Академический Документы
Профессиональный Документы
Культура Документы
Project Monitoring
The set of procedures and management practices used to
Purpose
Monitor the actual values of the project planning
Time
Cost
Project Control
tivities
Step 2. measure activity progress and actual cost
Step 3. calculate project progress as weighed sum
of activities
Budget
Structur
es
Footings
Procuremen
t
Budgeted
Quantity
Unit
Cost
76
Activity
Weigh
1,100,001.
40
100%
Budget
148,200.0
0
13%
106,400.0
1400
0
72%
Step
2
Structu
res
Actual
Actual
Quanti
Unit Cost
ty
Footings
Procurement
Shipping
Construction
Columns
Procurement
Shipping
Construction
700,000.52
162,209.12
1500
118,500.00
203.28
16,059.12
350
27,650.00
537,791.40
3200
345,600.00
400
43,200.00
1379.55
148,991.40
79
79
79
108
108
108
Actual Cost
[10 months]
Step
3
Budget
Actual
Activity
ed
Activity Project
Quanti
Progres
Quantit
Weigh Progress
ty
s
56.48
y
%
Structu
res
Footin
gs
Procurem
ent
Shipping
Construct
ion
Colum
ns
Procurem
ent
104% 13%
14.0%
79
79
76
76
104%
104%
72%
10%
74.6%
10.7%
79
76
104%
18%
18.7%
108
49%
220
49%
87%
65%
42.5%
31.8%
Example (Continued)
Schedule:
Duration: 18 months
budget: 1,100,000 $
After 10 months:
Actual consumed cost: 700,000 $
Progress: 56.48%
And not 700,000/1,100,000 = 63.63 %
Performance Indices
Cost
Schedule
Fig. Areas of cost and time performance using Cost and Schedule performance
indexes
Example
Duration (Months)
Cost (1000$)
D(2, 60)
C(4, 60)
H(3, 75)
G(5, 50)
A(2, 40)
I(1, 40)
E(4, 80)
B(2, 50)
J(5, 100)
F(3, 60)
Activit A B
y
ES
LS
Cost/Mo
nth
0
0
2
0
2
2
2
25 1
2
2
30
2
7
20
2
4
20
6
6
10
4
8
25
11
11
40
5
7
20
Cumulative Costs
he following:
a) Budgeted cost(BCWS) =175k$ [ From master sched
ule]
b)
c)
Example: Continued
Cost
Schedule
0.37
EXAMPLE
Assume that operations on a Work Package cost 1,500$ to c
omplete. They were originally scheduled to finish today. At t
his point, we actually spent 1,350$. And we estimate that w
e have completed two thirds (2/3) of the work. What are the
cost and schedule variances?
EXERCISE
A project to develop a country park has an actual co
Time t
BCWS
ACWP
BCWP
Month 17
Solution
BCWS = 475,000
BCWP = 300,000
CV = BCWP ACWP
SV = BCWP BCWS
ACWP = 350,000
Forecasting Performance
Attempts to predict the conditions at a later time or th
ACWP / BCWP = 1 / CI
EAC = BAC / CI
Example [EAC]
BAC=1,100
BCWP=621; ACWP=700
EAC=BAC/CI
CI= BCWP/ACWP=621/700=0.887
EAC= 1,100 /0.887 = 1,240,000 $
VAC variance at completion = 1,100 1,240 = - 140,000
rk rate)