Вы находитесь на странице: 1из 36

MIVAN FORMWORK

Presented by,
VB

11/9/15
1

Overview
Introduction
Formwork definition and discussions
Components and assembly of MIVAN formwork
Construction with MIVAN
Work cycle
Quality enhancements
Merits and demerits
Remedies proposed
Conclusion and Inference
Bibliography
11/9/15

Introduction
Concept of ALUMINIUM FORMWORK
Developed by MIVAN GROUPS, MALAYSIA
Driving force speed of construction, quality of

construction, seismic resistivity, economy


Good quality construction should not deter the project

speed nor should it be uneconomical

Cost is long forgotten, but the quality is


remembered forever
11/9/15

Construction Industry
Significant sectors of Indian economy
Indias urban population - Second largest
Land acquisition and rapid creation of dwelling units
Fortunately, now speed of construction is given

importance.
Prefabrication, autoclaved blocks, tunnel formwork,
aluminium formwork (Mivan technology) of
construction
11/9/15

Housing Scenario - India


Progressive rise in stock of housing in India

since independence
But speed has not kept pace with the rapid

growth of population and urbanization


And hence shortage of accommodation is

increasing continuously
The situation has become acute in urban areas
11/9/15

Innovation in Construction Technology


Traditional mode of construction - inadequate for

mass housing construction.


Prone to poor quality control
Mass housing works technologies for fast

construction to deliver quality, economic and durable


structure.
Pre-cast and cast-in-situ techniques are used for

quick construction.
Use of Aluminum alloy for formwork
11/9/15

What is a Formwork?

Support for plastic concrete when placed


Temporary supports and castings

Forms or moulds or shutters are the


receptacles in which concrete is placed, so
that it will have desired shape or outline when
hardened. Once concrete develops the
adequate strength to support its own weight
they can be taken out. - ACC
11/9/15

Formwork - Requirements
Sufficiently strong enough
The joints should be rigid
Construction lines in the formwork should be

true
Easily removable without damage to itself

11/9/15

MIVAN System
3S - SYSTEM OF CONSTRUCTION - Speed, Strength, Safety
Column and beam construction eliminated
Walls and slabs are cast in one operation
Specially designed, easy to handle light weight pre-engineered

aluminium forms.
Rapid construction of multiple units of repetitive type using

semi-skilled labours.
Fitting and erecting the portion of shuttering
Carrying out concreting of the walls and slabs together.

11/9/15

MIVAN Formwork
Aluminum alloy panels
Excellent stiffness-to-weight ratio
Face or contact surface - 4mm thick plate
Pin and wedge arrangement system
Requires no bracing
High strength wall ties
Small panels no heavy equipment
11/9/15

10

MIVAN FORMWORK
Heavy lifting eliminated
Semi skilled labors
Fast construction suitable for large magnitudes
Good quality with accurate dimensions
System components are durable repetitive
Monolithic construction

Mivan 4day cycle


Conventional 14 to 20 day cycle
Plastering eliminated completely
11/9/15

11

Comparison Mivan and


Conventional
More seismic resistance
Increased durability
Lesser number of joints reduced leakages
Higher carpet area
Smooth finishing of wall and slab
Uniform quality of construction
Negligible maintenance
Faster completion
11/9/15

12

Construction with MIVAN


PRE CONCRETE ACTIVITIES
Receipt of equipment on site
Level surveys
Setting out of formwork
Control / correction of deviation
Erect formwork vertical
Erect deck formwork
Setting kickers

11/9/15

13

Checks before Concreting


Formwork should be cleaned and coated
Wall formwork erected to the setting out lines
Openings are of correct dimensions
Horizontal formwork are in level
Deck and beam props are vertical
Wall ties, pins and wedges are all in position
Surplus material are cleared
11/9/15

14

On Concrete Activities
Checking pins, wedges and wall ties
Beam / deck props adjacent to drop areas

slipping due to vibration


Bracing at special areas slipping due to

vibration
Overspill of concrete at window opening

11/9/15

15

Post Concrete Activities


Strike down wall form
Strike deck form
Clean, transport and stack formwork
Strike down kicker formwork
Strike wall mounted working platform
All formwork can be struck after 12 hours

11/9/15

16

Beam components
Beam Side Panel

Prop Head

Beam Soffit Bulkhead


Beam Soffit Panel
11/9/15

17

Deck Components
Prop
Length

Deck
Panel

Deck Mid Beam

Deck Beam Bar


Soffit Length

Deck Prop
11/9/15

18

Other Components
External
Corner
Internal Soffit Corner

Internal Corner

11/9/15

External Soffit Corner

19

Wall Components
Wall Panel

Rocker

Kicker

11/9/15

20

Pin and Wedge System


Pin

Stub
11/9/15

21

Formwork Assembly

11/9/15

22

11/9/15
23

11/9/15

24

11/9/15

25

11/9/15

26

11/9/15

27

Work Cycle
System for scheduling & controlling the work of other

connected construction trades


Deshuttering of the panels 12 to 15 hrs
Positioning brackets & platforms on the level- 10 to 15 hrs
Deshuttered panels lifted & fixed on floor-7 to 10 hrs
Kicker & external shutters fixed in 7 hrs
Shutters are erected in 6-8 hrs
Reinforcement and electrical conduits are fixed 20 to 22

hrs
Pouring concrete
11/9/15

28

4 Day Cycle
Day 1: erection of vertical reinforcement bars and

one side of the vertical formwork


Day 2: erection of the second side of the vertical

formwork and formwork for the slab


Day 3: fixing reinforcement bars for slabs and

casting of walls and slabs


Day 4: removal of vertical form work panels after

24hours, props in place for 7 days, floor slab


formwork in place for 2.5 days
11/9/15

29

Quality Enhancements
High quality formwork panels - consistency of

dimensions
Level and verticality
Plastering eliminated
3mm to 4mm skin coat enough for pleasant

appearance
11/9/15

30

Merits
Total system forms the complete concrete

structure
Custom designed to suit project requirements
Unsurpassed construction speed
High quality finish
Cost effective
Panels can be reused up to 250 times
Erected using unskilled labour
Quality and speed - given due consideration
along with economy
11/9/15

31

Limitations
Because of small sizes - finishing lines are

seen
Concealed services become difficult
Requires uniform planning and uniform
elevations to be cost effective
Modifications are not possible
Large volume of work is necessary to be cost
effective
Spacers, wall ties - seepage, leakages during
monsoon
Shrinkage cracks
High heat of hydration shear walls

11/9/15

32

Remedial Measures
Wall ties - create holes in wall after deshuttering
Box-type construction - shrinkage cracks, near door

and window openings in the walls


Minimize these cracks by providing control strips in

the structure which could be concreted after a delay


of about 3 to 7 days after major concreting
The problem of cracking can be avoided by

minimizing the heat of hydration by using Flyash


11/9/15

33

Conclusion and Inference


Civil engineers not only build but also enhance the

quality of life
Creativity and technical skill help to plan, design,
construct and operate the facilities essential to life
MIVAN - cost effective and efficient tool to solve
problems of the mega housing project
MIVAN construction is able to provide high quality
construction at unbelievable speed and at
reasonable cost
Effective technology India

Cost is long forgotten, but the quality is


remembered forever
11/9/15

34

Bibliography
http://en.wikipedia.org/wiki/Formwork
http://www.reliancescaffolding.com/Wall-Form

-works/form-work.asp
www.mivan.com
www.mivantelecomms.com/news/?id=42&q

11/9/15

35

Thank You

11/9/15

36

Вам также может понравиться