GUJARAT
welcomes
Sh C S PRASAD
DG, CPWD
to
AHMEDABAD
Belvedere
House,
Bhulabhai
Desai
Road
Before repair
After repair
Project Details
REVISED AA & ES Amount : Rs.173.80 Crores
(Without DC, Architects Fee & Service Tax)
Plot Area
: 10,000 sqm
Floors
:2B+G+7
Permissible built up area : 20,000 sqm
Proposed built up area : 22,740 sqm
Basement Area
: 13,843 sqm
Present Status : Structure Completed
Likely date of application: 28-02-10
Likely date of completion: 31-03-10
Punjab
National
Bank Office
Building
Salient Features
DESIGN CONCEPT :
The Internal Finishes in Main Lobby and Floor Lobbies are combination of
Italian Marble and Granite in Floors and Dados. The Floor of Toilets and
Pantries will have Granite Flooring with Coloured Glazed Tiles full height
Dado on walls. The Internal Finishes of the Office Areas will be a part of
Interiors.
PASSPORT
OFFICE PLOT
Back
Left
Right
Front
Entrance Lobby
Concept
safety signage's
Rain water harvesting: All roof top rain water shall be canalised to the rainwater
harvesting
tank and used for horticulture.
Brief Specifications:
Combination of composite aluminum panel / Granite
Polished granite stone counters & combination of granite with marble flooring
for first three floors.
Vitrified tile flooring in other floors.
Double skinned pre laminated particle board partitions.
Canopy with steel space frame & Composite
Aluminium panel.
doors.
CPWD WORKS
IN
MUMBAI
(excluding BKC)
AA &ES
Stipulated date of start
: 43.20 Crores
:- 27/05/2009
:- 26/12/2010
Status as on 29-11-09
Hostel
Building
for
NITIE
G+16
Project Details
REVISED AA & ES Amount : Rs.40.50 Crores
Floors
: Ground + First floor (Dining hall) + 15
upper floors (Hostel).
Proposed built up area : 11,144 sqm
Present Status : Mobilization of man & machinary in
progress
Date of start: 16-12-09
Date of completion: 15-08-11
Hostel building
for National
Institute of
Industrial
Engineering
Renovation
work at
Securities
Appellate
Tribunal
DANTIWADA
VADNAGAR
HIMMATNAGAR
DEHGAM
s IN GUJARAT
CPWD
Name of Work
Location
Amount
Status
Jamnagar
1800.00
In Progress
Gandhinagar
600.00
In Progress
C/o RVTI
Baroda
380.00
In Progress
Ahmedabad
470.00
In Progress
Gandhinagar
160.00
Completed &
Handed over In
June 2009
ACADEMIC / EDUCATIONAL
BUILDINGS
Sr
Name of Work
Location
Amount (in
Lakhs)
Status
Jawahar Navodaya
Vidhyalaya
2810.00
In Progress
Jawahar Navodaya
Vidhyalaya
105.00
Under
Planning
Kendriya Vidhalaya
3000.00
Tendering in
progress
IIT Gandhinagar
Gandhinagar
150.00
In Progress
Central University of
Gujarat
Gandhinagar
100.00
In Progress
PARA-MILITARY WORKS
Sr
Name of Work
Location
Amount
Status
Dantiwada
1100.00
In Progress
Gandhinagar
185.00
In Progress
Gandhinagar
221.00
DE Prepared
Gandhinagar
261.00
DE is being
Prepared
Gandhinagar
175.00
In Progress
Bhuj
1500.00
work in
progress
Ahmedabad
300.00
work awarded
Rajkot
180.00
work awarded
Name of Work
Location
Amount
Status
Ahmedabad
2900.00
In progress
Surat
560.00
In progress
Gandhidham
360.00
Himmatnagar
210.00
In Progress
Okha
368.00
DE under
Preparation
Ahmedabad
8300.00
CNE Held
Gandhinagar
Prelim. stage
Requisition
Recd.
SPORTS WORKS
Sr
Name of Work
Location
Amount
Status
Gandhinagar
200.00
Completed
Gandhinagar
350.00
Completed
Gandhinagar
398.00
In Progress
4.
Gandhinagar
100.00
In Progress
5.
Gandhinagar
127.00
In Progress
Name of Work
Location
Amount
Status
Silvassa
340.00
In
Progress(70%)
Diu
320.00
In Progress
Daman
420.00
Under Planning
Daman
740.00
Under Planning
MISC. WORKS
Sr
Name of Work
Location
Amount
Status
Diu
290.00
Completed
Silvassa
190.00
In Progress
Ahmedabad
471.00
Work Started.
Baroda
2800.00
Under Planning
Project
Details
Project
Details
C/o 100 Bedded Hostel for SAI at Gandhinagar
Project Details
Project Details
:
:
:
:
:
:
Rs.100.00 Lakhs
Ground Floor
258991 Sqm.
550.88 Sqm.
90% work completed.
17.05.2009
: 31.05.2010
Project Details
Modern Fitness Centre for SAI at Gandhinagar
Project Details
Office Building for Income Tax at Himmatnagar
Providing & Laying Global Category Synthetic Hockey Surface at S.A.I., Gandhinagar.
Cost : Rs. 150.00 Lacs
Date of Actual Completion : 02.01.2008
Providing & Laying 400 M Standard Synthetic Athletic Track for SAI, Gandhinagar.
Cost : Rs. 350.00 Lakhs
Date of Actual Completion : 07.11.2009
C/o Vertical Extension of Boys & Girls Hostels for IHM at Gandhinagar.
Cost : Rs. 160.00 Lakhs
ACTUAL DOC 31-05-2009