 percent workstation.
The percentage load of every other workstation is determined by
dividing .167 into every other average cycle time:
Operation SSSA1 = .153 / .167 = 92 percent
SSA1 = .146 / .167 = 87 percent
SSA2 = .130 / .167 = 78 percent
and so on.

Balance

18

Step-by-step procedure for completing the


assembly line balancing form
14. Hours per unit:

100 % average cycle time


h.p.u.
60 minutes per hour
Example: Hours per unit of the toolbox assembly line balance

.167
h.p.u.
.00278 hour per unit
60
The .167 time standard is for one person, if considering the people
number, the hour per unit will be:
Two people = .00557 hour per unit
Three people = .00835 hour per unit
Four people = .01113 hour per unit
Balance

19

Step-by-step procedure for completing the


assembly line balancing form
15. Piece per hour:
Inversion of hours per unit.
16. Total hours per unit
Sum of the elements in column 14. For this example is .0696
hour.
17. Average hourly wage rate, say $15 per hour
18. Labor cost per unit
Total hours X average hourly wage
19. Total cycle time
It tells us what a perfect line balance would be.
Our example 3.494 minutes divided by 60 minutes per hour
equals .05823 hour per unit. Balance
20

Efficiency of the assembly line

Sum of hours per 1000


Line efficiency
100%
Sum of hours per 1000 line balance
or

Sum of hours per unit


Line efficiency
100%
Sum of hours per unit line balance
For our example:

0.05823
Line efficiency
100% 84%
0.06960
Balance

21

Analysis of single model assembly lines


Production Rate is given by

Da
Rp
50 S w H sh
where Rp = average hourly production rate, units/hr;
Da = annual demand, units/year;
Sw = number of shifts/week;
Hsh = hrs/shift.
This equation assume 50 weeks per year.
Balance

22

Analysis of single model assembly lines


The cycle time can be determined as

60 E
Tc
Rp
where Tc = cycle time of the line, min./cycle;
Rp = production rate, units/hr;
E = line efficiency;

Balance

23

Analysis of single model assembly lines


The cycle rate can be determined as

60
Rc
Tc
where Rc = cycle rate, cycles/hr;
Tc is in min./cycle;
Line efficiency E therefore defined as:

Rp

Tc
E

Rc Tp
Balance

24

Analysis of single model assembly lines


The number of workers on the line can be
determined as

WL
w
AT
where w = number of workers on the line;
WL = workload to be accomplished in a given time period.
AT = available time in the period.

WL R pTwc

TWc = work content time, min/piece.


Balance

25

Analysis of single model assembly lines


Using the previous equation, we also have

60 ETwc
WL
Tc
The available time in the period, AT.

AT = 60E

Substitute these terms for WL and AT into w


equation, we can state:

Twc
w minimun integer
Tc
*

If we assume one worker per station, then this ratio also


gives the theoretical minimum number of workstations on
the line.
Balance

26

Analysis of single model assembly lines


Example
A small electrical appliance is to be produced on a single
model assembly line. The work content of assembling the
product has been reduced to the work elements listed in
table below along with other information. The line is to be
balanced for an annual demand of 100,000 units per year.
The line will be operated 50 weeks/yr, 5 shifts/wk, and 7.5
hrs/shift. Manning level will be one worker per station.
Previous experience suggests that the uptime efficiency for
the line will be 96%, and repositioning time lost per cycle
will be 0.08 min. Determine (a) total work content time Twc,
(b) required hourly production rate Rp to achieve the
annual demand, (c) Cycle time, and (e) service time Ts to
which the line must be balanced.
Balance

27

Analysis of single model assembly lines


Example

Balance

28

Analysis of single model assembly lines


Example

Balance

29

Analysis of single model assembly lines


Solution:
(a) The total work content time is:
Twc = 4.0 min.
(b) The production rate is:

100,000
Rp
53.33 units/hr
50(5)(7.5)
(c) The cycle time Tc with an uptime efficiency of 96% is:

60(0.96)
TC
1.08 min .
53.33
Balance

30

Analysis of single model assembly lines


Solution:
(d) The theoretical minimum number of workers is given by:

Twc
w* min int
3.7 4
Tc
(e) The average service time against which the line must
be balanced is:

Ts Tc TR 1.08 0.08 1.00 min .


Balance

31

Analysis of single model assembly lines


The objective in line balancing is to distribute
the total workload on the assembly line as
evenly as possible among the workers
w

minimize ( wTs Twc ) or minimize (Ts Tsi )


i 1

subject to:

(1)

T
k i

ek

Ts

and

(2) all precedence requirements are


obeyed.

Balance

32

Analysis of single model assembly lines

The algorithms are:


1)Largest Candidate Rule
2)Kilbridge and Wester method
3)Ranked positional weights

Balance

33

Largest Candidate Rule


Step 1: Rank the Teks in the descending order.
Step 2: Assign the elements to the worker at first station
by starting at the top of the list and selecting the first
element that satisfies precedence requirements and does
not cause the total sum of Tek at that station to exceed the
allowable Ts; when an element is selected for assignment
to the station, start back at the top of the list for
subsequent assignments.
Step 3: when no more element can be assigned without
exceeding Ts, then proceed to the next station.
Step 4: repeat steps 2 and 3 for as many additional
stations as necessary until all elements have been
assigned.
Balance

34

Largest Candidate Rule


Work elements sorted in descending order

Balance

35

Largest Candidate Rule


Solution:
The largest candidate algorithm is carried out as presented
in table below. 5 workers and stations are required in the
solution. Balance efficiency is computed as:

Twc
4.0
E

0.8
wTs 5(1.0)

Balance

36

Largest Candidate Rule


Work elements assigned to stations by LCR

Balance

37

Analysis of single model assembly lines


Example

Balance

38

Analysis of single model assembly lines


Kilbridge and Wester method

Balance

39

Analysis of single model assembly lines


Ranked positional weights

Balance

40

Analysis of single model assembly lines

Largest Candidate
Rule

Kilbridge and
Wester method

Balance

Ranked positional
weights

41

Analysis of single model assembly lines

Automation, Production Systems, and


Computer-Integrated Manufacturing, By
Mikell P. Groover, 3rd edition, c2008.
Manufacturing Facilities Design and Material
Handling, By F. E. Meyers and M. P. Stephens,
4th Edition, Prentice-Hall, Inc., 2010

Balance

42

Вам также может понравиться