Project: Meaning
Definite Objective
Definite Timeframe
NICMAR, PUNE
SANJAY BHOYAR
Project Life-Cycle:
Concept &
feasibility
Operating &
Maintenance
Engg &
Design
Procurement
Commissioning
Construction
& Start-up
NICMAR, PUNE
SANJAY BHOYAR
Project Life-Cycle:
NICMAR, PUNE
SANJAY BHOYAR
Complexity in projects
Timely completion of projects
Resources limitations
Cost of capital
Price escalation
Increased outlay
Longer spans
Risks have increased
Financers require workable plan
Setting targets against which performance can be
measured
NICMAR, PUNE
SANJAY BHOYAR
Project Management:
Major functions:
Planning
Organizing
Controlling
Cost
Time
Quality &
Performance
Project scope
NICMAR, PUNE
SANJAY BHOYAR
Project Planning:
Design
Procurement
Construction
NICMAR, PUNE
SANJAY BHOYAR
a WBS
an OBS, & Responsibility matrix
Project Schedules
Cost accounts for cost aggregation & control
Budgets
PMIS
NICMAR, PUNE
SANJAY BHOYAR
Project deliverables
Sub-division of deliverables
work packages,
sub-work packages &
Activities
Project
Deliverables
Work packages
Activities:
NICMAR, PUNE
SANJAY BHOYAR
Preliminary
works
Bldg A
Buildings
Bldg B
Sub-structure
-Setting out
-Excavation
-PCC
-RCC footing
-RCC for PB
-Plinth filling
Amenities
Club house
Service facilities
Swimming pool
Drainage
Super-structure
-RCC column
-RCC slab & beams
-Brickwork
-Plastering
-Plumbing
-Flooring
-Doors & windows
-Electrification
-Painting
SANJAY BHOYAR
NICMAR, PUNE
Road Project
Road
Earthwork
Sub-grade
Major Bridges
Minor Bridges/
c/d works
Subways/
Underpasses
Pavement
Drainage
Lighting
Base
Sub-base
Wearing surface
Metalling
Compacting
NICMAR, PUNE
SANJAY BHOYAR
Hydropower Project
1.
2.
3.
4.
5.
6.
7.
8.
9.
Dam
HRT (Transfer Tunnel)
U/S Surge Shaft
Penstock Shaft
Power House
TRT
Sub-station Workshop
Operations Building
Transmission Line
NICMAR, PUNE
SANJAY BHOYAR
Dam
1.
1.1 Diversions
1.2 Dam wall construction
1.3 Spillway section
1.4 Gates
1.5 D/s works
1.6 Delivery tunnel
2.
HRT
2.1 ADIT
2.2 Tunnel construction
2.2.1 Survey & profile marking
2.2.2 Drilling & blasting
2.2.3 Defuming & mucking
2.2.4 Bottom cleaning
2.2.5 Rock bolting
2.2.6 Rib erection, legging & backfill concrete
2.2.7 Shotcrete
3.
4.
NICMAR, PUNE
SANJAY BHOYAR
5. Power house
5.1 Civil Works
5.1.1ADIT
5.1.2 Underground cavern
5.1.3 Main access tunnel
5.1.4 Transformer chamber
5.1.5 Penstock valve chamber
5.1.6 Access tunnel
5.1.7 D/S surge chamber
5.2 Turbines & Valves
5.2.1 Turbines
5.2.2 Penstock guard valve
5.2.3 Turbine inlet valve
5.2.4 Bypass valve
5.3 Electrical Works
5.3.1 Generators
5.3.2 Switch gear
5.3.3 Power transformer
6. TRT
7. Sub-station Workshop
8. Operations Building
9. Transmission Line
NICMAR, PUNE
