Академический Документы
Профессиональный Документы
Культура Документы
Project Time
Management
For
Time
Schedule
Defining Activities
Project
Activity Sequencing
Involves reviewing activities and determining
dependencies
Mandatory dependencies: inherent in the nature of
the work; hard logic
Discretionary dependencies: defined by the project
team; soft logic
External dependencies: involve relationships
between project and non-project activities
You must determine dependencies in order to use
critical path analysis
Project Network Diagrams
Project network diagrams are the preferred technique
for showing activity sequencing
A project network diagram is a schematic display of
Sample Activity-on-Arrow
(AOA) Network Diagram for
Project X
Arrow Diagramming
Method (ADM)
1. Find all of the activities that start at node 1. Draw their finish nodes and
draw arrows between node 1 and those finish nodes. Put the activity letter
or name and duration estimate on the associated arrow
2. Continuing drawing the network diagram, working from left to right. Look
for bursts and merges. Bursts occur when a single node is followed by two
or more activities. A merge occurs when two or more nodes precede a
single node
3. Continue drawing the project network diagram until all activities are
included on the diagram that have dependencies
4. As a rule of thumb, all arrow heads should face toward the right, and no
arrows should cross on an AOA network diagram
Precedence Diagramming
Method (PDM)
Project 98 file
10
Activity Duration
Estimating
12
13
MSProject
file
14
MS-Project file
White diamond: slipped milestone two bars: planned and actual times
15
16
17
Progress S-Curves
18
Progress S-Curves
19
Progress S-Curves
20
21
22
23
A=2
B=5
C=2
E=1
6
D=7
finish
F=2
25
If one of more activities on the critical path takes longer than planned, the whole
project schedule will slip unless corrective action is taken
Misconceptions:
The critical path is not the one with all the critical activities; it only accounts for
time
There can be more than one critical path if the lengths of two or more paths are
the same
The critical path can change as the project progresses
delayed from its early start without delaying the planned project finish
date
26
Start
Finish
Late Start
Late Finish
A
B
C
D
E
F
G
H
I
J
Mon 8/3/98
Mon 8/3/98
Mon 8/3/98
Tue 8/4/98
Wed 8/5/98
Wed 8/5/98
Thu 8/6/98
Wed 8/12/98
Fri 8/14/98
Thu 8/20/98
Mon 8/3/98
Tue 8/4/98
Wed 8/5/98
Fri 8/7/98
Tue 8/11/98
Mon 8/10/98
Thu 8/13/98
Wed 8/19/98
Mon 8/17/98
Mon 8/24/98
Wed 8/5/98
Mon 8/3/98
Wed 8/5/98
Thu 8/6/98
Wed 8/5/98
Fri 8/14/98
Mon 8/10/98
Wed 8/12/98
Tue 8/18/98
Thu 8/20/98
Wed 8/5/98
Tue 8/4/98
Fri 8/7/98
Tue 8/11/98
Tue 8/11/98
Wed 8/19/98
Mon 8/17/98
Wed 8/19/98
Wed 8/19/98
Mon 8/24/98
Free
Slack
0days
0days
0days
2d
0d
7d
0d
0d
2d
0d
Total
Slack
2days
0days
2days
2d
0d
7d
2d
0d
2d
0d
27
28
Shortening Project
Schedules
Original
schedule
Shortened
duration
Overlapped
tasks
29
30
OPTIM
MODE
PESS
10
16
20
10
20
15
18
21
25
30
32
12
21
25
28
MEAN
STD
33
activity;
Compute the standard deviations of
durations of each activity;
Determine the critical path of the
network.
Compute the mean and standard
deviation of the project
34
35
36
37
ASSIGNMENT