Академический Документы
Профессиональный Документы
Культура Документы
and
Procedures
Payment Modalities
Lump Sum
Re-measurement
Cost reimbursement
Lump Sum
Scope of the work and the amount is well
defined.
Contractor agrees to work for a pre-determined
lump sum.
Lump Sum
tem
Nr.
Description
Unit
Qty
Rate
Amount
Lump Sum
Advantages & Disadvantages
Cost commitment is
known at the outset
Relatively easy
contractor selection
Re- measurement
The scope of the work is generally well defined
but the amount of work is indefinite.
Sufficiently detailed scope of work to allow
contractor to calculate unit rates.
Description
Unit
Qty
Rate
Amount
Cost Reimbursement
Contractor is paid all what he spends plus OH & Profit.
Minimal pre-determined scope definition.
Clear and explicit definition of what constitutes
reimbursable costs.
Co-operative atmosphere and a competent and
trustworthy contractor.
Close audit and quality supervision and direction by the
Client.
Cost Reimbursement
Item
Nr.
Schedule
Rate
Unit
Cost Reimbursement
Advantages & Disadvantages
Useful when the
scope cannot be
specified in advance
Reduces ability to
compare contractors
bids
Evaluation by Engineer
(Clauses 12.3 and 12.4)
Sub Clause 12.3 Provides the basis for the Engineer to
determine the value of each item of work
The rates specified in the Contract will apply unless
there are no appropriate rates for a new item of
work
New Rates may be determined where items a) and
b) of Sub Clause 12.3 apply
Sub Clause 12.4 provides for possible
compensation to Contractor relating to omissions
of work
Prov. Sum
120
00
PC Sum
%
Item
800
00
PC Sum
(Contd)
55 00
Additions
800.00
80.00
120.00
850.00
85.00
Profit (10%)
120.00
General attendance
Total
Less omission
Net addition C/F to Grand Summary
1000.00
1055.00
(1000.00)
55.00
Daywork Records
The minimum information recorded should
include:
Hours worked by those engaged in daywork
Hours machines were hired
Material used by the Contractor for daywork
purposes
Progress Payments
Contractual Implications
(Clauses 14.3 - 14.6)
The conditions of contract stipulates:
Final Accounts
Sub Clauses 14.10/14.11/14.12/14.13
These deal with the Statement on completion,
application for Final Payment Certificate, discharge
and issue of Final Payment Certificate
Sub Clause 14.15 Currencies of Payment
This clause sets out the procedures if the payments
are to be made in more than one currency
Exercise 1
Read Clauses 12, 13 & 14 of the Red Book and answer following questions.
Yes
Does the Contractor undertake the measurement of
the Works in Red Book?
Should the method of measurement be stated in the
Bill of Quantities
Can the Engineer demand the Contractor to give the
breakdown of his rates?
No
May
be
Exercise 1 (Cont.)
Yes
Can the Daywork Schedule be used to agree
new rates
Can the Contract Price be fixed?
Can the Engineer correct previous payment
certificates?
Have Provisional Sums to be spent within the
contract?
No
May
be
Exercise 2 (Group)
A contract agreement was signed based on the FIDIC 1999
Red Book on 1st February, with Commencement Date
stated as 1st March. On 4th April the Contractor submitted an
application for an interim payment.
On 18th April, the Engineer replied that he did not intend to
issue an Interim Payment Certificate.
On what grounds can the Engineer refuse to issue an Interim
Payment Certificate?
Thank You