Академический Документы
Профессиональный Документы
Культура Документы
Presentation Contents
Introduction
Segment Casting
Storage Yard in the Site
Delivery and Storage of Segments
Movement of Launching Girder
Presentation Contents
Introduction
Contract Details
Overview of Contract Works
Bridge Arrangement
Segment Casting
Delivery and Storage of Segments
Bridge Segment Erection
Movement of Launching Girder
HARBOUR GRAND
HONG KONG
CITY GARDEN
HARBOUR
HEIGHTS
VICTORIA
CENTRE
Noise
Enclosure
EXISTING IEC
HING FAT SLIP
ROAD
BOX CULVERT
U1
NEW IEC W/B
TUNNEL APPROACH
RAMP
to D2)
Bridg e D (D1
ge
Brid
Bridge D3
Brid ge F
(F
1 to F3)
Brid
ge
F5
Br
id
Bridge C (C1 to
C5)
F3)
Bridge F ( F1 to
City Garden
Harbour
Height
Victoria
Centre
ge
F
Existing Bridge
Precast Segments Bridges
Re-Construct Westbound Bridge
Provident Centre
Span length :
26.5m to 40.0m
Bridge types :
653 segments
60 beams
5
Presentation Contents
Introduction
Segment Casting
Typical Segments
Casting Yard
Segment Casting
Delivery and Storage of Segments
Bridge Segment Erection
Movement of Launching Girder
26.5m to 40.0m
Maximum Super-Elevation
3.7%
Maximum Gradient
4.86%
350m
150 tons
Zhongshan,
China
Contract
HY/2009/19 Site
Precast Segment
Fabrication Yard
Hong Kong
Macau
10
11
12
Step 7 - Demoulding
Presentation Contents
Introduction
Segment Casting
Delivery and Storage of Segments
Delivery Route
Unloading Point
Storage Yard
Bridge Segment Erection
Movement of Launching Girder
14
Zhongshan,
China
Contract
HY/2009/19 Site
Precast Segment
Fabrication Yard
Hong Kong
Macau
15
PORTION III
PORTION VII
16
Segment Storage
(Max. Capacity = 20 Segments)
Front View
Side View
Stacking Arrangement
Segment Barge
Unloading
Derrick
Bridge Loading
Area
(After
completion of
Bridge D3)
17
Unloading Derrick
Presentation Contents
Introduction
Segment Casting
Delivery and Storage of Segments
Bridge Segment Erection
Launching Girder
Main Support and Lifting Beam
Install Bearing and Segment at Piers by Crawl Cranes
Segment Erection by Launching Girder
Movement of Launching Girder
19
REAR LEG
(RL)
MAIN SUPPORT
(MS2)
MASTER
WINCH
(MW01)
MAIN TRUSS
MAIN SUPPORT
(MS1)
MAIN SUPPORT
(MS3)
General Specification
Dimension (L x W x H)
160 T
700 T (7 segments)
Fabrication
Wuhu, China
20
Section
Elevation
Jack for adjustment of
crossfall and longitudinal fall
of segment
Main Truss
Section
Plan
Elevation
Section
Main Truss of
Launching Girder
Hanger Beam
Hanger Beam
Elevation
Section
Temporary
Hydraulic
Jacks
Bearing
s
(Example Photo)
Temporary Hydraulic
Jack
Adjusting Jack
Bearing
27
MJ Segments
Pier
Segments
28
Fixed by high
strength bars
Fixed by Nailing
At Intermediate Pier
29
3. Install Master
Winches
1. Install Main
Support on erected
segment
1. Install Main
Support on erected
segment
30
7. The certificate of launching girder issued by RPE once the load test is
satisfactory.
33
Temporary
Prestress Bars to
be removed
Design check for permanent structure (e.g. pier) due to segment erection is
required.
34
1 2 3 4 5
Temporary
Prestress Bars and
Supports to be
removed
6 7
Construct Stitch
Joint
As-constructed
Segment
Cantilever
Design check for permanent structure (e.g. pier) due to segment erection is
required.
35
30
50
Density
1685kg/m3
1685kg/m3
Pot time
>35 minutes
>20 minutes
Open time
>60 minutes
>60 minutes
>65MPa
>70MPa
>80MPa
>80MPa
Steel blister at
bridge deck
Bar is stressed by
Hydraulic Jack
Temporary
Prestressing Bar
Bar is stressed
by Hydraulic
Jack
Temporary
Prestressing Bar
Prestressing bars
Prestressing bars
Concrete Blisters
Elevation
Steel Blisters
Stitch Joint
Stitch Formwork
40
Permanent Prestressing
Thread strand through the tendon duct
Apply prestressing force gradually until required stressing force is attained.
(Min=784KN ,Max=4312KN)
Release the pressure, allow the wedge to draw-in and lock strand
Permanent Prestressing
Platform for workers of prestressing work (for balanced cantilever segment
erection only)
It is hung under the main truss of launching girder
Main Truss of
launching girder
Winch for
hanging
hydraulic
jack
Section
Stressing
platform
Erection
Completed grouting
(Example Photo)
43
Presentation Contents
Introduction
Segment Casting
Storage Yard in the Site
Bridge Segment Erection
Movement of Launching Girder
Forward Launching
Forward Launching in Curve Section
Typhoon Anchors
General Erection Sequence
44
Assemble
LG onLG
pier
D8,9,10 as
Launch
to D9,10,11
shown
LG
forward
MS again
LG forward
until reach
segments
ofasLaunch
Tshown
spanLaunch
by
Install segments
of endInstall
span Move
Erect
segments
of TD11
as shown.
pair
span
span
D12
segment at D12
span
Erect external
tendons
Cast the
stitch
Pier
D8
Cast the
stitch
Cast the
stitch
Pier
D9
Pier
D10
Cast the
stitch
Pier
D11
Pier
D12
Main Truss
Main Support
Main Truss
Main Support
46
Main Support
Main Truss
Edge of Existing
Bridge
47
300mm
Pier
F8
48
40 HIGH-STENGTH PT BAR
(PRELOADED TO 700KN
EACH)
40 HIGH-STENGTH PT BAR
(PRELOADED TO 700KN
EACH)
49
Sequence
Duration (Approx.)
206 Days
187 Days
100 Days
Pier
D8
Pier
D1
Pier
22
Abut
D12
Pier
F3
Pier
28
Pier
F8
Pier
43
Re-construct Westbound Bridge
(Connect to Approach Ramp)
THE END
51
51