Академический Документы
Профессиональный Документы
Культура Документы
Construction Management
Functions
Purpose of operating a business is
to earn a profit!
Construction Management
Functions
To be successful a construction
company must:
– Estimate the cost of construction
projects accurately
– Predict the schedule of the work
– Control the progress and
expenditures during construction
– Complete projects safely and on time
Construction Management
Functions
Responsibility to construct the project:
– in accordance with the plans and
specifications
– to satisfy the customer’s cost, quality,
and time expectations
The project team is organized for the
purpose of accomplishing those
missions!
Owner Functions
G e n e r a l
C o n t r a c t o r
O t h e r
M e c h a n i c a lE le c t r i c a l C o n c r e t e S t r u c t u r a l
T r a d e s
P lu m b i n g H V A C
Construction Company
Team Functions
• Project managers (PM)
• Superintendents
• Schedulers
• Estimators
• Material expediters
Owner’s Project Team
• Size of the owner’s project team will
depend on the size and complexity of
the project – small project (A/E)
• Large highway project
– Resident engineer
– Inspectors
– Surveyors
– Quality assurance technicians
Managing Critical Activities
• Contracts are broken down into
activities for purposes of
scheduling, estimating, progress
control, and cost control. Large
projects can have several hundred
activities, or more!
• Trick is to know which activities are
critical
Critical Activities
Critical activities are those that could
impact the cost of the work by at least
one half of one percent of the bid price:
– For example, on a $1,000,000
project, any activity with a potential
for cost over-run or under-run of
$5,000 or more is by definition a
critical activity.
Pareto’s 80-20 rule
• 20% of the activities are critical
and should be managed
carefully
• The other 80% will average
out…
Project Control
• Cost control
• Cash Flow Analysis
• Schedule Control
• Material
Management
Cost Control
Possible corrective actions could include:
• Adding additional trade workers or
crews
• Adding or removing equipment
• Working overtime
• Bringing in additional subcontractors
Cost Control
Possible corrective actions could
include:
• Making the job more efficient
• Eliminating factors that cause
subcontractors to interfere with
each other
Productivity Q
Let R = Production rate T =
R
Where: T is total time, Q is the
total quantity to be installed
The total cost is determined by the
equation:
Ct = C h × T
Where Ct = total cost and Ch = cost
per hour, or
Ct = Ch × (Q/R)
Cash Flow Analysis
Cost
Time
Front Loaded Cost Curve
Cost
Time
Cash Flow
Schematic
Diagram
Profit (loss) To Date
Project Manager must calculate profit
(loss) to date on a regular, weekly basis
– Cost to date
– Re-estimated cost to complete
– Amount billed
– Contract amount (including change
orders)
– Example 3.2
Schedule Control
• Chapter 4
• Critical path - By definition, activities
on the critical path will delay the
entire project if they are delayed
• Physical progress can be compared
with the financial progress to
determine if the project is:
– on schedule or late
– over budget or under budget
Materials Management
Ensure that materials are delivered
in a timely manner to the site in the
quantity and quality required. When
materials arrive they are:
– Counted
– Inspected
– if necessary, Tested
Materials Management
Must determine the latest order date
accounting for the:
– shop drawing
• Preparation
• submission and
• approval time
– lead time required for fabrication
– shipping
Materials Management
Too many materials stored on the site
can lead to problem of:
– space allocation
– weather damage
– theft
Construction Related Design
Temporary structures such as:
– Scaffolding
– Forms
– Temporary bridges
– Shoring
– Cofferdams
– Rigging
must be designed by the contractor
Risk Management
Risks are inherent in construction
• Industry is moving toward allocating
risks to the party most able to
control the specific risk
• Managing risks means:
– minimizing risks
– insuring against risks
– and sharing risks
Risk Management
• Construction risks - inability of a
subcontractor to perform
• Economic risks - cost escalation
• Political/public risks - disapproval of
the required project permits
• Physical risks - subsurface conditions
Risk Management