Review of Progress of NHAI Works in Gujarat State

by
Chairman NHAI

Regional Office Gandhinagar


National Highways Authority of India
27.01.2016
1

Organisation Chart in Gujarat

GM(T)
Vacant
Dy.Manager(T)Avishek Shaw

PD,
Ahmedbad
S.P.Singh
Mgr(T)
K.R.Vasant

DGM(T)
Shashi
Bhushan
Dy.Manager(T)Abhishek
Choudhary

PD,
Surat(Exp.
) C.K.Sinha
DGM(T)
M.T.Attarde

Mgr
S.K.Yadav

Mgr
A.K.Swamy

Dy.Mgr
Vacant
Dy.Mgr
Vacant
Acc
Falguni
Shah
Acc:
N.K.Toppo

Dy.MgrVikas Sehra
Dy.Mgr
Vacant
Acc: Zakir
Acc:
Apoorva

Regional
Officer
R.K.Bansal

PD, Rajkot
P.K.Jain
Mgr(T)
Pinjare
Mgr(T)
Vacant
Dy.Mgr(T)
Sandeep
Patidar(ad
dn)
Dy.Mgr(T)
Vacant
Acc
Harshad
Chauhan

Manager(T)N.M.Zade

Manager(T)Shachi Jain

AO- D.K.Vyas

JAODharmaveer

PD,
Gandhidham
P.K.Singh
Mgr(T)
Ajay
P.Gadekar
Mgr(T)
V.K.Gupta
Dy.Mgr(T)
Vikas Mittal
Dy.Mgr
Vacant
Acc
Sethi

PD,Somnat
h R.K.Bhati
Mgr(T)
Arbinda
Kumar
Mgr(T)
A.M.Mankar
Dy.Mgr(T)
Sandeep
Patidar
Dy.Mgr
Vacant
Acc
Harshad
Chauhan(ad
dn)

PD,
Bharuch
Vacant
Mgr(T)
D.A.Wankh
ede
Mgr(T)
Vacant
Dy.Mgr(T)
Umesh
Garg
Dy.Mgr(T)
Vacant
Acc
Vacant
3

Length of National Highways in Gujarat


Sr.
No.

NH
No.

2
3

Length in km

Description of Road

With R&B
Department

With NHAI

Total Length

0.00

132.91

132.91

8
8A

4-laning of Gujarat Maharashtra Border-Surat-Hazira Port section


of NH-6 (Approx. 133 Km)
Ratanpur-Himmatnagar-Ahmedabad-Vadodara-Surat-Dahisar
Ahmedabad-Bamanbore-Maliya-Bhachu-G'dham-Kandla

0.00
195.735

629.00
179.40

629.00
374.135

8A Ext.

Kandla-Mundra-Mandvi-Nalia-N. Sarovar

171.00

71.40

242.40

5
6

8B
8C

Porbandar-Rajkot-Bamanbore
Chiloda-Gandhinagar-Sarkhej

32.00
46.42

185
0.00

217
46.42

8D

Jetpur-Junagadh-Somnath

0.00

127.75

127.75

8E

Bhavnagar-Mahuva-Una-Kodinar-Somnath

0.00

260.10

260.10

9
10
11

8E Ext.
14
15

Somnath-Porbandar-Dwarka
Abu Road - Palanpur Radhanpur
Samakhiyali-Radhnapur-Bhabhar-Vav-Tharad

0.00
0.00
129.40

208.85
151.62
142.00

208.85
151.62
271.40

12

59

Ahmedabad-Balasinor-Godhra-Dahod

0.00

211.20

211.20

13
14
15

113
228
NE-1

Dahod-Zalod-Rajsthan Border
Ahmedabad-Dandi
Ahmedabad-Vadodara

43.00
386.04
0.00

0.00
0.00
93.00

43.00
386.04
93.00

1003.59

2391.23

3394.82

TOTAL
16
17

18

19

19

Providing NH connectivity to Backward areas/religious/tourist places:-Preparation of DPR


Talaja(NH-8E)-Palitana-Sihor
64.00
Modasa-Lunavada-Godhra
170
Bodeli(NH-56)-Champaner-Pavagadh Archaelogical park-Godhra(NH80
47)
Abu Road(NH-27)-Mount Abu

52

Bharatmala Scheme:- State roads entrusted to NHAI for preparation of DPR in Gujarat State
Dwarka(NH-51)-Khambala-Jamnagar-Dhrol-Amran-Maliya
267.00
4
G. Total..
2972.23

64.00
170
80
52
267.00

NHDP
Status

NHDP Status
Sr.
No.

Phase

Total Length

Completed
Length

Balance

Remark

Phase-I

602

602

GQ (NH-8)

Phase-II

637.5

637.5

E-W Corridor

Phase-III

531

497

35

NH-6, NH-59, Kandla-Mundra, NH-8D

Phase-IV

470

470

Phase-V

549.5

Phase-VI

Phase-VII

Port Connect.

537.20

12.30

(Out of total 473.00


Km in Guj. State)

261.10

260

260

261.10

56.16

56.16

Bhavnagar-Somnath (260 Km.)


Gadu- Dwarka Km(210.)

Project Awarded : 6-laning of A-V NH-8 and NE-1,


Construction of 4-lane Narmada
Bridge include Completed Length of
Vadodara Bharuch Surat Section of
NH-8
Surat Dahisar Sect. of NH-8
Six laning of Samakhiyali
Gandhidham
VME - LA in Progress, DPR under
Process

Ahmedabad Ring Road 175 Kms

Surat Ring Road - 85 Kms


Port Connect. (4-Lane)
(Samakhiyali Gandhidham
Project)
6

BOT Projects
under
construction

Total
Project
S. Contract Stretch Length
Cost
No (State)/NH No.
(Km.)
(Rs. in
Crores)

Kandla - Mundra
Port (NH 8A Ext.)

Six laning of
SamakhiyaliGandhidham
Section from Km
306.000 to Km
362.160(NH 8A)
AhmedabadVadodara (NH8)
section & NE-1
(AVEXP)

71.4

56.16

Date of
commencemen
t / Cumulative
physical
progress

Name of
Concessionaire/
Independent
Engineer

Stipulated
Anticipated
Completion

19.01.2011

M/s. KM Tollway
Private Ltd.

16.07.2013

82.09%

M/s K&J

11.09.2010

M/s L&T

954.00

805
99 %

102.30

M/s K&J

PCC issued
on
04.11.2015
11.03.2013
30.12.2015

01.01.2013

M/s. IRB AVSE Pvt.


Ltd.

31.12.2015

95.36%

Aarvee Associates
Architects, Engineers
& Consultants
Pvt Ltd
8

31.12.2015.
PCC issued
on
06.12.2015

2125.2

Total
Project
S. Contract Stretch Length
Cost
No (State)/NH No.
(Km.)
(Rs. in
Crores)

Six laning SuratDahisar Section of


NH-8

Gujarat /
Maharashtra
Border-SuratHazira Port section
(NH-6)

239

133

Date of
commencemen
t / Cumulative
physical
progress

Name of
Concessionaire/
Independent
Engineer

Stipulated
Anticipate
d
Completio
n

20.02.2009

M/s IRB Surat Dahisar


Tollway Pvt. Ltd.