SANJAY BHOYAR
Project Scheduling:
Part of Planning
Time-cost relationship
NICMAR, PUNE
SANJAY BHOYAR
Steps in Project
Scheduling:
Analysis of schedule
NICMAR, PUNE
SANJAY BHOYAR
Scheduling Techniques:
Non-Network techniques
chainage diagram
Line of balance (LOB) technique
CPM
PERT
NICMAR, PUNE
SANJAY BHOYAR
Network scheduling:
Activity:
AOA / AD / ADM
AON / ND / PDM
Event:
NICMAR, PUNE
SANJAY BHOYAR
Project start
1
D
B
G
3
NICMAR, PUNE
duration
Project finish
6
5
SANJAY BHOYAR
START
NICMAR, PUNE
FINISH
SANJAY BHOYAR
CPM Problem
Activity
Preceding activity
Succeeding
activity
Duration
H,F,G
K,L
C,D
E,H
F,G
L,N
NICMAR, PUNE
SANJAY BHOYAR
A-O-A Network
E
7
2
A
3
B
5
6
7
d2
D
4
H
4
5
9
d1
N
F
6
4
9
L
2
11
M
P
8
10
d3
G
7
NICMAR, PUNE
SANJAY BHOYAR
12
A-O-N Network
START
NICMAR, PUNE
SANJAY BHOYAR
FINISH
NICMAR, PUNE
SANJAY BHOYAR
Scheduling by CPM:
NICMAR, PUNE
SANJAY BHOYAR
EFT = EST + t
LST = LFT - t
NICMAR, PUNE
prec
Act
succ
SANJAY BHOYAR
CPM analysis
Float:
Total float:
prec
Act
succ
Free float:
FF = [ESTsucc - EFT]min
NICMAR, PUNE
SANJAY BHOYAR
CPM analysis
Critical activity:
Critical path:
NICMAR, PUNE
SANJAY BHOYAR
0 A 3
4 3 7
4
0
3 E 10
7 7 14
4
0
10 K 17
14 7 21
4
0
17 M 22
21 5 26
4
4
9 H 13
12 4 16
3
0
13 L 15
16 2 18
3
3
18 P 26
18 8 26
0
0
6 F 12
9 6 15
3
3
15 N 18
15 3 18
0
0
0
START
0
0 B 5
3 5 8
3
0
0 C 6
0 6 6
0
0
5 D 9
8 4 12
3
0
26
FINISH
26
Description
ES Act EF
CP: C-G-N-P
PD = 26
NICMAR, PUNE
6 G 15
6 9 15
0
0
LS
TF
SANJAY BHOYAR
LF
FF
A-O-N PDM
Precedence
Relationships:
-3
B
+5
B
+3
+4
A
PDM problem:
Activity
Duration
Predecessor
10
SS + 2
FS
FS
FS - 2
SS + 5
FS
12
FS
SF + 5
10
FS
FS
FS
FS
FS
FF +2
Relationship with
lead/ lag time
NICMAR, PUNE
10 M 19
11 9 20
1
0 K 10
0 10 10
0
START
15 Q 22
16 7 23
1
5
2 2
5
3
L 8
6 11
Description
-2
10 N 15
10 5 15
0
6
9
3
P 14
8 17
15 R 19
19 4 23
4
34
22 U 31
23 9 32
1
FINISH
34
2
15 S 27
15 12 27
0
5
27 V 34
27 7 34
0
ES Act EF
LS
LF
TF
NICMAR, PUNE
14 T 24
17 10 27
3
CP: K-N-S-V
PD = 34
SANJAY BHOYAR
NICMAR, PUNE
SANJAY BHOYAR
Scheduling by PERT:
NICMAR, PUNE
SANJAY BHOYAR
PERT analysis:
Activity time estimates
Beta distribution
Expected/ mean
duration of an activity
Variance of an activity
NICMAR, PUNE
te
to 4.t m t p
6
t p to
2
SANJAY BHOYAR
PERT analysis
Project completion (event) time:
proj varproj
NICMAR, PUNE
SANJAY BHOYAR
PERT analysis
Probability calculations:
Normal value
NICMAR, PUNE
SANJAY BHOYAR
PERT Problem
Activit
y
Preceding
activity
to
tm
(weeks) (weeks)
10
13
B,G
B,G
E,F,K
M,N
10
NICMAR, PUNE
tp
(weeks)
SANJAY BHOYAR
NICMAR, PUNE
SANJAY BHOYAR
Activity
Preceding
activity
to
tm
tp
te
3.17
0.25
0.44
7.16
0.25
0.44
4.33
0.44
0.11
10
13
10
5.16
0.69
B,G
7.67
0.44
B,G
0.44
0.44
E,F,K
