Вы находитесь на странице: 1из 10

WBS-Construction of House

Lecture by Junaid Arshad Department of


Engineering Management
Abridged and adapted by A. M. Al-Araki,
sept. 2013

1.

WBS-Construction of House (Example)

2.

WBS Dictionary

3.

Organization Breakdown Structure (OBS)

Decide individual tasks


necessary to complete the
house

The individual tasks necessary to complete the house.

Level 1

Level 1: is the highest level (ACME)


where the project (house) will be
summarized.
NOTE: We assume that the design is complete, all
permits issued, all material ordered and
inspection happens

Level 2 is identified at the project level: House. It


correspond to Level 1. In this case, the code is 1.1.

Level 1

Level 2
2

Divide the work into the major elements needed to build a house. You
divide Level 3 into six elements: concrete, framing, plumbing,
electrical, interior and roofing. These are both major deliverables and
milestones for managing the project. They also enable the project by task.
Each codes at level 3 is unique to the project and starts with the WBS code
from the level above (11.11.1.1).
Do we need another level?

Level 1
Level 2

Level 3

Level 4 of the WBS will enable us to manage the project as desired. All of
our contractors fit into specific elements at level 4, and so do all specific
departments. Organization Breakdown Structure (OBS)

The WBS is complete. It does include the necessary components to


manage the project by task.

Level 1
Level 2

Level 3

Level 4

Housing Corporation
1.1 New Home Construction
1.1.1 Concrete
1.1.1.1 Pour Foundation
1.1.1.2 Install Patio
1.1.1.3 Pour Stairway
1.1.2 Framing
1.1.2.1 Frame Exterior Walls
1.1.2.2 Frame Interior Walls
1.1.2.3 Install Roofing Trusses
1.1.3 Plumbing
1.1.3.1 Install Water Lines
1.1.3.2 Install Gas Lines
1.1.3.3 Install B/K Fixtures
1.1.4 Electrical
1.1.4.1 Install Wiring
1.1.4.2 Install Outlets/Switches
1.1.4.3 Install Fixtures
1.1.5 Interior
1.1.5.1 Install Drywall
1.1.5.2 Install Carpets
1.1.5.3 Install Painting
1.1.6 Roofing
1.1.6.1 Install Felt
1.1.6.2 Install Shingles
1.1.6.3 Install Vents

WBS Dictionary
The WBS dictionary is a narrative documentation of the effort needed to
accomplish all work defined in the WBS. The WBS dictionary is
developed for the lowest level element in the WBS only.
To better understand how a WBS and a WBS dictionary work, lets
compare it to a book and the books table of contents:

The WBS is the table of contents for the project. It captures the
contents in an organized fashion (chapters, subchapter).

The WBS dictionary is the book itself. It tells the story. In our case
the story is what work will be accomplished and what outputs will
be produced in each of the WBS elements. The total of these
descriptions is how a house will be built and what is needed to build
the house.

The WBS dictionary will often lead to the development of the Scope of
work (SOW) for the project.
6

WBS Dictionary

WBS Dictionary describes each component of


the WBS e.g.
Milestone
Deliverables
Activities
Scope
Resources
Quality
Cost
Sometime

dates

Organization Breakdown Structure (OBS)


Develop

the Organizational Breakdown Structure (OBS) for the


project. This indicates the organizational relationships and is
used as the framework for assigning work responsibilities. See
next slide.

The

OBS is structured by Responsible Department and then


by Performing Department at the lowest level. This
Performing Department level is where the responsibility and
resource needed to accomplish the project will be assigned.

With

the relationships and responsibilities defined, second and


final step is to merge the WBS and OBS.
8

Organization Breakdown Structure (OBS)


PROJECT OFFICE
RESP
DEPT
B. Smithers
CIVIL

STRUCTURAL

ELECTICAL

PLUMBING

RESP DEPT

RESP DEPT

RESP DEPT

RESP DEPT

R. Kelly

P. Tate

J. Sims

R. Lee

CONCRETE

CARPENTRY

WIRING

WATER/SEWER

PERF DEPT 5010

PERF DEPT 4010

PERF DEPT 3010

M. Manning

R. Sites

S. Johnson

K. Wells

MASONRY

ROOFING

HOOKUP/TIE-IN

GAS

PERF DEPT 6020

PERF DEPT 5020

PERF DEPT 4020

PERF DEPT 6010

T. Greams

Y. Taylor

TEST

DRYWALL

PERF DEPT 6030

PERF DEPT 5030

K. Neumann

D. Smith

P. Ottis

PERF DEPT 3020


R. Oriely

WBS-Construction of House cont.


Earlier

topics: [WBS], [Dictionary of WBS] and [OBS]

Continuation:
Responsibility

Assignment Matrix (RAM)

Technical

Approach, Scope of Work,


Specifications,
Risk
Management and Resource Allocation based on WBS
Multiple
The

Ways to Develop WBS

100% Rule

10

Вам также может понравиться