15.02.2012

99.7%

M/s CEG

PCC issued
on
06.04.2013

30.03.10

M/s. Soma - Isolux


Surat - Hazira Tollway
Pvt. Ltd.

25.09.2012

1693.75

1509.00
87.09%

31.03.2012
6

JetpurSomnath(NH8D)

123.5

Sheladia Associates
Inc
M/s. IDFC and PLUS
Expressway Ltd.

27.09.2014

MSV Consultants

PCC issued
on
04.08.2015

828.00
82.7%

PCC issued
on
19.08.2015

EPC Projects
under
construction

10

S.
No.

Contract
Stretch
(State)

Construction of
a new four lane
Narmada bridge
(Extra dosed
bridge) across
river Narmada
in the State of
Gujarat on
EPC(NH8)

Length
(km.)

Date of
Total
Name of
commenceme
Project Cost
Concessionai
nt /Cumulative
(Rs. in
re/ Authority
Physical
Crores)
Engineer
Progress
03.03.2014

6.745

407.00

58.00%

Contractor
M/s. L&T
Ltd Mumbai
M/s. Aarvee
Associates
Engineers

11

Stipulated
Completion

29.08.2016

Brief Of
Construction
Of New
Narmada
Bridge

12

Proposed New four lane Extra Dose Bridge across river


Narmada from Ch. 192.000 to 198.000

Flyover at
Zadeshwar Junction
(192.360) with
service road on both
side

Proposed Toll Plaza


Location at km
196.000

Vadodar
a
Flyover at
Zagadia
Junction
(198.100) with
service road on
both side

13

Surat

Conceptual view of Narmada Bridge


Extra Dosed Y-Shape Pylon

14

Details of new Narmada Bridge(km 192.000 to km 198.000)


Sr.
No.

Description

Name of Project

Name of EPC Contractor

Name of Authority Engineer

Name of Proof Consultant

Name of Safety Consultant

6
7
8
9
10
11

Date of Issuance of letter of


Acceptance
Date of Signing of Agreement
Appointed Date
Construction Period
Maintenance Period
Actual or Schedule Date of Completion
of Construction work/ Expected
Completion Date

Details
Six Laning of Km. 192.00 to Km. 198.00 between
Vadodara Surat section of NH-8 including
construction of a new four lane Extra Dose Bridge
across river Narmada in the state of Gujarat on
EPC contract mode.
M/s Larsen & Toubro Limited, Mumbai
M/s Aarvee Associates Architects Engineers &
Consultants Pvt. Ltd. in JV with M/s Nag
Infrastructure Consulting Engineers Pvt. Ltd.
M/s Roughan & ODonovan (ROD), Ireland
(engaged by EPC Contractor with consent of NHAI)
M/s Craphts Consultants (engaged by EPC
Contractor with consent of NHAI)
07 Feb. 2014
25 Feb. 2014
03 Mar. 2014
30months(910 days) w.e.f. appointed date
5 years (after completion)
29 Aug. 2016
15

Details of new Narmada Bridge(km 192.000 to km 198.000)


Sr.
No.

Description

Details

The total length of project

6.610 Kms (Bridge-1.34 Km, Approach-5.27 Km)


1 no. (New four lane extra dosed bridge 1.34 Km,
Span Arrangement- 1X96m + 8X144m + 1X96m )
2 nos. (Reconstruction)

Major Bridges

Culverts

Inter changes/Flyovers

Service Roads

Toll Plaza

2 nos.(at Zadeshwar and Zagadia)


(Span Arrangement- 2X25m + 1X40m)
3.195 Km(LHS + RHS)
1 no. at km. 195.800

16

Repair of
rehabilitated
old Narmada
Bridge

17

Rehabilitation work
Description of Old Sardar Bridge
a) Year of Construction
b) Name of River
c) Constructed by
d) Location
e) Span Arrangement & Total Length
f) Type of bridge
g) Type of foundation
h) Type of Bearings
i) Carriageway Width
j) Bridge Approach length
Recent Problems / Deterioration observed in
rehabilitated old bridge since April 2014
a) Differential deflection at all joints
b) Spalling out / damage of concrete at bearing
location
c) Cracks in concrete at bearing locations

Details
1977
Narmada River
M/s GAMMON INDIA
on NH-8 near Zadeshwar at Bharuch under Km.
192.000 Km. 198.000.
13 spans x 96.16m + 2 spans x 48.08m (Total
Length-1346.24 m)
PSC Box Girder balanced Cantilever Bridge with
expansion joints
Well Foundation
Central Hinge Type Bearings
2-lane bridge
3.4 Km. long 2-lane approach on Mumbai side
and 1.2 Km. 2-lane approach on Ahmedabad side
Details
in the range of 40-50 mm with knocking sound at
some bearings
At 5 locations u/s side (LHS) (bearing no. 3-4 , 67, 8-9, 11-12 & 13-14) and at 3 locations d/s side
(RHS) (bearing no. 2-3, 8-9 & 11-12)
At 3 locations u/s side (LHS) (bearing no. 2-3, 78 & 4-5) and at 3 locations d/s side (RHS)
18
(bearing no.
3-4, 7-8 & 4-5)

Constitution of Expert Committee, Site visit & their suggestions


Details
Constituted in June 2014 comprising 3 Members
a) Constitution of Expert
(i) Sh. Ninan Koshi, Retd DG (RD) & A.S., MoRTH,
Committee by NHAI
(ii) Sh. Mahesh Tandon, M/s Tandon Consultant Pvt. Ltd.
(iii) Dr. A.K. Nagpal, Professor Civil Engineering, IIT Delhi.
24-25th June 2014 @ Narmada Bridge,
26-27th August 2014 @ Mahatma Gandhi Setu Bridge, Patna
b) Site Visits of Expert Committee
29th August 2014@ Narmada Bridge, 3rd Feb. 2015 @ Narmada
Bridge & 19th Sept 2015 @ Narmada Bridge
c) Suggestions of Expert Committee
(1) Treatment with pressure grouting works /FRP at locations 2-3(u/s
& d/s) & 3-4(d/s)
(2) Repairs using epoxy grout at locations 6-7(u/s), 11-12 (u/s & d/s)
(i) Damages/ Cracks in concrete at
(3) Repairs using carbon FRP laminates/wrapping at 7-8 (u/s & d/s) &
bearing locations
4-5 (u/s & d/s)
(4) Treatment using Epoxy/Cementious grout at bearing no. 2-3 (d/s),
3-4 (u/s), 8-9 (u/s & d/s) & 13-14 (u/s)
Similar treatment by inserting of Shim plates in all CHB joints (26
(ii) Deflection Control
locations) as adopted at Mahatma Gandhi Sethu, Patna
(iii) Scanning of reinforcement in Being specialized work as per requirement of CoE, a vendor has been
original structure
contacted.
2 Agencies have been
shortlisted and 3 rounds of Expert committee has suggested to get
presentation have been held a trial application of FRP laminate at
iv) RFP invited for
in front of Expert Committee U/S & D/S of CHB P4-P5 using Carbon
repair/rehabilitation works in the
for finalization of
FRP laminates through M/s R&M to
long term.
rationalized BOQ and once
review the
performance of FRP work
19
finalized, further course of
before the finalization of rationalized

