Академический Документы
Профессиональный Документы
Культура Документы
Question 5
Key Words
Trainee ( No Experience)
Medium Cost Housing Development
Preliminary Sketches Drawing
One Day to complete task
Methods of estimating
a. Single rate estimating
b. Multiple rate estimating
Square Meter
Definition
Requirement
Calculation
Advantages
Disadvantages
Produce an estimate
quickly
A very minimum data
required to estimate
Has a huge amount of
data is published based
on square meter cost
Easy to communicate to
layman
Requirements:
a) Client has a budget set for the project.
How to obtain?
Cost is obtained by comparing previous projects
of similar nature and dividing the total cost by the
number of functional units obtained.
Calculation:
Example 1:
A school cost MYR 5,000,000 and provided 1000
student places the functional unit cost is MYR 5000
per school place.
Example 2:
From previous experience, the cost of a 50 bed
hospitals has been constructed for MYR 60 millions
(60,000,000). Hence, the unit cost = MYR 60
million/500beds=MYR120,000 per bed. Thus,
estimated 40 bed wing hospital will be 400 x MYR
120,000=MYR48 million.
Advantage:
Produces estimate very quickly
A minimum data required
Easy communicate to layman
Disadvantages:
Low level of accuracy
No breakdown of the single rate, not useful for cost
control.
APPROXIMATE QUANTITIES
Approximate quantities
measurement
substructure
External
work
Superstructure
Internal
finishes
Fitting and
furniture
preliminaries
contingencies
Advantages
Disadvantages
Calculation:
A cavity wall measured and priced with both skin included in the
unit rate. The rate includes forming cavity, wall ties, plastering
and pointing (according to the specification). If the previous
project does not include plastering and pointing, adjustment must
be made accordingly.
Elemental Cost
Estimating
Definition
Using the Elemental Cost Analysis (ECA) to estimate a
building cost.
Requirement
Basic size and shape of building (Preliminary sketch)
Purpose and location of building
Historical cost data of similar buildings constructed at the
same general location
Advantages
More accurate than square meter method
Only needs a very minimum information to prepare
the estimate, hence can be used as early as feasibility
stage of project
Disadvantages
Faster but less accurate than approximate method
Part B
Scenario 1
If the trainee has access to ECA and knows how to utilize
the information extracted
Elemental Cost Estimating is the most suitable method
It takes into account all the elements of the building
Information is easy to find since its a typical medium
cost development
Takes a minimum time to complete the estimate since its
only taking the GFA of one house and multiplying it to
the cost per m2.
Scenario 2
If the trainee has no experience on using the ECA or have
no access to it
Square meter method is most suitable
A very minimum data required
A lot of data are published based on cost per square meter
Very straight forward, easy to understand
Questions
1. What are the factors to choose which
method of estimating to use?
2. Why is elemental cost more accurate than
square area method?