KPIs
Outline
Key Performance Index
Manufacturing KPIs
Productivity
Quality
Cost
Delivery
Safety
Morale
Outline Continued
Uses of KPIs
MOTSAP
Learning Objectives
When you complete this chapter, you
should be able to:
Identify or Define:
Key Performance Index
Manufacturing KPIs
Available time for
production
Operation time
Downtime
Learning Objectives
When you complete this chapter, you
should be able to:
Describe or Explain:
KPIs in Manufacturing
Causes of Downtime
Uses of KPIs
Manufacturing KPIs
Indicators used to indicate
manufacturing performance
6 groups of KPIs
Productivity
Quality
Cost
Delivery
Safety
Morale
Production
performance
Quality performance
Cost performance
Delivery performance
Safety and
Environmental
Employee collaboration
Manufacturing KPIs
Customer &
Consumer
Development
Supplier
Planning
Sourcing
Production
Delivery
Manufacturing
Products &
Processes
Development
Productivity KPIs
Total Time
Available Time
Holiday
Unused
Time
Used Time
Planned
Halt Time
Operation Time
Production Time
Effective Time
Unexpected
Stoppage
Performance
Routine
Production
Stoppage
No plan
Planned
maintenance
Productivity KPIs
Total Materials
Total Produced Product
Product that can be sold
Priority Product
Good Product
By Product
Rework
Waste
Defect
Monitoring,
Adjustment
Unbalanced line,
Lack of automation
Idle time,
Motion
Productivity KPIs
1
Actual Cycle Time =
Actual Production Speed
Labor Productivity =
AM Ratio =
Production Volume
Man-hour
Number of Self-Fixing
Number of Breakdown
Productivity KPIs
Actual Output - Defect x 100
%Quality Rate =
Actual Output
%Rework =
%Waste =
Rework
x 100
Actual Output
Waste
Actual Output
x 100
Productivity KPIs
%Performance Rate =
Theoretical Cycle Time x Actual Output x 100
Operation Time
%Availability Rate =
Operation Time - Downtime x 100
Operation Time
Productivity KPIs
%OEE (Overall Equipment Efficiency =
%Availability x %Performance x %Quality Rate
10,000
OEE
%Availability x %Performance x %Quality/10,000
%Availability =
%Performance =
%Quality =
OEE
%Availability Rate =
Operation Time - Downtime x 100
Operation Time
%Performance Rate =
Theoretical Cycle Time x Actual Output x 100
Operation Time
Actual Output - Defect x 100
%Quality Rate =
Actual Output
OEE ( )
500 1
480
30
500 9
0.8 /
OEE
%Availability = (480 30)/480 = 94%
%Performance = (0.8 x 500)/450 =
89%
%Quality = (500 9)/500 = 98%
%OEE = (94 x 89 x 98)/10,000
= 82%
Productivity KPIs
%Breakdown =
Breakdown Time
Operation Time
x 100
MTTR, MTBF
MTTR = Mean Time To Repair
Weekly plan
Wed Thu
1500
Fri
4000
20 hrs
Sat
3000
2000
2500
4
Planned Maintenance
Repair Time
No Plan
Example
Sun Mon Tue
Wed Thu
Fri
Sat
4.25-4.35
10
3.30-3.50
20
22.25-23.00
21.50-22.20
35
30
3.20-4.20
60
610
22.00-8.10
Productivity KPIs
Available Time x 100
%Machine Availability =
Total Time
Used Time x 100
%Machine Utilization =
Total Time
Effective Time x 100
%Operation Efficiency =
Operation Time
Quality KPIs
Average Rejection Case by Customer
Average Rejection Case by QA
Capability Index =
USL - LSL
6SD
Controllable
1.00
Good Control
1.33
Quality KPIs
Number of Quality Kaizen
Total Rejection x 100
%Rejection =
Actual Output
Cost KPIs
Conversion Cost = Cost used for conversion
of Raw material to Product
1. Production direct, indirect and service cost.
2. Purchasing, Planning and Supply support cost
Cost KPIs
Inventory of Spare Part = Cost of Spare Part
Inventory
Inventory of Material = Cost of Raw Material
and Finished Goods
Inventory
Inventory of WIP = Cost of Work-InProcess Inventory
* Usually showed in % of Produced Product
Cost KPIs
Production Direct Cost =
Direct Labor + Depreciation + Other Direct
Product Volume
Production Indirect Cost =
Indirect + Other Indirect
Product Volume
Repair & Maintenance Cost
Delivery KPIs
Actual Output x 100
%Output Reliability =
Planned Output
Number of Target Hit x 100
%Plan Attainment =
Number of Production Run
Safety KPIs
%Accident Frequency Rate =
Lost Working Time + Restricted Working Time
Total Working Time
Number of Safety Suggestion
Number of Unsafe Correction
Number of Incident
Number of Accident
Morale KPIs
Absent Employee x 100
%Absent =
Total Employee
Kaizen Rate =
Training Rate =
Number of Kaizen
Total Employee
Total Training Hour
Trained Employee
Using of KPIs
5W-1H
What data should be collected
Where location of machine/working place
Who take action to report KPI
When timing and frequency of report
Why meaning of KPI
How to collect data
Using of KPIs
MOTSAP
Strategy
1.
2.
3.
4.
5.
%Rejection = 0
Reduce %Defect 50%
Increase %OEE 5%
Increase labor productivity 30%
Reduce downtime 50%
Action
Policy
Mission
Objective
Target
Plan
Establish projects
Establish plans