Академический Документы
Профессиональный Документы
Культура Документы
Project Management
Operations
Operations Management
Management -- 55thth Edition
Edition
Roberta Russell & Bernard W. Taylor, III
Beni Asllani
University of Tennessee at Chattanooga
Lecture Outline
Project Planning
Project Scheduling
Project Control
CPM/PERT
Probabilistic Activity Times
Project Crashing and Time-Cost
Trade-of
Copyright 2006 John Wiley & Sons, Inc.
9-2
What is a Project?
Project
Examples
9-3
Project Elements
Objective
Scope
Contract requirements
Schedules
Resources
Personnel
Control
Risk and problem analysis
9-4
Project planning
Project scheduling
Project control
Project team
Matrix organization
Project Manager
9-5
Project Scope
Scope statement
Statement of work
9-6
9-7
9-8
Project Scheduling
Steps
Define activities
Sequence
activities
Estimate time
Develop schedule
Techniques
Gantt chart
CPM
PERT
Microsoft Project
9-9
Gantt Chart
Graph or bar chart with a bar for each
project activity that shows passage of
time
Provides visual display of project
schedule
Slack
9-10
Month
4
10
Activity
Design house
and obtain
financing
Lay foundation
Order and
receive
materials
Build house
Select paint
Select carpet
Finish work
Month
9
9-11
Project Control
Time management
Cost management
Quality management
Performance management
Communication
Enterprise project management
Copyright 2006 John Wiley & Sons, Inc.
9-12
CPM/PERT
Critical Path Method (CPM)
9-13
Project Network
Activity-on-node (AON)
Activity-on-arrow (AOA)
Event
Node
1
Branch
completion or beginning
of an activity in a project
9-14
3
Design house
and obtain
financing
3
2
Dummy
0
1
Order and
receive
materials
4
Select
paint
Build
house
3
1
Finish
work
1
Select
carpet
9-15
Concurrent Activities
Lay foundation
Lay
foundation
Order material
3
Dummy
2
0
1
Order material
(b) Correct precedence
relationship
9-16
Build house
4
3
2
2
Start
Finish work
7
1
1
3
Design house
and obtain
financing
3
1
5
1
6
1
Select carpet
Select paint
9-17
Critical Path
4
3
2
2
Start
1
3
3
1
A:
B:
C:
D:
7
1
1-2-4-7
3 + 2 + 3 + 1 = 9 months
1-2-5-6-7
3 + 2 + 1 + 1 + 1 = 8 months
1-3-4-7
3 + 1 + 3 + 1 = 8 months
1-3-5-6-7
3 + 1 + 1 + 1 + 1 = 7 months
6
1
5
1
Critical path
Longest path
through a network
Minimum project
completion time
9-18
4
3
2
2
Start
Finish at 9 months
7
1
1
3
3
1
Start at 3 months
5
1
Finish
6
1
Start at 6 months
9-19
Mode Configuration
Activity number
Earliest start
Earliest finish
Activity duration
Latest finish
Latest start
9-20
Forward Pass
Start at the beginning of CPM/PERT network to
determine the earliest activity times
Earliest Start Time (ES)
EF= ES + t
9-21
Start
Build house
2
1
1
Design house
and obtain
financing
1
3
1
Order and receive
materials
Copyright 2006 John Wiley & Sons, Inc.
Finish work
1
Select carpet
Select pain
9-22
Backward Pass
Determines latest activity times by starting at
the end of CPM/PERT network and working
forward
Latest Start Time (LS)
LS= LF - t
9-23
Start
Design house
and obtain
financing
Build house
Finish work
Select carpet
Select pain
9-24
Activity Slack
Activity
LS
ES
LF
EF
Slack S
*1
00
00
33
33
*2
33
44
33
33
55
55
55
44
55
55
88
77
88
66
55
66
77
66
88
77
*7
88
88
99
99
3
*4
1
1
* Critical Path
9-25
Variance:
where
b-a
2 = 6
a = optimistic estimate
m = most likely time estimate
b = pessimistic time estimate
Copyright 2006 John Wiley & Sons, Inc.