Immediate & Urgent


actions taken

Details

Remarks

Traffic restriction continued as per


recommendation of CoE.The
a) Traffic allowed in single
Since January 2015
condition survey of CHBs and
lane for Cars , LCV, Buses
deflection measurement are
monitored on regular basis.
Approval for repair/ maintenance
b) M/s L&T have been
Repairing done for spalled/ cracked
work using carbon FRP
advised to carryout the
concrete at CHB locations, shim
laminates/wrapping at CHB P4-P5
urgent remedial works and plates placed at 26 CHBs (i.e. 13
and for repair/ maintenance work
tests as per Expert
Expansion Joints), test carried out as
using Epoxy grout at CHB P2-P3
Committee suggestion
per suggestion of CoE
(D/s) obtained.
c) Provision of dedicated
cranes & tractor with
Work awarded to M/s Hastee
In service w.e.f. 25.07.2014
pulling arrangment for
Conctruction
Incident Management
d) Provision of installation
WIM installed but not commissioned
Agreement signed with M/s Rajdeep
of weigh in motion before
as no heavy traffic is allowed to
info techno pvt. Ltd. on 01.09.2014
old Narmada bridge
cross through the bridge.
e) Provision of Video
Agreement signed with M/s
Video camera installed and in
Camera with AVCC for
Techsture technologies on
operation.
traffic survilliance
11.08.2014
f) Provision of 2 Nos. of
Agreement signed with M/s . S. S.
Work completed and high mast
High mast tower for
Electricals on 09.02.2015
commissioned.
illumination in night
20

Photographs of existing old Narmada Bridge(Zadeshwar)

Existing Bridge

Superstructure projecting from Pier -Heads

Finger type Expansion Joint

Hinge Bearing

21

Rectification done to Severe Damaged section at CHB P8-P9 and P11-P12

22

Severe Dame at CHB P7-P8 proposed to be repaired by FRP laminates as per


recommendation of CoE

23

24

Value
Addition
Projects

25

Value Addition Projects At a Glance


Value addition between Vadodara to Bharuch (Km. 108.700 to Km. 192.000) and Bharuch to Surat
(Km. 198.000 to km 263.000) Sections

Rehabilitation / upgradation of Existing 2 lane Major bridges (11 Nos.)

VUP / PUP / Flyover & extension of service roads.

Widening of existing 4 lane carriageway into Six lane between Km. 248.000 to Km. 263.000

Value Addition Proposal


Sr.
No.

Description

Fly over

VUP

PUP

Total
Cost
(Rs. In
Crores)

Vadodra to Bharuch
(Km. 108 to Km.
192)

267.68

Included in VME

369.88

To be included in
Kadodara-Chaltan EPC
Document which has
been tendered. Due
Date of Submission: 04
Aug2015

Bharuch to Surat
(Km. 198 to Km.
263)

Jetpur-Gondal

10

26

Remarks

It also include one FOB,


curve improvement,
service road widening.

Brief Of
Proposed
Vadodara
Mumbai
Expressway

27

NE-1

End of V-M Expressway


Ch. 378+722

Vadodara-Mumbai Expressway
including SPUR to JNPT
Phase I : Km 104.700 to Km
378.722 (Main Exp.)
Phase II : Km 26.32 to
Km 104.700 (Main Exp.) &
SPUR to JNPT (Km 0.000 to
Km 94.390)
Phase III : Km 0.00 to
Km 26.32
NH-8

Start of SPUR
Start of V-M Expressway
Ch. 0+000

Proposed NaviMumbai Airport


End of SPUR
Ch. 94+390
JNPT

Proposed 8 Lane Cross Section

29

Project Packaging for Execution


In the meeting held on 02-02-2015 under the Chairmanship of Advisor to Honble Minister, MoRT&H, it was
discussed that, the Project has to be spilt into different packages to make the project viable for implementation.
Phases

Stretches

Length(Km)

Administrative area

Phase I A

Main Expressway-Kim (Km 254.43) to Vadodara


(Km 378.722)

124.292

Phase I B

Main Expressway-Talasari (Km 104+700) to Kim


(Km 254.43)

149.730

Phase II A

Main Expressway-Shirsad (Km 26.320) to Talasari


(104.700)
Connectivity to NH 8 along SPUR-Shirsad (Km 0.0Km 1.86)

80.24

Maharashtra

Phase II B

SPUR to JNPT-Shirsad (Km 1.86) to JNPT


(Km94.390)

92.53

Maharashtra

Phase III

Main Expressway-Ghodbunder (Km 0.0) to Shirsad


(Km 26.32)

26.32

Maharashtra

Gujarat
Gujarat, DNH(5.5 km),
Maharashtra(8.15Km)

30

Vadodara Mumbai Expressway (473 km)


Length of main alignment : 378.68 km
Length in Gujarat

260.40km

Length in Maharashtra

112.83km

Length in Dadra & Nagar Haveli


Total Length of main alignment

5.45km
378.68 km

Length of spur alignment : 94.32 km


Length of spur in Maharashtra

94.32 km

Total Length = 378.68 km + 94.32 km = 473.00 km

31

Project Phasing & Cost of Construction


Civil Cost (in Crores)
Sl.
No.

Phases

Length
in Km

Phase 1A

124.292

5,040.22

3,024.13

Civil
Cost

Cost per
Km

Others (in Crores)


Others
LA Cost
including
Sub Total
including R&R
Env, Utility

Total (in Crores)


Cost
Total
Per
Km

Add 12%IDC & 8%


Inflation-3 Years
Sub Total for
Phase 1A
Phase 1B
Add 12%IDC & 8%
Inflation-3 Years
Sub Total for
Phase 1B

8,064.35

64.88

3,959.02

367.78

4,326.80

12,391.15

99.69

149.730

6,071.77

3,643.06

9,714.83

64.88

4,769.28

443.06

5,212.34

14,927.17

99.69

Phase 2A

78.380

74.12

1,209.10

297.27

1,506.36

7,315.91

93.34

1,814.06

9,799.20

103.82

Add 12%IDC & 8%


Inflation-3 Years
Sub Total for
Phase 2A
Phase 2B (Incudes
Tunnel & Elevated)
Add 12%IDC & 8%
Inflation-3 Years
Sub Total for

3,630.96
2,178.58
5,809.54

94.390

4,990.71

2,994.43

7,985.14

84.60

1,456.07

357.98

32

Civil Cost (in Crores)


Sl.
No.

