MOHAMAD IDHAM BIN NOR

RAHIM

PROJECT MANAGEMENT
& CONSTRUCTION
PRACTICE DDPA2033
MOHAMAD NURARIFULLAH BIN ABU BAKAR

CONSTRUCTION
PHASE
TEMPORARY
: AMINUDIN ALIWORKS

LECTURER
PRESENTER
RAHIM

: MOHAMAD IDHAM BIN NOR


MOHAMAD

WHAT IS TEMPORARY
WORKS?
Is a temporary structure
used to support permanent
structure and any associated
raking elements during its
erection and until it is self
supporting.

TYPES OF
TEMPORARY WORKS

HOARDING
SIGNAGE
SCAFFOLDING
TEMPORARY ACCESS R
WORKERS ACCOMODA
TEMPORARY STOR. ETC

Temporary Works
Preparation (BS 5975)
BRIEF DESIGN

VERTICAL &
OPENINF
CONTROL
INCLUDING
MAINTENANCE

DESIGN CHECK &


CINSTRUCTION
OPERATION

CONCEPT SCHEME

DESIGN &
SPECIFICATION

ADEQUATE
MATERIAL

DISMANTLING &
OPERATING OF
TEMPORARY
WORKS

SCAFFOLDING
Temporary erections,
constructed to support a
number of platforms at
different heights to enable
workmen to reach their
work and to permit the
raising of materials

TIMBER
SCAFFOLD
ING

TURBULAR
METAL
SCAFFOLDING

MAIN
COMPONENT:
TUBULAR
METAL
SCAFFOLDING
(MOST
COMMON)

PUTLOG
SCAFFOLDING
Consists of a single
row of uprights or
standard & uses
external wall as the
part of support
system

INDEPENDENT SCAFFOLDING
Consists of two row of standards
and do not rely upon the building for support

MOBILE SCAFFOLDING
Constructed to the basic
principles as independent
tubular scaffolds and are
used to provide access to
restricted or small areas
and/or where mobility is
required

NETTING

To prevent any
falling or flying
objects that can
seriously injure
people and severely
damage property.

FORMWORK
A structure, usually
temporary, used to contain
poured concrete to mould it
to the required dimensions
and support it until it is able
to support itself.

TYPES OF FORMWORKS

Pecaform
Tunnel Formwork
Climbing Formwork
Slip Formwork
Table Form
Wall Formwork
Steel Formwork

PECAFORM
steel wire mesh
with a heat
shrunk layer of
stabilised
polythene

TUNNEL
FORMWORK
enables walls and
slabs to be cast
monothically in one
day to achieve a oneday construction
cycle.

CLIMBING
FORMWORK
for vertical
concrete
structures

SLIP
FORMWORk
for tall

WALL
FORMWORK
ideal framed
formwork for largearea forming using
the crane

STEEL
FORMWORK

CASE STUDY:

SITE LOGISTIC

JOHOR LAND BERHAD


CADANGAN PEMBANGUNAN
DAN PEMBINAAN 2 BLOK 14
TINGKAT RUMAH PANGSA
SITE ENGINEER: MR.ALLEY

Site logistic(site layout)


used to show location:
:
Storage for construction
material
Temporary access road for
transportation
Site office
Factory
Entrance and guard house
Kongsi kong and canteen
Infrastruktur and others.

REASONS AND USE


FOR SITE LOGISTICS
LOCATION

MAIN ENTRANCE 1
The road is already done as the site is located in the middle of residential area

WASH TRUCK
Wash truck is for the trucks and lorries to wash their tires to prevent from dirty
the road as they can be summon by MPJBT.
Wash Truck is also placed beside the main entrance (Pintu Masuk 1) to enable
machineries wash.

GUARD HOUSE
To protect the site from strangers entering and damaging the site
To make sure that people who enters into the site is under the guards
permission and knowledge just for incase of emergency.

ENTRANCE 2
This entrance is for usage of the staffs just beside the site office so that they
can park their vehicle around office.

SITE OFFICE
Site office is important to monitor and to place the sites information just
incase if site is to be visited by Officers.

WORKERS HOUSE(RUMAH PEKERJA)


For the accommodation of foreign workers
Also included with toilets and bathrooms
Workers house is located at the end of the construction site because the site
construction starts from the middle towards the end. So Rumah pekerja will
be demolished at the end of the day.

TOWER CRANE 1(KREN MENARA 1)


Tower crane 1 is a 360 degrees crane that is located in between two
buildings which is under construction.
TOWER CRANE 2(KREN MENARA 2)
Tower Crane 2 is a 180 degrees crane. This crane is preferable to use
in this site because the site is beside residential area.
Works beside the main road is to be done by using Tower Crane 2 to
avoid trespassing.
GATHERING PLACE(TEMPAT BERKUMPUL)
This place is to gather during meeting every Monday morning from
8.00AM until 9.00AM to discuss about the progress of the site and the
problems accur during the construction.
BATHING PLANT
Bathing Plant is to store water for concreting works.
Batching Plant is located in the middle of the site so that it will be
easier to mix the concrete and to send to the building for concrete
works.
MACHINERY PARKING
Machinery parking is located just opposite to the Site Office so that is
under acknowledgement of the site clerks.
BARBENDER YARD
Barbender yard is to do the reinforcement for the building works
Barbender Yard is located near the Main Entrance (Pintu Masuk 1)
because it will be easier for the reinforcement supplier or lorries to
enter through the entrance and place it.

OTHER COMMOM
TEMPORARY
WORKS ON SITE

SCAFFOLDING(MODERN)

SIGNAGE
All the construction safety signs and warning signs must
clearly mark what the danger is in the area and who is or is
not allowed on the site. Signage is used to prevent
unauthorized personnel from entering or to make construction
workers aware of dangerous conditions

HOARDING
Close hoarded fences or barriers erected
adjacent or around the construction sites or
public footpath

TEMPORAR
Y BUIDING
ENTRANCE

TEMPORARY WORK
PLACE

TEMPORARY DUSTBIN

TEMPORARY
REFUSE CHUTE

TEMPORAR
Y
STORAGE

TEMPORARY STAIRCASE

TEMPORARY
ELETRICITY
SUPPLY

**HANDRAIL**

WORKPLACE

ACCESS
ROAD

BATCHIN
G PLANT

TEMPORARY
LIGHTS

Temporary light
inside the building

Access to transfer
material from floor
level to higher
floor

THANK
YOU