BRGF Status as on

30.04.2015
Dist- Birbhum
Agency JSL , Pk-5

Schedule completion date : December


2014

Revised target : 30/06/2015


Time Overrun: 6 Months
Criticality: Fund problem.
Follow up action: : Agency advised to

Agency L&T, Pk-5A

Schedule completion date January -2015


Revised target : 30/06/2015
Time Overrun: 5 Months
Criticality: Mobilization of Work
Follow up action: Asked Agency to speed-up
the Job.

BRGF Status as on
30.04.2015
Dist- Birbhum
Agency JSL , Pk-5

Criticality: Fund problem &


Manpower.
Follow up action: Agency

Agency L&T, Pk-5A

Criticality: Late mobilization of


work & Man Power problem.
Follow up action: Man Power
problem solved. Asked Agency for
Proper planning to speed up the

BRGF Status as on
30.04.2015
Dist- Birbhum
Agency JSL , Pk-5

Agency L&T, Pk-5A

Criticality: Fund, Manpower &

Criticality: Planning & Crops in

Crops in the Field

the Field.

Follow up action: Agency


advised to solve fund problem &

Follow up action: Man Power


problem solved. Asked Agency for

BRGF Status as on
30.04.2015
Dist- Birbhum
Agency JSL , Pk-5

Criticality: Fund , Materials &

Agency L&T, Pk-5A

Criticality: Manpower.

Manpower

Follow up action: : Agency

Follow up action: Asked Agency


to improve Manpower.

BRGF Status as on
30.04.2015
Dist- Birbhum
Agency JSL , Pk-5

Agency L&T, Pk-5A

Criticality: Fund ,Materials &


Manpower.

Follow up action: : Agency


advised to solve fund problem &
speed up the Job.

Criticality: Matching material.


Follow up action: Asked Agency to
supply Matching material

BRGF Status as on
30.04.2015
Dist- Birbhum
Agency JSL , Pk-5

Criticality: Pole.
Follow up action: : Agency advised
to solve fund problem & speed up the
Job.

Agency L&T, Pk-5A

Criticality:

Matching material.
Follow up action: Asked Agency to
supply material.

Scope

66,155

W. O. Issued

38,632

BRGF Status as on. 30.04.2015 Installed


Energized
Dist-Birbhum
F-III sent to
DCC

APL

Agency JSL , Pk-5

Criticality: Fund problem &


dispute location.

Follow up action: Dispute issues

34,787
32,727
26,492

Agency L&T, Pk-5A

Criticality: Material & dispute


location.

Follow up action: Asked Agency


to supply material & dispute issues

Scope

BRGF Status as on 30.04.2015W. O. Issued


Installed
Dist-Birbhum
Energized
BPL

Agency JSL , Pk-5

Criticality: Fund problem &


dispute location.

Follow up action: Dispute issues

F-III sent to
DCC

63,122
11,919
12,523
11,087
8,715

Agency L&T, Pk-5A

Criticality: BPL intened to take


connection as APL, Material
Problem.

MARGRAM 33/11 KV SUB-STATION

MARGRAM 33/11 KV SUB-STATION

MARGRAM 33/11 KV SUB-STATION

MARGRAM 33/11 KV SUB-STATION (CONTROL ROOM)

RAJGRAM 33/11 KV SUB-STATION

RAJGRAM 33/11 KV SUB-STATION

RAJGRAM 33/11 KV SUB-STATION

Head Quarter Follow up action /


Instruction
PK 5 (Jyoti)

Agency has been asked to speed up their work.


Service Cable is the Critical Item and it will reach at site by end of
December, 2014.
So far 9.68 Cr. L.C. opened for all the 5 districts for different materials out
of 10 Cr. after several persuasions by our highest authority.
DI issued materials will be reached at different project sites by end of
December, 2014.

PK 5A (L &T)

Zone code & DTR code is not available due to non-compliance of APL
Consumers and as a result DTR charging is getting hampered.
Agency advised to complete HT Stringing by May 2015.
PM advised to submit revised BOQ for next course of action.