Phases

Length
in Km

Phase 3*
26.320
Add 12%IDC & 8%

Inflation-3 Years
SubTotal for Phase 3
Total for VME

Others (in Crores)


Total (in Crores)
Others
Cost
LA Cost
including
Sub Total
Total
Per
including R&R
Env, Utility
Km
2,665.17

Civil
Cost

Cost per
Km

1,856.20

70.52

1,113.72

2,969.92

112.84

2,823.17

473.112 34,543.78

14,216.64

116.37
1,582.46

2,939.54

5,909.46

15,799.1 50,342.88
0

* Phase 3 Under consideration for deletion


Construction Period - 4 Years

33

224.52

Vadodara Mumbai Expressway (Phase-1 in Gujarat state)-260km(Total area 3021 Ha.)


Sr.No.

District

Total
3A stauts
Villages

3C status

3D status

Draft
3G Hearing award
Remarks
pending submitte
d
6(Dodka,
5
Notices for panchnama for valuation of
Sokhda
trees etc. to be issued/distributed by CALA
Khurd,
through Sarpanch & Talati. The expert
Ghayaj,
Horticulture officer has completed work for
Sadad,
Vadodara and Horticulutre expert is likely to
Handod,
submit report by 20.12.2015.
Sanpa)
Nil
10
Notices for panchnama issued and to be
distributed through sarpanch and talati for
valuation of trees etc. Structure evaluatio is
on and it will be completed by 15.12.2015
The expert Horticulture officer will be
completing the work for Bharuch in a couple
of days and Horticulutre expert is likely to
submit report by 20.12.2015.
20 (3D
Nil
Notices for panchnama for valuation of
under
trees etc. to be issued/distributed by CALA
publication)
through Sarpanch & Talati

Vadodara (Area 29
654.1922 Ha.;
Length:
54.448km)

Completed Completed

Completed

Bharuch(Area:7 32
12.067 Ha.:
Length:62.5km
)

Completed Completed

Completed

Surat(Area:639 37
.681 Ha.;
Length:57.287
km)

Completed Completed

Navsari(Area:4 22
54.7747 Ha.;
Length:
37.55km)

Valsad(Area:56 28
0.266Ha.length
: 48.625km)

Completed (i) 8 villages completed


(ii) Balance for 14
villagesKanbad, Kambada,
Matvad, Gandeva,Baroliya,
Sunthwad, Degam, Alipor,
Khundh, Sadakpor,
Talavchora, Maliyadhara,
Ghej, Char
Completed Balance for all 28 villages

(i)17 Completed
(ii)20 partially
completed(Kuvarda,
Tarsadi, Siyalaj, Moti
Naroli, Valesa, Chhamusar,
Karanj, Virpor, Karjan,
Ghala, Dhatava, Digas, Jat
Bharhana, Segava, Pali,
Haldaru, Kareli, Ena, Puni,
NAugama (under
publication)
(i)Completed for 8 villages (i)
2 out of 8 (i) Notices for 8 villages for panchnama for
(ii) Yet to be published for Completed villages
valuation of trees etc. to be
14 villages
for 8
issued/distributed by CALA through
villages
Sarpanch & Talati.
(ii) NA for 14
(ii) 3C hearing pending for 14 villages.
villages
(iii) JMS pending for 14 villages
Yet to be published
General Issues

NA

Nil

(i) 3(c) hearing is pending for all the 28


villages.
34 (ii)JMS pending for all 28 villages

Vadodara Mumbai Expressway Alignment Plan

35

NHDP Phase
VII

36

NHDP Phase VII


Sl.
No.

Name of the stretch

NH
No.

Approx.
Length
(km.)

TPC
(Approx)
In Cr.

Ring
Road
around
Ahmedabad City

Ring
Road

175

1500

Ring
Road
Surat City

Ring
Road

85

750

260

2250

around
Total

Status

Feasibility consultant to be
appointed by NHAI Head
Quarters
Feasibility consultant will be
appointed by NHAI HQ.

State Govt. Consent yet to be received for Ahmedabad outer Ring Road
Consultancy Services for feasibility study and alignment is being finalized for Surat city. Major
portion is within jurisdiction of NHAI & R&B GOG (SH). 4/6 laning of NHAI portion is in progress. The
alignment is in the final stage of approval is likely to be received within a short period. Remaining
27 Km. work is to be taken up by SUDA /SMC.
Various alternatives to take up the project either by SUDA/SMC/NHAI were discussed. It is was
decided to examine in detail the option of handing over the whole project to NHAI for execution
and maintenance either on BOT, PPP, or such other module during Meeting held on 31.01.2012

37

Projects in
Pipeline

38

Projects in pipeline
Sr.
No.

Name of the stretch

Length
(km.)

Status

Six / Four / Two lane with


paved shoulder of
Bhavnagar Pipavav
Veraval Section (NH-8E)

256.6

Status of Bhavnagar Veraval : 3D notification


complete. 3G award approved by NHAI for 36
villages.
Forest Proposal at Regional Office Bhopal
Divided into six sections: Bhavanagar-Talaja
section tendered.

Six / Four / Two lane with


paved shoulder of Gadu Porbandar Dwarka
Section NH-8E (Extn.)

210.00

Status of Gadu Dwarka : JMS complete and 97% 3D


has been notified, Tender documents under
preparation, Forest proposals at APCCF level

Vadodara Mumbai New


Expressway Phase-I

274.00

Construction of 4 lane
bridge across Varsova

Vaodara- 5 draft awards submitted. 3G hearing of


6
villages
pending;
Bharuch-3G
hearing
completed. 10 draft awards submitted. Surat-Main
3D complete. Additional 3D in 20 villages pending.
3G hearing in 17 villages complete; Navsari- 3C to
be conducted for 14 villages.; Valsad-3C hearing
balance for all 28 villages
Tender issued

39

New Additional Works in Planning


1

4 to 6 laning of Kamrej to
Kadodara Section of NH-8

Long term Improvement of


Black Spots coming under
Jetpur-Gondal stretch

14.00

3.7km

Tender issued
It includes one Flyover,3 PUPs, 1 FOB, curve
improvement and service road widening in around 6km .
EPC proposal has been submitted to NHAI-HQ and is
under process.
Bharatmala Scheme:- State roads entrusted to NHAI for
preparation of DPR in Gujarat State.

Dwarka(NH-51)-Khambala267.00
Jamnagar-Dhrol-AmranMaliya
Talaja(NH-8E)-Palitana64;170;
Sihor section;
80 and
Modasa-Lunavada-Godhra
30
Providing
NH
connectivity
to
Backward
section;
areas/religious/tourist places:-Preparation of DPR
Bodeli(NH-56)-ChampanerPavagadh -Archaelogical
park-Godhra(NH-47);Abu
Road-Mount Abu
Sub-Total

628.70

Grand Total

1369.3
40

Issues with
the State
Government

41

(A) Transfer of Govt. Land


Govt. of Gujarat is insisting for compensation for state owned Govt. land from NHAI at market rate.
No

charges are levied in other States for transfer of state-owned Govt. land. It is therefore

requested to review the policy to transfer the land to NHAI free-of-cost.

