Академический Документы
Профессиональный Документы
Культура Документы
Learning Objectives
Understanding APQP (Advanced Product
Quality Planning)
Production Part Approval Process (PPAP)
Purpose
Benefits
Standards
When is PPAP required?
PPAP submission levels
Elements of PPAP and its importance
Design Records
Process Flow Diagram
DFMEA & PFMEA
Control Plan
MSA
Initial Process Capability Study
APQP Elements
APQP 1 - Sourcing Decision
Formal commitment of the customer to work with the supplier (customer order,
Nomination Letter etc.) so that investments can be effected on schedule.
APQP 2 - Customer Specifications
To avoid misunderstandings in Customer specifications include the design criteria and
program requirements, e.g. drawings, specifications (Note if material or
coating/plating, etc. is not included on the drawing or in specifications, then there must
be a sign off between engineering, purchasing, and supplier prior to issue of purchase
order) and design requirements which are necessary for the introduction of the
supplier's APQP.
APQP 3 - Contract Review
To carry out a commercial and technical assessment of the documents provided by the
customer to check that they are complete, up-to-date and feasible.
APQP 4 - Craftsmanship
To define characteristics relating to appearance, texture, handling ability, noise and
smell.
APQP Elements
APQP 5 - Design-FMEA
To prevent defects during product development
APQP 6 - Design Review
To prevent misunderstandings and problems; to monitor the progress of measures
and to ensure that objectives are met
APQP 7 - Design Verification Plan DVP
To provide a clear illustration of the progress that a subcontractor is making on a
project
APQP 8 - Quality Planning for Subcontractor
To provide a clear illustration of the progress that a subcontractor is making on a
project
APQP 9 - Facilities, Tools
To obtain capable/released operating materials from initial samples onwards
APQP Elements
APQP 10 - Inspection Methods and Equipment
To obtain capable/released inspection equipment, which is suitable for the measuring task
required of it, from initial sampling onwards; planning (monitoring of dates) and provision
of all necessary inspection equipment; acceptance in accordance with the criteria of MSA
(ISO 9000/TS16949).
APQP 11- Inspection Method
To achieve uniform inspection methods
APQP 12 - Contingency Plan
Aim: To ensure the guaranteed delivery quantities and product quality in the event of
broken tooling, machine failures or other unforeseen events
APQP 13 - Prototype Build Control Plan/Inspection Plan
Aim: To secure the prototype quality and planning instruments for purchasing inspection
equipment
APQP 14 - Production/Inspection of Prototype Parts
Aim: To dispatch, on schedule, prototypes which meet cost and quality requirements
APQP Elements
APQP 15 - Drawings/Specifications (Design Freeze)
To provide, on schedule (customer/supplier), all drawings and specifications that
are needed to observe the initial sample date/start of production (SOP).
APQP 16 - Confirmation of Manufacturing Feasibility
To assess production feasibility (volume) relative to the intended design
APQP 17 - Process Flow Diagram and Production Layout
To provide a foundation for investment planning, System FMEA Process / Process
FMEA, production plan, control plans and visual aids
APQP 18 - Logistics/Supply Concept
To ensure delivery capability
APQP 19 - Process Freeze
To ensure that there are no problems at start of production
APQP 20 - Process FMEA
To prevent defects during process development
APQP Elements
APQP 21- Measurement Systems Evaluation and Inspection Equipment Capability
To evaluate the suitability (scatter) of inspection equipment for the required
measurement task
APQP 22 - Pre-production Inspection Plan/Pre-launch Inspection Plan
To ensure that process and product requirements are implemented
APQP 23 - Process Instructions
To ensure quality and quantity
APQP 23 - Packaging Materials and Specifications
To maintain the quality achieved
APQP 24 - Production Trial Run
To ensure that volume production starts without any problems and that the requested
values are observed (cost - profitability)
APQP 25 - Production Control Plan
To ensure that process and product requirements are implemented
APQP Elements
APQP 26 - Preliminary Process Capability Study
To provide statistical proof of capable processes
APQP 27 - Technical Tests on Production Parts
To confirm that the parts meet technical standards/customer
requirements.
APQP 28 - Initial Sampling Inspection
To provide proof of product and process release.