9-26
P(time)
P(time)
Time
P(time)
Time
m=t
Time
Copyright 2006 John Wiley & Sons, Inc.
9-27
6,8,10
System
development
Start
3,6,9
Position
recruiting
1,3,5
Equipment testing
and modification
2,4,12
Manual
testing
2,3,4
System
training
3,7,11
Job Training
2,4,6
3,4,5
System
testing
Final
debugging
10
1,4,7
Finish
11
1,10,13
System
changeover
Orientation
2,2,2
9-28
1
2
3
4
5
6
7
8
9
10
11
MEAN TIME
VARIANCE
6
3
1
2
2
3
2
3
2
1
1
8
6
3
4
3
4
2
7
4
4
10
10
9
5
12
4
5
2
11
6
7
13
8
6
3
5
3
4
2
7
4
4
9
0.44
1.00
0.44
2.78
0.11
0.11
0.00
1.78
0.44
1.00
4.00
9-29
1
2
3
4
5
6
7
8
9
10
11
ES
EF
LS
LF
8
6
3
5
3
4
2
7
4
4
9
0.44
1.00
0.44
2.78
0.11
0.11
0.00
1.78
0.44
1.00
4.00
0
0
0
8
6
3
3
9
9
13
16
8
6
3
13
9
7
5
16
13
17
25
1
0
2
16
6
5
14
9
12
21
16
9
6
5
21
9
9
16
16
16
25
25
1
0
2
8
0
2
11
0
3
8
0
9-30
Start
2 0
6 0
3 0
3 2
4 8
5 16 21
10 13 17
8 9
7 9
Critical Path
13
5 6
3 6
6 3
4 5
16
3
Finish
16
1 0
9 9 13
4 12 16
11 16 25
9 16 25
7 3 5
2 14 16
9-31
9-32
where
= tp = project mean time
= project standard deviation
x = proposed project time
Z = number of standard deviations x
is from mean
Copyright 2006 John Wiley & Sons, Inc.
9-33
= tp
Copyright 2006 John Wiley & Sons, Inc.
Time
9-34
2 = 6.89 weeks
=
6.89
= 2.62 weeks
= 25 x = 30
Z= x-
= 30 - 25
2.62
= 1.91
Time (weeks)
9-35
= 6.89
= 22 - 25
2.62
= 2.62 weeks
= -1.14
x = 22 = 25
Time
(weeks)
9-36
Project Crashing
Crashing
Crash time
Crash cost
Goal
9-37
2
8
12
7
4
12
3
4
5
4
6
4
9-38
Crash cost
Crashed activity
$4,000
$3,000
Normal activity
$2,000
$1,000
Normal cost
Normal time
Crash time
|
2
|
4
|
6
|
8
|
10
|
12
|
14
Weeks
9-39
ACTIVITY
1
2
3
4
5
6
7
NORMAL
TIME
(WEEKS)
CRASH
TIME
(WEEKS)
NORMAL
COST
12
8
4
12
4
4
4
7
5
3
9
1
1
3
$3,000
2,000
4,000
50,000
500
500
15,000
$5,000
3,500
7,000
71,000
1,100
1,100
22,000
$75,000
$110,700
CRASH
COST
TOTAL
ALLOWABLE
CRASH TIME
(WEEKS)
5
3
1
3
3
3
1
CRASH
COST PER
WEEK
$400
500
3,000
7,000
200
200
7,000
9-40
$500
$7000
2
8
12
$700
7
4
12
$400
3
4
Project Duration:
31 weeks
Additional Cost:
$2000
FROM
6
4
5
4
$3000
TO
Project Duration:
36 weeks
$200
$200
$500
$7000
2
8
12
$700
7
4
$400
3
4
$3000
5
4
$200
6
4
$200
9-41
Time-Cost Relationship
Crashing costs increase as project
duration decreases
Indirect costs increase as project
duration increases
Reduce project length as long as
crashing costs are less than indirect
costs
9-42
Time-Cost Tradeoff
Minimum cost = optimal project time
Cost ($)
Indirect cost
Direct cost
Crashing
Project duration
Copyright 2006 John Wiley & Sons, Inc.
Time
9-43
9-44