(B) Slow disbursement of compensation


Even after deposition of the compensation amount in the joint account for disbursement, there is
delay in disbursement of payment to the land losers by CALAs in case of number of projects.
This has hampered progress of the projects as 80% of encumbrance - free land is required to be
handed over to the BOT Concessionaire at appointed dated.

(C) Miscellaneous Issues (General)


Mutation of acquired land in the name of NHAI by the state government.
The Govt. of Gujarat may depute more number of skilled technical staff to NHAI for speedy
implementation of NHAI projects in the State of Gujarat.
Forced Possession- Delay due to hindrances by Individuals after 3G notification.
Slow progress of JMS by designated Land Acquisition authorities after publication of Land
Acquisition notification.
42

(D) Suggestions
Fortnightly review meetings by District Collectors with CALAs and concerned NHAI official be
taken
Monthly review meeting at Chief Secretary level at Gandhinagar with Secretaries of Revenue,
PWD and other utility departments apart from concerned district collectors and senior officers of
NHAI.

Targets for
FY 15-16

44

Target Achievement for Projects under Gujarat State


Description

Length (km)

Total length of ongoing Projects under ROGandhinagar

935.22

Target length for FY 2014-15

89.68

Achieved completed length in FY 2014-15

90.56

Target length for FY 2015-16

45.00

Target Length up to Dec 2015

34.80

Target length completed upto Dec 2015

50.16

Remarks

Achieved more than


target.

Ahead of Target.

45

National Highways Authority of India


NOVEMBER-2015

Regional Office, Gujarat (Gandhinagar)


State-Gujarat

Sl.
No.
1
1

2
3

6
7

10
11

Project

2
Six Laning of
Ahmedabad to
Vadodara Section
of NH 8
Ahmedabad Godhra Sect. of
NH-59
Godhra to Guj/MP
Border Section of
NH-59
Jetpur-Somnath
Section of NH-8D
Four laning of
Guj./Mah. Border
Surat Hazira
Port Section of
NH-6
Six laning of
Surat-Dahisar
Section of NH-8
SamakhiyaliGandhidham
Gandhidham
(Kandla) - Mundra
Port Road (Siracha
Junction)
Six Laning of Km.
192.00 to Km.
198.00 between
Vadodara Surat
section of NH-8
including
Narmada Bridge
Bhavanagr to
Veraval section of
NH8E
Gadu to Dwarka
section of NH-8E

NHDP
Phase /
Others

Total
Length

Total
completed
UI
April'15
length length Target
upto
(in km)
March, 15
Achi.
(in km)
4
5
6

102.30

64.62

37.68

III

117.57

117.11

0.46

III

87.102

83.155

3.95

III

123.45

99.00

24.45

III

131.50

127.55

.70km

239.00

238.20

0.00

56.16

53.22

2.94

III

71.40

51.5

19.90

6.74

0.00

6.74

IV

256.24

0.00

256.24

IV

210.00

G. Total... 1401.46

0.00

210.00

834.36

562.3
6

May'15
Target
Achi.

Targets length (in kms.) for the year 2015-16


June'15 July'15 Aug'15 Sept'15 Oct'15
Target Target Target Target Target
Achi.

Achi.

Achi.

Achi.

Achi.

Nov'15
Target
Achi.

Upto
Curren
t
Month

Reason for delay in achivement

Target
2015-16

10

11

12

13

14

15

20

21

3.00

4.00

4.00

0.00

0.00

0.00

1.50

1.50

12.50

23.00

1.40

6.25

8.10

5.22

1.91

1.30

4.45

3.75

32.38

32.38

0.00

0.21

0.25

0.00

0.00

0.00

0.00

0.00

0.46

0.46

0.00

0.21

0.10

0.00

0.00

0.00

0.00

0.00

0.31

0.31

1.00

1.00

1.00

0.95

0.00

0.00

0.00

0.00

3.95

3.95

1.02

1.00

0.43

0.00

0.00

0.87

0.00

0.00

3.32

3.32

1.00

1.45

0.00

0.00

0.00

0.00

0.00

0.00

2.45

2.45

0.00

0.39

0.00

0.00

0.00

0.00

0.00

0.00

0.39

0.39

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.70

0.60

0.50

0.00

0.00

0.00

0.00

1.25

0.00

2.35

2.35

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.30

0.13

0.00

0.00

0.00

0.00

0.00

0.43

0.43

0.00
0.00
1.50

0.80
0.00
1.50

0.40
0.00
1.50

0.00
0.00
0.00

0.00
0.78
0.00

0.60
1.00
0.00

0.60
0.00
1.00

0.54
0.00
1.00

2.94
1.78
6.50

2.94
1.78
9.00

3.50

1.50

2.50

0.50

0.50

0.70

0.00

0.00

9.20

9.20

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

2.50

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

0.00

6.50
6.52

8.96
10.15

7.15
11.26

0.95
5.72

0.00
3.19

0.60
3.87

3.10
5.70

3.04
3.75

30.30
50.16

45.00
50.16

46

22

Junagadh Bypass(19.8km), LA
process for 3G restarted &
concessionaire will mobilize for
work. Achievement in last two
months will depend on availability of
land. Resistance of public in Supasi.
Due to non-availability of forest
clearanace and non-finalisation of
dispute on CoS for ROB
Due to Sanjay Gandhi National Park
Toll Plaza Building under
construction
Galpadar/Khedoi Villages and
Construction of ROB.

Work to be awarded

Targets will be fixed only after


completion of tendering process and
award of contract

State Support
Agreement
Issues
Gujarat

47

Chronology of State Support Agreement


National Highways Authority of India established under NHAI Act 1988 having principal office at New Delhi
was entrusted to develop National Highways all over India under NHDP Scheme of Government of India.
Accordingly, during Vibrant Gujarat Global Investors Summit 2009, a MOU was signed by Government of
Gujarat for development of National Highway in the State of Gujarat (copy enclosed at Appendix-A).
Subsequently Government of Gujarat, Revenue Department vide resolution dtd- 19.02.2010 formed a High
Level Committee constituting, Principal Secretary (Revenue) as chairman with Chief General Manager & ROGujarat NHAI as Member (Copy enclosed as Appendix-B) along with other Member.
Again a MOU was signed by Government of Gujarat and NHAI during Vibrant Gujarat summit in 2011 for
additional projects (Copy enclosed as per Appendix-C). As per MOU signed by Government of Gujarat, it was
agreed that the GoG would facilitate pre construction activities like LAQ, Utility Shifting, Forest clearance and also
sign the State Support Agreement during concession period of each project for development of National
Highways in the State of Gujarat.
MoRT&H has circulated an umbrella SSA to be signed by each State, but, Government of Gujarat has some
reservations in certain clauses and did not sign the Umbrella State Support Agreement. The issue was addressed
during the CCI meeting on 30.03.2015,wherein Chief Secretary, Government of Gujarat consented to sign the
project specific State Support Agreement on the lines of already signed State Support Agreement by the State of
Uttar Pradesh. Further during CCI review meeting on 27.07.2015, the issue was again discussed under the
Chairmanship of present Chief Secretary and the current status was appraised.