Voice of the
Reliability and
Quality Goals
Business
Plan/Marketing
Strategy
Product/Process
Benchmark Data
Product/Process
Assumptions
Product Reliability
Studies
Packaging Standards
Product/Process
Quality System Review
Preliminary Bill of
Material
Design for
Manufacturability and
Assembly
Preliminary Process
Flow Chart
Design Verification
Characteristics Matrix
Design Reviews
Preliminary Listing
of Special Product
and Process
Characteristics
Product Assurance
Plan
Management
Support
Develop Product
Quality Timing Plan
Prototype Build
Control Plan
Engineering Drawings
(Including Math Data)
Engineering
Specifications
Material Specifications
Drawing and
Specification Changes
New Equipment,
Tooling and Facilities
Requirements
FMEA
Pre-Launch Control
Plan
INPUT
OUTPUT
Production Trial
Run
Measurement
Systems Evaluation
Production Part
Approval
Production
Validation Testing
Packaging
Evaluation
Measurement Systems
Analysis Plan
Production Control
Plan
Preliminary Process
Capability Study Plan
Quality Planning
Sign-Off and
Management Support
Gages/Testing
Equipment
Requirements
APQP
Customer
Satisfaction
Delivery and Service
MSA
PPAP
Management Support
Team Feasibility
Commitment and
Management Support
Reduced Variation
Preliminary
Process Capability
Study
Process Instructions
Packaging
Specifications
OUTPUT
Feedback,
Assessment and
Corrective Action
Product and
Process
Validation
INPUT
OUTPUT
INPUT
OUTPUT
INPUT
Design Goals
Customer
Customer Inputs
Product Design
and Development
OUTPUT
INPUT
Prepare for
APQP
SPC
What is PPAP?
Production Part Approval Process
Standard used to formally reduce risks
prior
to product or service release,
in a team oriented manner using well
established tools and techniques
Initially developed by AIAG (Auto Industry
Action Group) in 1993 with input from the
Big 3 - Ford, Chrysler, and GM
AIAGs 4th edition effective June 1, 2006 is
the most recent version
PPAP has now spread to many different
industries beyond automotive
Applicability of PPAP
PPAP shall apply to External and internal
suppliers sites of:
Bulk Material
Production Material
Production Parts
Service Parts
For Bulk material PPAP is not required unless
asked by the customer.
A supplier of production parts / service parts
shall comply with the PPAP requirements unless
the same is formally waived by the Customer
(documented evidences should be available)
Application
Something
Changed
AIAG (Automotive
Industry Action Group)
PPAP manual defines
when PPAP submission
is required
New part
Correction to discrepancy
in previous submission
Design or process change
Change in source of
subcontracted materials
or services
transfer or
Benefits of PPAP
submission
Helps to maintain design integrity
Identifies issues early for resolution
Reduces
warranty
charges
and
prevents cost of poor quality
Assists
with
managing
supplier
changes
Prevents use of unapproved and
nonconforming parts
Identifies suppliers that need more
development
Improves the overall quality of the
product & customer satisfaction
Submission Levels
The supplier shall submit the items and/or records specified by
the level as requested by the customer.
Level 1 Warrant only (and for designated appearance items, an
Appearance Approval Report) submitted to the customer.
Level 2 - Warrant with product samples and limited supporting
data submitted to the customer.
Level 3 Warrant with product samples and complete supporting
data submitted to the customer.
Level 4 Warrant and other requirements as defined by the
customer.
Level 5 - Warrant with product samples and complete supporting
data available for review at the suppliers manufacturing location.
Definition of Risk
High Risk
Parts associated with multiple critical features, complex
design, or high end technology that is not yet
established in the general manufacturing environment
Suppliers quality system and/or quality performance is
not to Customers satisfaction
Medium Risk
Parts that have at least one critical feature
Low Risk
Parts that have no critical features and can be
manufactured by any manufacturer in the commodity
category
Suppliers quality system and quality performance are
New
Parts
acceptable
Part Changes
Level 3 is required for Parts produced at a new or additional location
Supplier Quality Excellence will define the level required for all other changes
PPAP Status.
Approved
The part meets all Customer
requirements
Supplier is authorized to ship
production quantities of the part
Interim Approval
Permits shipment of part on a
limited time or piece quantity basis
Rejected
The part does not meet customer
requirements,
based
on
the
production lot from which it was
Design Records
Authorized Engineering Change Documents
Customer Engineering Approval, if required
Design Failure Modes and Effects Analysis (DFMEA) applied in
special situations
Process Flow Diagram
Process Failure Modes and Effects Analysis (PFMEA)
Control Plan
Measurement Systems Analysis (MSA)
Dimensional Results
Records of Material / Performance Test Results
Initial Process Studies
Qualified Laboratory Documentation
Appearance Approval Report (AAR)
Sample Production Parts
Master Sample
Checking Aids
Customer-Specific Requirements
Part Submission Warrant (PSW)
1. Design Records
Design Records and & Bubbled Part Prints
Purpose:
To document & provide a copy of the formal part print.
