agenda
Sr
Description
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
17
18
Introduction of teams
Self-introduction with brief of discipline, experience and expertise
Broad view of project purpose, goals and targets
Big picture of project + FV brief of machine
Project plan time line schedule
Expectations from teams / individual
Dependencies
Deliverables and schedules
Process flow
Bottle necks, Risk and key issues
Communication plans and review meetings
Requirements occl / oem / ec
Tea break
Way forward
Questions and answer
Lunch
Plant round
Detailed discussion on project activities
conclusion
Welcome note
It is our pleasure to welcome you all on a project of setting up a coal
fired boiler in a new plot of @ 6400 sq mt area, adjacent to existing
premise.
The state of the art technology boiler will be supplied by Forbes
Vyncke and detail engineering for the same will be shouldered by
Mott McDonald.
We at OCCL have great faith in both the agencies' domain expertise
and capacities for timely completion of this assignment with great
accuracy.
The project may be little difficult for all of us, as the boiler technology
is bit new to us and this is the first instance, where we all are roping
our efforts to climb a tough cliff, in just 8 months from now.
Team introduction
The members from all 3 agencies are as:
Client - OCCL
Mr Vijay Sabarwal
J V Shah
Designation
Sr V P operation
Dy G M- projects (Focal
point)
G M Engineering
Asst Mgr- Civil
Asst Mgr Mech
Executive Instrument
Cad designer
Manager electrical
Manager- instruments
Design Engineer
Project manager (Focal
point)
Mr Arvind patel
Div. Director
Project manager (Focal
point)
Manager civil
Mr Vinay Patel
Mr Ankur Chavda
Manager mech
Executive- process
Mr Shyam Mathuria
Mr Rahim Multani
Mr Dipak Sharma
Mr Jignesh Solanki
Mr Dhruv Nakoom
Mr Sanjay Agrahari
Mr Sanjay Hiwase
OEM / contractors -FORBES
VYNCKE
Mr Yogesh Barge
Mr Sanjay Sharma
Consultant - MOTT McDonalds
Mr Arpan Shah
Mr Rakesh Mistry
Project Outline
Purpose = The purpose of projecting this boiler is to suffice total steam requirement
for all 4 production lines at Mundra. At average 2.3-2.5 Tph saturated steam
requirement at 6 kg/cm2 g per line admeasuring 110 to 120 TPD, running
continuously at varying loads without much deviation in operation efficiency. In case
of its out of operation days, 3 numbers FO fired 3 tph steam boilers will cater the
steam requirements. For full load operation on FO boiler , one more boiler may be
procured in future of required capacity.
The main purpose of this project to avail sustainable and reliable steam supply to
customers at least interruptions and lowest operation coast.
Goal = The goal is to set up all the systems encompassing entire scope conformities.
Targets = The entire project is expected from kick-off to steam out is to be finished in
8 months. Commissioning, training and fine tuning to achieve efficient operating
parameters shall be 1 month, post commissioning.
Special Note: The time base line shall be very important, as our next project of U3U4 will overlap, with these schedules.
Clients expectations
Priorities: OEM and EC are expected to deliver correct drawings and documents on time.
Since they have good experience in their domain, we look forward all good inputs, in advance
stage to incorporate in design and result in documents.
Dependencies: This project is a blend of CCC (client, OEM, consultant and contractor)
interface, it is not a stand alone project. OEM is playing a key role in entire project. The
deliverables from OEM are highly important in terms of time and accuracy. EC will be the first
dependent contributing to schedule. OCCL obviously can not move a step without all of above.
Constraints: scope of work, deliverables, site readiness, stretched delivery, safety norms may
be the major constraints. Seasonal effect are of consideration. Monsoon is scanty and will not
impact field work much, but 80% execution shall be in short days of winter, that may affect
daily outputs. Communication can be a constraint and converted to risk.
In light of above factors, our expectations are more inclined to timely delivery of documents. The
correctness of deliverables will save time, efforts, reduced rework and efficient operation of
generation and distribution systems.
Scope of work: We all have rigorous exercise on scope of work and hope is clear to every one.
However, in case of doubt, please make it clear at the earliest. At the end, OCCL requirement
will be considered decisive for all goods of project success.
Process of work
FV has to deliver documents and specific requirement
for efficient operation of steam generation system. FV
also will extend valuable inputs at the design time to
make project successful.
Based on inputs from OCCL and FV, MM will design
their scope of items, put on drawings and documents.
In both the cases, documents will first be submitted
to OCCL for review and will be corrected for
comments, before issuing for work. All will clearly
mention assumptions considered in design /
documents.
OCCL shall have right to make final decision.
Big picture
Occl has decided to install a 14 tph saturated steam boiler delivering
10.54 kg/cm2 g pressure.
The entire set up right from coal yard and handling system to boiler,
ash handling system, flue gas to chimney emitting gas well within
GPCB norms, boiler feed water with DA and steam to plant customer is
planned in adjacent plot
Max steam pressure required in process is 6 kg/cm2 g. Pressure
requirements of other processes are met by respective PRS in all 4
lines.
The length of plot is 168 mtr and width is apx. 39 mtr having roads on
3 sides of approximate 6400 sq.mtr area.
We have prepared a broad layout of facilities and building s with
overall outer dimensions and expected elevations .Construction
features are indicated in respective drawings.
The new facility will have roads, drains, weigh bridge, security cabin,
area and plant lighting for smooth operation round the clock.
Big picture
Big picture
Big picture
A control room in RCC having GF+1 floor will have MCC room
at ground floor, where in FV + OCCL scope MCC and LDB etc
will be installed. First floor will be functioning as control room
and will have all instrument panels, operating and control
stations, effimax, small dedicated lab etc. This building will have
provision of change room, toilets and maintenance room. The
second floor will have a DA tank.
FO boilers will be relocated from hot utility building and housed
in a shed as shown in drawing, with their respective operating
panels. MM has to incorporate details accordingly. FO day tank,
boiler feed water tank chimneys shall be o/s FO boiler shed.
Pipe racks connecting to various buildings and facility shall be
laid and designed to carry steam, hot oil and other utility lines.
Electrical and instrument Cable will be routed through these
racks.
The plot
CFB PLOT
The layout
The layout
The layout
The layout
The layout
The layout
The layout
The layout
The layout
Time line
Communication plan
Single contact point:
Occl J V Shah 9687699009
FV Sanjay Sharma
MM Rakesh Mistry
Team members will communicate with specific person, as and when required after prior intimation to
Mr J V shah