Project specific SSA has now been approved by MoRT&H. Accordingly it has been submitted to Secretary,
R&B Department, Govt. of Gujarat vide this office letter no.F-56,dtd-30.07.2015 (Copy enclosed appendix D)
for further necessary action.
Govt. of Gujarat consented to sign SSA. Pending at MoRTH for approval

BOT
Projects
under
O&M

52

BOT Projects under O&M


Total
Total Project
Name of
Date of
Concessio
Length Cost Concessionai Commenc n period
(km)
(Rs.
re
ement
(years)
crore)

S.
No

Section

1.

Vadodara to Bharuch
Section BOT- (Pkg-I) (Six
lane)
NH 8

83.30

660.00

M/s. L&T Vadodara


Bharuch Tollway Ltd.

2.

Bharuch to Surat Section


BOT- Pkg-II (Six lane)
NH8

65.00

492.00

M/s. IDAA
Infrastructure Pvt.
Ltd.

Widening of the Existing


Jetpur - Gondal Section
(Km. 117/00 to 143/00)
from Two lane Gondal
Rajkot Section (Km.
143/00 to Km. 175/00) and
widening (Km, 175/00 to
185/00) from two lane to
four lane on NH-8B in
Gujarat, India on BOT
Basis

68.00

288.36

M/s. West Gujarat


Expressway Pvt. Ltd

08.01.2007

03.01.2007

22.09.2005

53

Funding

15

BOT
Negative grant of
Rs. 497 Cr.

15

BOT
Negative grant of
Rs .502 Cr.

20

During first 5 years


after completion NHAI
was suppose to provide
assistance in terms of
grant amounting to Rs.
40 Cr. (Period
Completed) after
vacation period of one
year (6th year) the
Concessionaire is
suppose to pay Rs. 280
Cr. During 7th Year to
15th Year after
completion. Net Rs. 240
Cr. is receivable to NHAI
and at the end of 15
years after completion

BOT Projects under O&M


Total
Total
Concessi
Project Name of
Date of
Lengt
on
Cost
Concessio Commen
h
period(y
(Rs.
naire
cement
(km)
ears)
crore)

S.
No

Section

Palanpur to
Swaroopganj (42 km.
in Raj & 34 km. in
Guj) NH14

Four laning of
Ahmedabad Godhra
section
(Package-I)(NH59)

117.60

1155.40

Four laning of
Godhra to
Gujarat/MP Bordersection (Package-II)

87.29

750.00

34.00

498.00

M/s. . L&T
Interstate Road
Corridor Ltd.

17.5

Annuity basis Completion


date. 24.03.2024
(Rs. 43.21 Cr.- 6 Monthly
basis)

30

108 Cr Grant

27

7.83 Cr Premium per year


with annual increase of 5
%

Sep 2006

M/s. Essel Infra.


Project Ltd and
China Railway
Corp. Ltd.

27.12.10

M/s. BSCPL Infra.


Pvt. Ltd.

01.03.2011

Funding

54

Black Spots

55

Summary of Black spot coming under NHAI


Total
nos.

Temporary
Measures
Completed

Permanentl Measures
Completed

Under
Progress

Remarks

EPC/
Tender

PIU-Gandhidham
1

PIU-Ahmedabad
4

2(Vasad
flyover and
Hariyala
Bypass)

2*

* Both the bypass fall under proposed


six laning of Ahmedabad-Kishangadh
section, which has been terminated.
Matter is subjudice.

PIU-Rajkot
5

3+
1(droppe
d)

For the 3 black spot, EPC proposal


submitted to NHAI HQ for approval &
tendering. The Balance one black
spot is under the feasibility study
by M/s. Aarvee, which has been
dropped due to non-viability and
separate proposal under
preparation

PIU-Surat (Exp.)
10

10

Tender has been called for the balance 6

Black Spots
Sr.
NH
No
No.
.

Long term remedial Measures (Nos.) Remarks


Nature of
Nature of
Likely
Likely
Location of
Nature of Short Term
Long Term
Action taken
date of
date of
Black Spots
Remedial Measures
Remedial
for Long Term
completio
completio
required and taken
Measures
Remedial
n
n
required
Measures
PIU-Ahmedabad
Village Jethipura Junc. Of Road markings, painting Completed
Flyover proposed in 6
Sep 2018 GMR
Board
6L with
Laning of Ahmedabadterminat
Km.502.500
2L road
Ratanpur section of NH-8
ed.
Matter
Shamlaji Town
Curve
Rumble Strips, road Completed
subjudic
Road
Road
marking paint
e.
Km.398.000
Brief
Descripti
on of
Problem
at Site

Short Term Remedial Measuress

Near Hariyala
Y Point &
Byepass - Y
Road Markings ,Sign
Improvement
Overtakin
Completed
Junction- NH-8
Boards, Rumble Strips
of Junction
g
(km. 33.500)

Village Vasad
Road Markings and Sign
Junction
4 8A Cross Road -NHBoards have been
Completed
with SH
8 (Ch. 90.740)
provided.

Completed

Flyover

Flyover Completed

PIU Gandhidham
Chandisar Bus
Over
Zebra Crossing on NH &
Stop NH-27 Km Speeding
Construction
5 14
Speed breakers on cross Completed
581.000,
& Cross
of VUP
roads
Banaskantha
Road

Completed
57

Sr. NH
No. No.

27

27

27

27

10 8D

11 8D

Short Term Remedial Measuress


Long term remedial Measures (Nos.)
Brief
Likely
Nature of Long Nature of Action Likely
Location of Description Nature of Short Term
Remar
date
Term Remedial taken for Long
date of
Black Spots of Problem Remedial Measures
ks
completio
Measures
Term Remedial completi
at Site
required and taken
n
required
Measures
on
PIU Rajkot
Shapar
Both Side
Viaduct flyover with tentative
Safety Boards, Road Complete
Veraval
Resi. Area &
cost of Rs.30.00 Crore has been
Marking & Delinators
d
at 165/500
GIDC
proposed
EPC
Ribbon
PUP with tentative cost of
12
propos
Pardi Board
Road markings and Complete
Developmen
Rs.10.00 Crores has been
months
al
at 168/500
speed limit boards
d
t
proposed.
after sentto
Pardi Board
Curve &
approval MoRTH
PUP with tentative cost of

Nr. Shitla
Both Side Safety Boards, Road Complete
Rs.10.00 Crores has been
Temple
Resi.
Marking & Delinators
d
proposed
km167/400 Industries
A bypass for Morbi was proposed by DPR
Maliya
cross road Safety Boards, Road
consultant however since the project was dropped
Halvad Cross
without
Marking, Cat eyes, Complete
and standalone proposal for flyover at the
Road
speed
Ambulance, crane and
d
blackspot location is under preparation.
237/460
breaker
patrol vehicle