2.83
0.25
M,N
5.83
0.69
10
0.11
NICMAR, PUNE
SANJAY BHOYAR
PERT Network
A
3.17
30
17.16
7.16
40
7.16
24.83
C
7.16
15.33
70
21.67
H
5.16
E
4.33
F
2
B
5
10
0
3.17
20
9.50
10.17
50
16.50
G
10
17.16
60
17.16
80
24.83
M
6
N
2.83
27.67
100
27.67
7.67
L
4
P
5.83
21.16
90
24.50
33.50
110
33.50
EOT
i
LOT
Act
te
SANJAY BHOYAR
EOT
j
LOT
Z = (30-33.50)/1.62 = -2.16
Corresponding, p = 0.0154 = 1.54%
Z = (35-33.50)/1.62 = 0.93
Corresponding, p = 0.8238 = 82.38%
NICMAR, PUNE
SANJAY BHOYAR
Project costs:
Direct costs
Indirect costs
Penalties / incentives
Time-cost trade-off
NICMAR, PUNE
SANJAY BHOYAR
Compression:
critical activities
Crashing:
NICMAR, PUNE
SANJAY BHOYAR
Indirect Cost
Direct Cost
Project duration
Minimum PD
NICMAR, PUNE
Optimum PD
Normal PD
SANJAY BHOYAR
Steps in compression:
NICMAR, PUNE
SANJAY BHOYAR
Numerical problem:
Activity
Precedin
g activity
NT
(weeks)
CT
(weeks)
NC
(x Rs 1000)
CC
(x Rs 1000)
64
76
30
33
54
74
28
34
70
91
82
92
47
47
D,E
39
45
27
30
86
98
F,H
55
65
27
29
SANJAY BHOYAR
Activity
NT
CT
NC
CC
Compression
potential
Cost
slope
64
76
30
33
54
74
28
34
70
91
82
92
10
47
47
39
45
27
30
86
98
55
65
27
29
NICMAR, PUNE
SANJAY BHOYAR
A(6)
START
C(9)
G(4)
L(9)
D(3)
H(6)
M(5)
K(3)
N(2)
B(4)
E(7)
A-O-N Network
(normal durations)
F(5)
Paths
A-C-G-L
28*
A-D-H-M
20
B-E-H-M
22
B-F-M
14
B-F-K-N
14
NICMAR, PUNE
FINISH
SANJAY BHOYAR
A(6)
START
C(9)
G(4)
L(9)
D(3)
H(6)
M(5)
K(3)
N(2)
B(4)
E(7)
A-O-N Network
(normal durations)
F(5)
Paths
FINISH
A-C-G-L
28*
25*
22*
21*
20*
19
A-D-H-M
20
20
20
20
18
16
B-E-H-M
22
22
22*
21*
20*
19
B-F-M
14
14
14
13
12
11
B-F-K-N
14
14
14
13
13
13
NICMAR, PUNE
SANJAY BHOYAR
Compression table:
Stage
Act
CS
Dur of
comp
PD
Increase
in DC
DC
IC
TC
28
609
280
889
25
12
621
250
871
22
15
636
220
856
5
1
21
08
644
210
854
20
11
655
200
855
19
11
666
190
856
M
NICMAR, PUNE
SANJAY BHOYAR
NPD
OPD
Min
PD
A(6)
START
B(3)
A-O-N Network
(Optimum PD)
START
B(3)
NICMAR, PUNE
G(4)
L(6)
D(3)
H(6)
M(5)
K(3)
N(2)
C(5)
G(4)
L(6)
D(3)
H(6)
M(3)
K(3)
N(2)
FINISH
E(7)
F(5)
A(4)
A-O-N Network
(Minimum PD)
C(5)
E(7)
F(5)
SANJAY BHOYAR
FINISH
Resources scheduling:
Resources allocation
Resources aggregation
Resources smoothing
Resources leveling
NICMAR, PUNE
SANJAY BHOYAR
RUF or EFR =
NICMAR, PUNE
SANJAY BHOYAR
Preceding activity
Duration (days)
Resource rate
D,E
F,H
NICMAR, PUNE
SANJAY BHOYAR
ESS
G/6
C/6
A/5
L/5
D/5
E/4
B/4
H/3
M/7
F/2
K/2
Days
DRR (ESS)
9 11 11 17 17 17 12 12 11 15 15 9
NICMAR, PUNE
10
11
N/6
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
9 13 13 12 12 12 5
SANJAY BHOYAR
293
G/6
C/6
A/5
ESS
L/5
D/5
E/4
B/4
H/3
M/7
F/2
N/6
K/2
G/6
C/6
D/5
A/5
H/3
E/4
B/4
TRIAL1
L/5
M/7
F/2
K/2
Days
DRR (ESS)
DRR (Trial 1)
11 11 17 17 17 12 12 11 15 15
