CONSTRUCTION
Presumption
Earth work is not significant part in road
construction
No Technical skills required
It is nothing but dumping and dozing
Except earth work team all other are
important part of road team
But
Earth work Engineer is the face of the company
Entire project reputation depends on his behavior
skills and communication skills as he is the first
man to deal with locals
He playes different roles
like leader,
IR manager,
Manager
Engineer
Supervisor and
Lost but not least as labour
Types of roads
Express ways
National high ways
State high ways
Major district roads
Minor district roads
Other district roads
Village road
EARTH WORK IN
EXCAVATION
Classification
Excavation in soil
Excavation in ordinary rock (not required
blasting)
Excavation in rock required blasting
Soil
Top soil
Gravel
Mud
Silt
Clay
Sand
And any material of one side less than
75mm and can be picked by pick axe
comes under the above category
EMBANKMENT
CONSTRUCTION
.
25
25
25
25
25
25
25
25
Sand Content
2 tests per 3000 cubic metre of soil.
Plasticity Test
Each type to be tested, 2 tests per 3000 cub. metres of soil.
Density Test
Each soil type to be tested, 2 tests per 3000 cubic metres of
soil.
Deleterious Content Test
As and when required by the Engineer.
Moisture Content Test
One test for every 250 cubic metres of soil.
CBR Test
One CBR test for every 3000 cu.m. atleast or closer as and
when required by the Engineer.
Suitable material
Soil
Gravel
moorum
stump
Unsuitable Material
Materials from swamps, marshes and bogs
Peat, log, stump and perishable material
Materials susceptible to spontaneous
combustion;
Materials in a frozen condition;
Highly expansive soils exhibiting marked
swell and shrinkage properties (free
swelling index exceeding 50 per cent when
tested as per IS: 2720-Part 40)
Density requirement
Embankments up to 3
metres
height,
not
subjected to
extensive
flooding
Embankments exceeding 3
metres
height
or
embankments
of
any
height subject to long
periods of inundation
Construction
Before starting any activity the toe line
should be marked.
the original ground shall be leveled to
facilitate placement of first layer of
embankment, scarified, mixed with water
and then compacted by rolling to achieve
the compaction requirements
Spreading
The embankment and subgrade material
shall be spread in layers of uniform
thickness not exceeding 200 mm
compacted thickness over the entire width
of embankment/sub grade
Each compacted layer shall be finished
parallel to the final cross-section of the
embankment/sub grade
Compaction
Moisture content of the spreaded soil to be
checked and if required water to be added
are else it should be allowed for dry.
At the time of compaction Moisture content
should be in the range of 1 per cent above
to 2 per cent below the optimum moisture
content Compaction
In no case compaction started when
moisture is more than required OMC