Академический Документы
Профессиональный Документы
Культура Документы
Content
MRP overview
Benefits of MRP
MRP application
Requirements of an effective MRP system
MRP system
The development of MRP
An Overview of MRP
MRP is a computer-based information system
An Overview of MRP
Dependent demand: demand for a higher-
Benefits of MRP
Ability to keep track of material requirements:
MRP application
Apply for the typical manufacturing or
Industry type
Assemble-tostock
Examples
Expecte
d
benefits
High
Low
High
Low
High
Requirements of An
Effective
system
A computer andMRP
necessary software
programs;
Accurate and up-to-date master schedules,
bills of materials and inventory records;
Integrity of file data.
MRP System
Includes 3 major sources:
Master production schedule
Bill of materials
Inventory records
Answer 3 questions:
What is needed?
How much is needed?
When is it needed?
MRP System
MRP
Input Master
Orders
Production
MRP
Forecast Output
Schedule
MRP ProcessingChanges
Planned-order
schedules
Order releases
Design
Bill of
Materials
change
MRP
Computer
Programs
Exception reports
Planning reports
Receipts
Withdrawals
Inventory
Records
Bo
Performanceco n
hng
controlthc
reports
hin
Cc
Inventory
nghip v
d
transactions
tr
MRP Input
Includes:
- Master Production Schedule
- Bill of Materials
- Inventory Records
MRP Input
Master Production Schedule
Are made by:
- Demand from the known customers
- Forecast demand
=>Questions:
- Which end items are to be produced;
- When these are needed;
- And in what quantities?
MRP Input
Master Production Schedule
The schedule indicates that 100 units of X will
be needed at the start of week 8
X
Quantity
(units)
8
100
MRP Input
B(2) C(1)
Level 2
E(4) D(3)
Level 3
H (4)
G(2)
I (5)
F(2)
MRP Input
Bill of Materials
Example: Determine the quantities of B, C, D, E,
F, G, H and I needed to assemble one unit of X
Answer:
MRP Input
Inventory Records
Information on the status of each item by time
period
- Gross requirements, scheduled receipts,
expected amount on hand;
- Details for each item: supplier, lead time, lot
size;
- Changes due to stock receipts and withdrawals,
canceled orders
=> Must be accurate and up-dated
Part No.
Description
Order quantity
Class
Control balance
Totals
Projected
available balance
Planned order
releases
Order details
Subsidiary data
segment
Pending action
Counters
Keeping track
Etc.
MRP Processing
MRP Computer Program
Steps to follow:
- Specify end item requirement by the master
schedule
- Explode them into time-phased
requirement for assemblies, parts, and raw
materials using the BOM offset by lead times;
- Determine net requirements in period t
MRP Processing
Step 1: specify end item requirement
X
Quantity
100
(units)
Wee 1
k
MRP Processing
Step 2: Assembly Time chart
Week 1 Week 2 Week 3 Week 4 Week 5 Week 6 Week 7 Week 8
Procurement
of H
Fabrication of D
Procurement
of I
Subassembly B
Final
assembly
X
Procurement of E
Procurement of G
Subassembly C
Fabrication of F
MRP Processing
Step 3: Determine net requirements in
periodProjecte
t:
Net
Gross
d
requirem
requirem
Safety
=
- inventor +
ents in
ents in
stock
y in
period t
period t
period t
MRP Processing
MRP Output
Primary reports:
Planned orders: amount and timing of future
orders
Order releases: authorization for executing
planned orders
Changes: in date, quantity, cancellation, etc.
Secondary reports:
Performance-control reports
Planning reports
Exception reports
Example
A firm that produces wood shutters and bookcases has
received two orders for shutters: one for 100 shutters and one
for 150 shutters. The 100-unit order is due for delivery at the
start of week 4 of the current schedule, and the 150-unit
order is due for delivery at the start of week 8. Each shutter
consists of two frames and four slatted wood sections, and its
assembly takes 1 week. The wood sections are made by the
firm, and fabrication takes 1 week. The frames are ordered,
and lead time is 2 weeks. There is a scheduled receipt of 70
wood sections in week 1. Determine the size and timing of
planned-order released necessary to meet delivery
requirements under each of these conditions:
1. Lot-for-lot ordering
2. Lot-size ordering with a lot size of 320 units for frames and 70
units for wood sections.
Development of MRP
Manufacturing resources planning (MRP