13 13 12 12 12
11 11 12 12 12 12 12 13 17 17
SANJAY BHOYAR
10
11
N/6
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
NICMAR, PUNE
293
8 12 12 12 12 12
293
G/6
C/6
A/5
ESS
L/5
D/5
E/4
B/4
H/3
M/7
F/2
N/6
K/2
G/6
C/6
D/5
A/5
H/3
E/4
B/4
TRIAL 2
L/5
M/7
F/2
N/6
K/2
Days
DRR (ESS)
DRR (Trial 2)
11 11 17 17 17 12 12 11 15 15
13 13 12 12 12
293
11 11 10 12 12 12 12 12 11 11
293
SANJAY BHOYAR
10
11
12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28
9 12 12 12 12 12 11 11 11
NICMAR, PUNE
NICMAR, PUNE
SANJAY BHOYAR
NICMAR, PUNE
SANJAY BHOYAR
Sample problem:
Progress
rate
(km/day)
Duration
for 12 km
Buffer
Start
buffer
End
buffer
Start
time
Finish
time
Subgrade
1.0
12
12
Sub-base
0.5
24
26
Base
0.5
24
28
Wearing
course
1.5
22
30
NICMAR, PUNE
SANJAY BHOYAR
Time-chainage Diagram
12
11
10
Sub-base
Chainage (km)
Sub-grade
Wearing
Base
7
6
5
4
3
2
1
0 1 2 3 4 5 6 7 8 9 10 1112 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
NICMAR, PUNE
Time (days)
SANJAY BHOYAR
Monitoring:
Control:
NICMAR, PUNE
SANJAY BHOYAR
Project Control
Base Plan
-schedule
-budget
-scope
Raplace
Base plan
Revised Plan
-schedule
-budget
-scope
NICMAR, PUNE
Actual status
-schedule
-budget
-scope
Deviations
-schedule
-budget
-scope
Corrective Actions
SANJAY BHOYAR
S- curve
Earned value
NICMAR, PUNE
SANJAY BHOYAR
Cost variance
CV = BCWP - ACWP
Cost performance index
CPI = BCWP/ ACWP
Estimated cost at project completion
EAC = BAC/ CPI
Schedule variance
SV = BCWP - BCWS
Schedule performance index
SPI = BCWP/ BCWS
Estimated time for project completion
ETPC = STPC/ SPI
Project performance index (Critical ratio) = SPI x CPI
NICMAR, PUNE
SANJAY BHOYAR
Sample problem:
Task Duratio
n
(weeks)
Preceding Budgeted
task
cost
(Rs in
lacs)
Status by end of
5th week
% complete
Actual
expendi
ture
(Rs in
lacs)
100
20
40
30
33.33
12
24
50
16
50
16
D,E
B,F,G
18
NICMAR, PUNE
SANJAY BHOYAR
Task Duratio
n
(weeks)
Weightag
es
Budgeted
cost
(Rs in
lacs)
Status by end of
5th week
%
complete
Actual
expendi
% project ture
Progress (Rs in
lacs)
11.54
100
11.54
19.24
20
40
7.70
11.54
30
33.33
3.85
12
15.38
24
50
7.70
7.69
16
50
3.85
15.38
16
11.54
7.69
18
NICMAR, PUNE
100
34.64
SANJAY
BHOYAR
B/4
A/2
C/10
ESS
F/4
D/6
H/9
G/3
E/8
Weeks
NICMAR, PUNE
11
12
3.85
3.85
3.85
3.85
3.85
3.85
7.70
100
28
28
20
14
11
34
62
82
96
107
114
121
130
139
11.54
10
SANJAY BHOYAR
Dura Budgete
tion d cost
(BC)
Sched Sched
uled
uled
Start Finish
% completion Cost
Sched
uled
(WS)
Actual
(WP)
Schedul
ed
(BCWS
)
Actual
(ACWP
)
Earned
value
(BCWP
)
100
100
20
40
40
30
66.67
33.33
20
12
10
24
50
50
12
12
16
100
50
16
16
10
10
18
10
12
62
42
44
NICMAR, PUNE
SANJAY BHOYAR
SANJAY BHOYAR
Thank You
NICMAR, PUNE
SANJAY BHOYAR