Village Gadu
to
Long Bridge
Safety Boards &
Complete
Curve improvement along with Four laning of
Shantipura
& Curve
Delinators
d
Jetpur Somnath Section completed.
(km. 95.180Road
99+100)
Village Vadal Junc. Of 3SH
Spot not identified on existing Jungadh Bypass.
board
with NH
58

Short Term Remedial Measuress


Brief
Location
Sr. NH
Description of Nature of Short Term
of Black
No. No.
Problem at
Remedial Measures
Spots
Site
required and taken

12
13

Likely date
of
completion

PIU-Surat Expressway
Budhel
Narrow
A bypass to budhel and talaja villages has been proposed
village
road
under the proposed 4 laning of the stretch for which
Presently stretch with
feasibility study and Land Acquistion is under progress. The
R&B Department
Talaja village Sharp curve
work is likely to be awarded in FY 2016-2017

From L&T
Sardar
booth till
bridge South
the
Repair & Rehabilitation
14 8
side
crossing of of Old Narmada Bridge Completed
Ankleshwar bridge only
city
1 or 2 lanes
existing
Delineators, Bollards
Both Side
Near Village
Pedestrian marking,
Resi. Area
Kim Cross
Median opening sign
Near
15 8
Road
board, U Turn Sign
Completed
Highway
Pipodara
board, Keep Left sign
Due to
Km.239+100
board, Accident Prone
Cross Road
Zone board, Road studs

16 8

Long term remedial Measures (Nos.)


Rem
arks
Nature of
Nature of Long
Likely
Action taken for
Term Remedial
date of
Long Term
Measures
completi
Remedial
required
on
Measures

Village
Kamrej
Sugar

Without
Opening

The construction of new four lane


Extra Dose Bridge and work is in
progress

Sept-16

No provision for
CoS. VUP
VUP(1X30X5.5)
proposed under
at Lindayat
EPC work of 6
village
laning of Kamrej Tender with
Chalthan.
due date
5.1.2016
Flyover (1 X 40m
floated. 24
+ 2 X 25m) at
months
Navi Pardi
reqd. after
village, Km
No provision of
appoint. of
242.200 & 59 Flyover proposed
Delinators No Entry
agency.
Completed
Service Road under EPC work of

sign board, Road studs

Short Term Remedial


Long term remedial Measures (Nos.)
Measuress
Brief
Sr. NH
Nature of Short
Location of Description
Likely
Likely Rema
No No
Term Remedial
Nature of Long Term
Nature of Action
Black Spots of Problem
date of
date of rks
. .
Measures
Remedial Measures taken for Long Term
at Site
completio
comple
required and
required
Remedial Measures
n
tion
taken
PIU-Surat Expressway
Flyover (1 X 40m + 2
X 25m) at Navi Pardi
No provision of CoS.
Km 242.200 &
Village
Flyover proposed
Due to Cross
Service Road
17 8 Dhoran Pardi
under EPC work of 6
Road
Km241.250 - 242.800
Km.244+000
laning of Kamrej(both side) & Km
Chalthan
242.800 - 243.450
(LHS)
Village
Delineators,
No provision of CoS.
Without
Kholvad
Bollards,
Service Road
Tender with
Opening Cut
Service road from
18 8 Cross Road
Pedestrian
proposed under EPC
due date
& Service
km 246.600 to km
Km.246+600
marking, Sign
work of 6 laning of
5.1.2016
Road
247.310 (LHS)
Boards (Median
Kamrej-Chalthan
floated. 24
Completed
opening, U turn ,
months reqd.
Keep Left,
after
Flyover (1 x 50m +2
No provision of CoS.
Accident Prone
x 25m) at Umbhel
appoint. of
Flyover and Service
Village Vav to
Zone) Road
village Km.258.600 &
agency.
Ribbon Devp.
Road proposed
19 8 Village Ubhel
studs, Storage
Service Road
And cross
under EPC work of 6
Km.258+600
lane.
Km.258.200-259.120
road
laning of Kamrej(LHS) & Km. 258.160
Ribbon Devp.
Chalthan
- 260.00 (RHS)
And cross
road
Kadodara
No provision of CoS.
VUP (1 X 12m X
60 proposed under
Bridge to
VUP
5.5m) at Sanjivini
20 8
Village
EPC work of 6 laning

Brief
Sr. NH
Descriptio
Location of
No No
n of
Black Spots
. .
Problem
at Site
Khadak
Pardi Borad
Sonwada(32
22 8
4.210)
21 8

Short Term Remedial Measuress


Nature of Short Term
Remedial Measures
required
And taken

Long term remedial Measures (Nos.)

Likely
Nature of Long Nature of Action Likely
Remar
date of
Term Remedial taken for Long date of
ks
completio
Measures
Term Remedial completi
n
required
Measures
on

PIU-Surat Expressway
Khadki(km 350.920) in Pardi Taluka- provision of PUP (5m X 3m) sanctioned by HQ in 2014.
Undertaken by Concessionaire
Proposal for construction of PUP under consideration under CoS.

Small
Village
Divider,
cautionary sign boards
Bajipura T Without
Complete
23 6
and reflectors & diversion
Joint Km
Zebra
d
sign boards.
50.780
crossing &
Cat eye
Village
Absence
Bajipura
of divider
Signages. Traffic
Complete
24 6 Near Sumul
&
Diversion
d
Dairy
pedestria
Km 53.333 n crossing
Village
Mayapur
Absence
Opp,
All signages / road
Complete
25 6
Speed
Seventh Day
marking
d
Breakers
School Km
45.350

Bypass completed

Flyover completed

Service road completed

61

Details of
Toll Plazas

62

Details of Toll Plazas


National Highways Authority of India- Regional Office-Gujarat
Details of Toll Plaza
Sr. No.

Name of PIU

Date of
Stipulated date EOT up to
start of toll
of Completion (if any)
Collection

DBFOT

OMT

Auction

Next date
of
revision of
user fee

01.01.2013

31.12.2037

DBFOT

1.4.2016

M/s ESSEL
(New NH-47) Ahmedabad Godhra 02.11.2013
Toll Roads Limited

26.12.2040
( End of
Concession
Period)

DBFOT

1.4.2016

M/s ESSEL
Ahmedabad Godhra 02.11.2013
Toll Roads Limited

26.12.2040
( End of
Concession
Period)

DBFOT

1.4.2016

28.02.2038
( End of
02.11.2013
Concession
Period)

DBFOT

1.4.2016

16.01.2016

Auction

1.4.2016

21.08.2016

Auction

1.4.2016

Name of the Toll Plaza & Location

Five Plazas namely Ahmedabad, AUDA Ring Road,


Nadiad, Anand and Vadodara Plazas of Ahmedabad
Vadodara Expressway Ltd.
Kheda & Vasad Plaza Ahmedabad -Vadodara Section of
NH-8

Pithai Toll Plaza at Km. 37+300 of NH-59

Ahmedabad

Vavdi Khurd Toll Plaza at Km. 110+436 of NH 59


( New NH 47)

Bhatwada Toll Plaza at Km. 146+500 of NH 59


( New NH 47)
Kathpur Toll Plaza At Km 472/00 on Ratanpur Himatnagar - Chiloda Section of NH-8
Vantada Toll Plaza At Km 416/00 on Ratanpur Himatnagar - Chiloda Section of NH-8

Name of Agency

IRB Ahmedabad
Vadodara Super
Expressway Tollway
Pvt. Ltd.