All part prints must have clearly defined CTQs
To provide any additional engineering records for reference.
All submissions should have one copy of the formal print
Bubble print that supports the dimensional report.
Must have all notes and specifications circled and
numbered.
Must be clear and legible.
Any additional supporting information including
Reference prints
Sub-assembly prints
Component prints with a different part number
Applicable specifications
2. Engineering Change
Documents
The
supplier
shall
provide
authorized change documents
for those changes not yet
recorded in the design record,
but incorporated in the product,
part or tooling, such as:
ECNs (must be approved, not pending)
Specifications
Feasibility studies Advantages
Supplier change requests
Sub-assembly drawings
Life or reliability testing requirements
3. Customer Engineering
Approvals
Purpose:
To demonstrate pre-approval by Customer
to produce a product
Required only when customer demands
FMEA
Failure Mode and Effects
Analysis
What we learn?
What is it?
Motivation
FMEA Methods
Example
FMEA in-class exercise
What is FMEA?
Failure Mode & Effect
Description: Analysis
A procedure that examines each item
in a system, considers how that item
can fail and then determines how that
failure will affect the system
A structured approach to:
Identifying the ways in which a product or process can fail
Estimating risk associated with specific causes
Prioritizing the actions that should be taken to reduce risk
Evaluating design validation plan (product) or current control plan (process)
History of FMEA
First used in the 1960s in the
Aerospace industry during the Apollo
missions
In 1974, the Navy developed MIL-STD1629 regarding the use of FMEA
In the late 1970s, the automotive
industry was driven by liability costs
to use FMEA
Later, the automotive industry saw
the advantages of using this tool to
reduce risks related to poor quality
4. DESIGN FMEA
(DFMEA)
The Design FMEA is used to analyze products
before they are released to production.
It focuses on potential failure modes of products
caused
by
design
deficiencies.
Design FMEAs are normally done at three levels
system, subsystem, and component levels
This type of FMEA is used to analyze hardware,
functions or a combination
Method to Conduct an
FMEA
Identify all components or systems at
given level of the design hierarchy.
List the function of each identified
component or system.
Identify failure modes for each
component/system.
Typically there
will be several ways in which a
component can fail.
Determine the effect (both locally
and globally) on the system.
Method to Conduct an
FMEA
FMEA Form
Severity
Assessment of the seriousness of the effect of the potential failure
mode to the customer. Give ranking between 1 & 10 as per the
guidelines
Classification
To Classify any special characteristics such as critical, key, major,
significant, etc.,
Potential Causes / Mechanism of Failure
How failure could occur described in terms of how the failure
can be corrected or can be controlled.
Potential Causes of failure should be engineering related such as
incorrect material, corrosion, wear and human related such as
inexperience, misuse, etc.
Occurrence
How frequently the specific failure cause / mechanism is projected
to occur. Give ranking between 1 & 10 as per the guidelines
Effect
Criteria
None
No effect
Very Slight
Slight
Minor
Moderate
Severe
High Severity
Very High
Severity
Extreme Severity
Maximum
Severity
10
Rank
Criteria
Extremely
Unlikely
Remote Likelihood 2
Very Low
Likelihood
Low Likelihood
Moderately Low
Likelihood
Medium
Likelihood
Moderately High
Likelihood
Very High
Severity
Extreme Severity
Maximum
10
Detection
Ran
k
Criteria
Extremely Likely
Very High
Likelihood
High Likelihood
Moderately High
Likelihood
Medium Likelihood
Moderately Low
Likelihood
Low Likelihood
Very Low
Likelihood
Remote Likelihood
Extremely Unlikely
10
Effect 1
Failure Mode 2
Effect 2
Failure Mode 1
Effect 1
Failure Mode 2
Effect 1
Failure Mode 1
Effect 2
Verify
Make
sure
that
high
RPN
process concerns are carried
over into the control plan
Make
FMEA EXERCISE
5. Process Flow
Diagrams
What is It?
A visual diagram of the entire process from receiving
through shipping, including outside processes and
services
Objective or Purpose
To help people see the real process. Process maps
can be used to understand the following characteristics
of a process:
Set-by-step process linkage
7. CONTROL PLAN
What we learn?
What is it?
When to use?
Why Required?
