Академический Документы
Профессиональный Документы
Культура Документы
Dr. V. Thiruvengadam
Dr. V. Thiruvengadam
Dr. V. Thiruvengadam
Dr. V. Thiruvengadam
In a front loading strategy, profit margins are kept more on early items
like foundations and structural works to improve positive cash flow.
Dr. V. Thiruvengadam
Profit
Cost
Cumulative
Cost
Period
Dr. V. Thiruvengadam
Value
Cost
Cost
Period
Dr. V. Thiruvengadam
Total Cost
Material
Cumulative
Costs
Labor
Equipment
Subcontracto
r
Project Period
Costs
100
80
60
40
20
0
Costs
50
0
40
0
30
0
20
M1
M2 M3 M4
M5
M6
M7
0
10
00
M8
0 M1 M M M4 M5 M6 M7 M8
2 3
Cumulative
Cost Profile
Cost
Histogram
Months
M1
M2
M3
M4
M5
M6
M7
M8
Monthly Costs
50
60
70
80
60
50
40
20
Cumulative Costs
50
110
180
260
320
370
410
430
Dr. V. Thiruvengadam
% Cumulative Costs
Project S-curve
120
100
80
60
40
20
0
2/3
1/3
T
T Time Period
Dr.
% Cumulative Costs
Project S-curve
Dr.
120
100
80
60
40
20
0
1/3
2/3
T
T
Time Period
Project S curve
Example problem on S-curve
80
20
80
70
60
60
30
20
10
80
40
50
40
20
20
% Cumulative Costs
90
Period
Months
Monthly Costs
10
10
20
20
10
10
Cumulative Costs
Dr. V. Thiruvengadam
20
60
80
Project S curve
% Cumulative Costs
Use of S-Curve
Dr.
120
100
80
60
40
20
0
2/3
1/3
T PeriodT
Dr. V. Thiruvengadam
Dr. V. Thiruvengadam
2.
3.
4.
5.
6.
Dr. V. Thiruvengadam
7.
2.
Prepare the project schedule in the form of bar chart with activity
listings and durations. Schedules prepared using network techniques
are consolidated in bar chart formats.
3.
Determine activity costs from the itemized costs available in the bill of
quantities. One or more item costs may constitute an activity cost. A
raft foundation activity will involve items of reinforcement, shuttering
and concreting items.
4.
Determine the proportional costs that are expended per unit duration
(per month) of an activity. For some activities the expenses may not
be in a linear proportion over the activity duration. Such breakup of
activity cost within its duration is important for activities which
consume more resources/ cost in the early part and less cost in the
later part of the activity duration. For example activities involving
procurement
and installation of electrical/ mechanical works involve
Dr. V. Thiruvengadam
more cost for procurement and less cost for installation. In such cases
it may be better to keep procurement and installation as separate
For expenses towards overhead charges, the total cost under this
subhead may be distributed equally over the project periods.
6.
Calculate the monthly (or any other unit period) cost expenditure
of the project by summing up the cost expenditure of different
activities during the month under consideration. This means sum
the portions of activity costs of different activities incurred during
each monthly interval of the project. These monthly costs are
shown in the first row of the table at the bottom of the bar chart.
Calculate the cumulative monthly costs and show in the second
row of the table. (See Fig).These calculations could also arranged
in excel format.
7.
Dr. V. Thiruvengadam
9.
Dr. V. Thiruvengadam
Dr. V. Thiruvengadam
Cash Flow
Peaks due
to release
of retention
money
Negative
cash flow
period
Dr. V. Thiruvengadam
Positive
cash flow
period
Project Period
Profit
Row 12The difference between row 10 (cash inflow) and row 11 (cash
outflow) provides the net cash flow.
Time (months)
10
11
12
13
14
15
16
17
18
Cumulative Value
1.15
2.88
5.75
8.63
11.5
0
14.38
17.25
23.0
0
28.7
5
30.48
31.05
31.63
31.63
31.63
31.63
31.63
31.63
31.63
1.03
5
2.58
7
5.17
5
7.76
2
10.3
5
12.93
7
15.52
5
20.7
25.8
7
27.42
7
27.94
5
28.46
2
28.46
2
28.46
2
28.46
25
28.46
25
28.46
25
28.46
25
1.03
5
2.58
75
5.17
5
7.76
25
10.35
12.93
75
15.5
25
20.7
25.87
5
27.42
75
27.94
5
28.46
25
28.46
3
28.46
3
28.46
3
28.46
3
28.46
3
1.581
3.162
1.03
5
2.58
7
5.17
5
7.76
2
10.35
12.93
7
15.5
2
20.7
25.87
5
27.42
7
27.94
5
30.04
3
28.46
3
28.46
3
28.46
3
28.46
3
31.62
5
Cumulative Cost
1.00
2.50
5.00
7.50
10.0
0
12.50
15.00
20.0
0
25.0
0
26.50
27.00
27.50
27.50
27.50
27.50
27.50
27.50
27.50
0.25
0
0.62
5
1.25
0
1.87
5
2.50
0
3.750
5.00
0
6.25
0
6.625
6.750
6.875
6.875
6.875
6.875
6.875
6.875
6.875
0.25
0
0.62
5
1.25
0
1.87
5
2.50
0
3.125
3.750
5.00
0
6.25
0
6.625
6.750
6.875
6.875
6.875
6.875
6.875
6.875
6.875
0.40
0
1.00
0
2.00
0
3.00
0
4.00
0
5.000
6.000
8.00
0
10.0
0
10.60
0
10.80
0
11.00
0
11.00
0
11.00
0
11.00
0
11.00
0
11.00
0
11.00
0
10
0.40
0
1.00
0
2.00
0
3.00
0
4.000
5.000
6.00
0
8.00
0
10.00
0
10.60
0
10.80
0
11.00
0
11.00
0
11.00
0
11.00
0
11.00
0
11.00
0
11
Cumulative equipment
cost(20%)
0.20
0
0.50
0
1.00
0
1.50
0
2.00
0
2.500
3.000
4.00
0
5.00
0
5.300
5.400
5.500
5.500
5.500
5.500
5.500
5.500
5.500
12
0.20
0
0.50
0
1.00
0
1.50
0
2.000
2.500
3.00
0
4.00
0
5.000
5.300
5.400
5.500
5.500
5.500
5.500
5.500
5.500
13
0.15
0
0.37
5
0.75
0
1.12
5
1.50
0
1.875
2.250
3.00
0
3.75
0
3.975
4.050
4.125
4.125
4.125
4.125
4.125
4.125
4.125
14
Cumulative subcontractor
payment made
0.15
0
0.37
5
0.75
0
1.12
5
1.500
1.875
2.25
0
3.00
0
3.750
3.975
4.050
4.125
4.125
4.125
4.125
4.125
4.125
15
0.25
0
1.37
5
3.12
5
5.62
5
8.12
5
10.62
5
13.12
5
16.2
5
21.2
5
25.37
5
26.62
5
27.12
5
27.50
0
27.50
0
27.50
0
27.50
0
27.50
0
27.50
0
16
0.25
0
0.34
0
0.53
8
0.45
0
0.36
3
0.275
0.188
0.72
5
0.55
0
0.500
0.803
0.820
2.544
0.963
0.963
0.963
0.963
4.125
3.125
example
Fund
Requirement
based on
Negative Cash
flow
= area of graph
of negative cash
flow region
= average
vertical
coordinate x base
= .409 X 8 =
Rs.3.27lakhs
Hence the
contractor has
to mobilize of
Rs. 3.27 lakhs
during the
period of
negative cash