QC functions in eALPS+

The following are functions


* Piping Specification upload (its a one time entry)Pipe Spec.JPG
* Weld test specification upload (its one time entry) Weld test spec .JPG
* Welding Procedure Specification upload (its one time entry )WPS.JPG
* Welder Master upload Complete Welder Master.JPG
* Daily Welding progress upload. (Activity Sequence.JPG, FITUP1 .JPG, ,Weld Visual1 .JPG
RT Report.JPG, MPT.JPG)
* NDT offering and uploading reports
* Spool clearance
Reports through eALPS+:

*
*
*
*
*
*
*
*

Daily Fitup reports


Daily weld visual reports
Overall NDT STATUS
NDT Backlog Report
Weekly welders rejection rate
Tracer weld status report
Bolt Tightening report (under development)
Test Package Status Report (under development)

NDT Offering & Reports through eALPS

4/11/15

NDT Offering & Reporting through eALPS+

Inputs required for NDT Offering through eALPS+:

* Daily Welding progress upload.


* NDT Group creation.
* NDT Joint selection(offer).
* NDT Group Pass
* Tracer weld Selection

NDT Offering & Reports through eALPS

4/11/15

Daily Welding Progress


upload

Check points:

WPS Qualified Range - WPS Master


Welder Qualified Range( Dia & Thk)- Welder Master
Time span for joint to offer for NDT-3 days maximum
1st day- Welding Inspection at shop/field
2nd day- Daily progress upload + NDT Group Create
3rd day- Joint Selection+ Offer for NDT
NDT Offering & Reports through eALPS

4/11/15

NDT Group Creation


Logic:
* Specified no.of joints are grouped into single lot as per NDT requirement for
each piping spec(e.g for 5% NDT, 20 joints are made into one group).
Input for NDT requirement:
* For each Weld Test Specification NDT requirements for BW, BR and SW are
updated in eALPS+.
* For example see below snap shot of eALPS+ for PE16 Piping spec

NDT Offering & Reports through eALPS

4/11/15

Group Creation

NDT Offering & Reports through eALPS

4/11/15

Group Creation

Same procedure is applicable for other NDE Group


creation(DPT,MPI,PWHT, PMI, HT)
NDT Offering & Reports through eALPS

4/11/15

NDT Joint Selection


* After creation of groups ,a joint from EACH group shall be picked for NDT offering
* Prior to joint selection the following things shall be ensured
o Welder coverage in each NDT scope %

shall be monitored for required % coverage , it


can be done by using welders rejection rate report.

NDT Offering & Reports through eALPS

4/11/15

NDT Offer

Sample:
MPI OFFER
DPT OFFER
PWHT OFFER
NDT Offering & Reports through eALPS

4/11/15

Tracer(Penalty) Weld Selection for


rejected joints
Need to select two joints for each welder for each rejected joints as penalty .
Two joints shall be selected from the same lot.
If tracer welds are already been selected for repaired joint, the Joint ID wouldnt
available in drop down.

NDT Offering & Reports through eALPS

4/11/15

NDT Group pass


* Activity has to perform after the respective test reports are uploaded at

ealps+.
* Without NDT offer/testing acceptance report ,the group can not be passed
and released for further activity (Erection planning)

NDT Offering & Reports through eALPS

4/11/15

NDT Offer Status


NDT status of each group can be traceable.

NDT Offering & Reports through eALPS

4/11/15

Spool Clearance
Once All NDT Groups are passed, spools will be released by
eALPS system itself and spool status can be verified through
Spool history report in eALPS Spool Clerance (SC).JPG

NDT Offering & Reports through eALPS

4/11/15

Reports through eALPS


Daily Fitup reports -.xls
Daily weld visual reports -.xls
Overall NDT STATUS -.xls
NDT Backlog Report -.xls
Weekly welders rejection rate -.xls
Tracer weld status report -.xls
Bolt Tightening report -.xls(Under
Development)
Test Package Status Report -.xls(Under
Development)

NDT Offering & Reports through eALPS

4/11/15

Need Support for following


Required complete repair joints status report in tracer weld
reports. (under development)
Required support weld progress upload and its visual report.
(under development)
Required NDT offer status as per required modified report.
(under development)
Required Test Package Status report (under development)

NDT Offering & Reports through eALPS

4/11/15