M/s BSCPL Godhra


Tollways Limited

M/s Eagle Infra India


17.01.2015
Ltd.
M/s Riddhi Siddhi
Associates

21.08.2015

63

Mode of Operation

Details of Toll Plazas


Mode of Operation
Sr. No.

Name of PIU

Gandhidham

Name of the Toll Plaza & Location

Name of Agency

Date of start of
toll Collection

Stipulated date EOT up to


of Completion (if any)
DBFOT

OMT

Auction

Next date
of
revision of
user fee

Samakhiyali Toll Plaza At Km


309 .000 on NH8A

L&T Samakhiyali
Gandhidham Tollway Pvt.
Ltd

11.09.2010

10.09.2034

DBFOT

1.4.2016

Surajbari Toll Plaza At Km


286.655 on NH8A

M/s. MEP Infrastructure


Developers Pvt. Ltd.

12.10.2015

12.10.2016

Auction

1.4.2016

Khemana Toll Plaza At Km 339 .


000 on NH 14

Shri Bholanath Rajpati


Shukla

05.04.2015

04.04.2016

Auction

1.4.2016

Undvariya Toll Plaza At Km 270 .


000 on NH 15

Ashirvad Industries &


Infrastructure

14.09.2015

14.09.2016

Auction

1.4.2016

Patel Highway Management


Pvt. Ltd.

27.04.2010

26.04.2019

OMT

1.4.2016

Bhiladi Toll Plaza At Km 403 .000


o NH 14
Bhalgam Toll Plaza At Km 439 .
000 on NH 14
Varahi Toll Plaza At Km 160 .000
on NH 15
Makhel Toll Plaza At Km 226 .00
on NH 15

64

Details of Toll Plazas


Mode of Operation
Sr. No.

Name of PIU

Rajkot

Name of the Toll Plaza & Location

Name of Agency

Date of start of toll


Collection

Stipulated date of
Completion

EOT up to (if
any)
OMT

Auction

Vaghasiya Toll Plaza NH-8A (Km. 213.100) for BamanboreGaramore Section in the State of Gujarat.

M/s Welcome Infra Toll


(JV)

16.09.2015

16.12.2015

Auction

1.4.2016

Vanana Toll Plaza NH-8B(at km. 10.755) Porbandar-BhiladiJetpur Section

Shri Suresh Chandra

14.10.2015

14.01.2016

Auction

1.4.2016

Dumiyani Toll Plaza NH-8B (at km. 82.215) PorbandarBhiladi-Jetpur Section

M/s Arya Toll Infra Ltd.

05.09.2015

04.12.2015

Auction

1.4.2016

Veti Toll Plaza- NH-8B ( at Km. 207.500) Rajkot-Bamanbore


Section in the State of Gujarat)

M/s Coral Associates

20.09.2015

20.12.2015

Auction

1.4.2016

Pithadia & Bharudi Toll Plaza NH-8B (at km. 120.700 &
156.800) for Jetpur-Rajkot Section on BOT basis in the State
of Gujarat.

M/s West Gujarat


Expressway Limited

16.05.2008

24.09.2025

BOT Concession
Period 20 years

1.10.2015

Gadoi & Dari Toll Plaza -NH-8D Jetpur-Somnath Section

Jetpur Somnath Tollway


Pvt. Ltd.

07.05.2015

31.03.2042 (End of
Concession Period)

Bharthana Toll Plaza At Km. 157, NH-8,

L&T Vadodara Bharuch


Tollway Ltd.

3/6/2009

07.01.2022 (End of
Concession Period)

BOT

1.7.2015

Choryasi Toll Plaza At Km. 245.70 , NH-8,

IDAA Infrastructure Pvt.


Ltd.

9/25/2009

02.01.2022 (End of
Concession Period)

BOT

1.7.2015

1.9.2015

32

1.4.2016

Khaniwade Toll Plaza (Km. 470.00)


4

DBFOT

Next date of
revision of
user fee

BOT NHAI Share


Rs. 377.75 Lacs

Surat (Exp.Way)
Charoti Toll Plaza (Km. 420.300)
Bhagwada Toll Plaza (Km. 356.200)

M/s. IRB Surat Dahisar


Tollway Ltd.

20.02.2009

21.02.2021 (End of
Concession Period
of 12 yaears)

Boriach Toll Plaza (Km. 297.300)

65

BOT NHAI Share


Rs. 349.75 Lacs
BOT NHAI Share
Rs. 351.18 Lacs
BOT NHAI Share
Rs. 344.43 Lacs

Total

19

Status of ETC Implementation at Toll Plazas


Signing of Deed of Adherence: Completed for all Toll Plazas.
Master Data Submission: Completed for all Toll Plazas.
Segregation of traffic Islands: Work is likely to be completed by 30.06.2015.

Total TPs
under
BOT/OMT

ETC
functioning/ins
talled

27

19

Remarks(Pending works)

2 Toll Plazas in Surat-Hazira section and 2Toll Plazas in AhmedabadVadodara section of NH-8 is under construction.
Instrumentation work of 3 TPs under OMT section from PalanpurRadhanpur-Smakhiali is expected to be completed by 07.07.2015.
Bhalgam TP is temporary and permanent is under construction (delayed
due to LA constraint).

Total
Auctio
ned
TPs

Civil works
completed

Instrumentat
ion works
completed

2 (Vantada and
Kathpur Toll
Plaza)

Remarks (Pending works)

For Balance Civil works: Work completed.


For Instrumentation work :
3 Toll Plazas in Rajkot-Bamanbore-Garamore section:
Inetgration work pending in Vaghasiya Toll Plaza
2 Toll Plazas on Palanpur-Swaroopganj: Integration work
pending. Poor effort by Vaan Infra. 66

Discussion

67

Discussion

Critical Deficiencies in Sr.N


Staff and man-power
Rank

Critical
Deficiency(nos.)

o.
1

General Manager(T)

Project Director

1 (PIU Bharuch)

Manager(T)

Manager(Fin)

Accounts Officer

Improvement in Tender Documents of O&M contracts

Appointment of Supervision Consultant in O&M contracts akin with IE services of


BOT(O&M) (Refer RO-Gujarat letter no. F-44 dated 13.05.2015)

Periodic evaluation of stretches under O&M of NHAI.

68

Thank You