Вы находитесь на странице: 1из 9

Information for process owners

Upgrade of SAP PI 7.1 to SAP PO 7.4


March 2015
Jorge Lopez Lead Integration and Development

Content
SAP PI is the integration hub at Nobel Biocare
Objective and scope of migration to version SAP PO 7.4
Migration and Test approach
Timeline
Test responsible by Integration Scenario

SAP PI is the integration hub at Nobel Biocare

SAP PI is the integration hub processing all transactions between


applications

Online Store
Front End Scanners (NobelProcera, NobelClinician, 3shape)
Manufacturing systems (Implant Systems and Procera plants)
VMI cabinets
Suppliers
CVM
And many more

A total of 500000+
messages are processed
daily in realtime 24/7

Objective and scope of migration to version 7.4

The current SAP PI 7.1 system is running


unchanged since 2011 and will run out of support

An upgrade to the current version SAP PO 7.4 is


required to ensure support, improve performance
further and reduce cost of operations

New functions will be used for business


requirements like the UDI submission

There will be no functional changes of existing


interfaces by the upgrade

Migration and Test approach

The new SAP PO 7.4 will be installed as a separate


system landscape in parallel to SAP PI 7.1

No big bang - Interfaces can be migrated one by


one once a UAT is successful

In case of issues on a specific interface on PO 7.4,


this can fall back to the PI 7.1 system

All business critical processes need to be tested


end-to-end and signed off before deployment to
production

Migration day and time can be aligned with the


process owner to minimize business impact

Time line
Milestones

Tests can start from April 6

Tests should be completed by April 24

Interface migrations during May month

Shut down old PI systems by end of June


Task
Analyze active interfaces
Prepare test system POA and connect to
interfaced test systems
Migrate interfaces to test system POA
User Acceptance Test on POA (UAT)
Deployment to production system POP
Fallback period with parallel systems
Shut down old system PIP

March

April

May

June

Test responsible by Integration Scenario


List of Integration Scenarios and responsible person (tester and IT)
Integration scenario
Online Store
NobelProcera
NobelClinician/3shape
Manufacturing IS
Manufacturing Procera
CVM
Cloud for travel
Supplier integration SMI
VMI cabinets
Bloomberg

Responsible Tester

Responsible IT

Deadline UAT

Questions?
and answers
Question

Answer

BACKUP: SAP Integration Overview

SAP PI is the 24/7 integration hub processing all transactions


between applications

E.g. the order flow from the front ends and the online store to
SAP and further down to the production systems

A total of 500000+
messages are
processed daily

Green arrows
represent PI
intergration

Example
Example of
of
Business critical
Business
critical
interfaces
interfaces

Вам также может понравиться