Over view
Example of Control Plan
Control Plan Process
Class Exercise
CONTROL PLAN
What Is A Control Plan?
It is a management tool to identify and monitor the activity required
to control the critical inputs or key outputs for a process so the
process will continually meet its product or service goals.
Control plans are usually monitored at least by Quality Assurance,
departments using inspection procedures and sometimes using
quality function deployment methods.
Control charts are typically used in a control plan to monitor items.
When Is It Used?
It is used in the control phase to identify and record controls,
targets, and specification limits for Key Process Input Variables and
Key Process Output Variables.
from
the
engineering
Effectiveness of controls
Control plan (say) vs. what is actually done
(do)
Use process flow diagram and PFMEA to build the control plan; keep
them aligned
Controls must be used to be effective. Keep it simple.
Ensure that the control plan is in the document control system of the
business
Good control plans address:
All testing requirements - dimensional, material, and performance
All product and process characteristics at every step throughout
the process
The control method should be based on an effective analysis of the
process
Such as SPC, Error Proofing, Inspection, Sampling Plan
Control plans should reference other documentation
Specifications, tooling, etc.
8. Measurement System
Analysis (MSA)
What is It?
An MSA is a statistical tool used to determine if a
measurement system is capable of precise measurement.
Objective or Purpose
To determine how much error is in the measurement due to
the measurement process itself.
Quantifies the variability added by the measurement
system.
Applicable to attribute data and variable data.
When to Use It
On the critical inputs and outputs prior to collecting data
for analysis.
For any new or modified process in order to ensure the
quality of the data.
Measurement System
Analysis (MSA)
Attribute Data Examples:
Measurement System
Analysis (MSA)
Repeatability
Error in Repeatability
Possible Cause
Equipment Variation
Measurement System
Analysis (MSA)
Reproducibility
Error in Reproducibility
Possible Cause
Appraiser Variation
Step 2
Step 3
Step 4
Step 5
Step 6
Step 7
Step 8
Step 9 Step 10
Measurement System
Analysis (MSA)
9. Dimension Test
Results
What is It?
Evidence that dimensional verifications have been completed
and results indicate compliance with specified requirements.
Objective or Purpose
To show conformance to the customer part on dimensions
and all other noted requirements.
When to Use It
For each unique manufacturing process (e.g., cells or
production lines and all molds, patters, or dies
10. Records of
Material/Performance Test
Results
The supplier shall perform tests for all parts and product
materials when chemical, physical, or metallurgical
requirements are specified by the design record or
Control Plan
For products with NCR-developed material specifications and/or
an NCR-approved supplier list, the supplier shall procure
materials and/or services from suppliers on that list
When to Use It ?
1. To establish baseline capability.
2. To validate process improvements.
Step 2 Step 3
Step 4
Step 5
Step 6
Step 7
Capability Indices
Capability
Index
Cp
Cpk
PP
Ppk
Formula
(USL LSL)
6*sshort-term
Min{(USL X), (X LSL)}
3*sshort-term
(USL LSL)
6*slong-term
Min{(USL X), (X LSL)}
3*slong-term
What it shows
Relates short term (within subgroup) standard
deviation to tolerance
Sometimes called Entitlement, meaning it is the
best the current process can do, if centered
Relates short term mean & short term (within
subgroup) standard deviation to tolerance
Only tells you about the nearest spec limit; doesnt
tell anything about the other side
Cpk Index of of Cp
measures the variation of Cp value
between U and L and consider the
variation closest to Specification limit.
Ensure
PPAPs
Appearance Approval
Report
What is It?
A report completed by the
appearance and color criteria
supplier
containing
Objective or Purpose
Typically only applies for parts with color, grain, or surface appearance requirements
When to Use It
Sample parts should be delivered WITH the PPAP
submission
The sample parts provided should be the same parts measured for the dimensional results
Default quantity for all submissions is 3 parts unless otherwise requested
Points to Remember ..
Supplier is responsible for meeting all applicable specifications.
Do not submit parts and documentation results if they are
outside specification.
Take corrective action to meet all design record requirements.
Contact customer if unable to meet all requirements
Comply with customer developed material specifications and/or
approved source list.
Suppliers are required to complete and maintain copies of all
documentation identified in requirements for approval
regardless of submission level.
Records of PPAP are to be retained for the life of the part plus
one calendar year.
References
PPAP 4TH Edition
Quality Planning and Analysis by J.M.Juran & Frank.M.Gryna
www.citehr.com
Production Operations Management Dr.B.S.Goel
Wikipedia