Process Plant Commissioning and
Hamdy Ahmed Abd ElStartup
Rahim
Hamdy Ahmed
ALPHA
Introduction
Hamdy Ahmed
ALPHA
Approach to Commissioning
The Commissioning Phase can be split into 5 distinct activities that are
usually performed in chronological order
Pre-Commissioning
Commissioning
Start-Up
3
Hamdy Ahmed
ALPHA
Hamdy Ahmed
ALPHA
Hamdy Ahmed
ALPHA
Hamdy Ahmed
ALPHA
Hamdy Ahmed
ALPHA
Commissioning Phase
Size of the Task
Hamdy Ahmed
ALPHA
Hamdy Ahmed
ALPHA
ALPHA
Hamdy Ahmed
of
all
aspects
of
the
Project
Construction
ALPHA
Hamdy Ahmed
of
commissioning,
completed systems.
certification
and
handover
of
12
Hamdy Ahmed
ALPHA
Construction,
Commissioning
and
Handover
to
operations.
13
Hamdy Ahmed
ALPHA
14
Hamdy Ahmed
ALPHA
15
Hamdy Ahmed
ALPHA
16
Hamdy Ahmed
ALPHA
DEFINITIONS
Means the assigned person(s) to Coordinate the pre
commissioning and cooperate to the commissioning
Commissioning Manager
activities
With all involved parties until "Ready for
Commissioning"
Site Manager
Integrated Team
17
Hamdy Ahmed
Mechanical
Completion
Construction
Completion
ALPHA
Pre-commissioning
Punch List
18
Hamdy Ahmed
ALPHA
System
19
Hamdy Ahmed
ALPHA
Documents
Hamdy Ahmed
ALPHA
Mechanical Completion.
Mechanical Completion means the System or Sub-System is:
1- Physically Complete ( Conformity Check)
equipment is aligned.
Hamdy Ahmed
ALPHA
Mechanical Completion.
2- Tight
There is no loss of pressure or leakage from equipment, piping, joints,
etc
3- Functional
can operate as intended.
4- Tested
Equipment has been successfully inspected, tested and certified as
required.
22
Hamdy Ahmed
ALPHA
Mechanical Completion.
5- Safe
The facilities are inherently safe and all systems for the protection of
personnel, environment and property are installed, operational and
documented
6- Clean
The facilities have been flushed, are clean, dry and have the
necessary temporary equipment installed ready for Commissioning.
23
Hamdy Ahmed
ALPHA
Mechanical Completion.
Inspection and testing activities performed to achieve Mechanical
Completion by System or -Sub-System are:
24
Hamdy Ahmed
ALPHA
25
Hamdy Ahmed
ALPHA
26
Hamdy Ahmed
ALPHA
27
Hamdy Ahmed
ALPHA
Example
1Instrument tagging.
2Model number and instrument classification.
3Size and connections.
4Material of construction.
5Instrument range and calibration.
6Valve action and air/electrical failure positions
28
Hamdy Ahmed
ALPHA
29
Hamdy Ahmed
ALPHA
design specifications
Rotational checks
30
Hamdy Ahmed
ALPHA
Non-destructive examination
Bolt tensioning
System flushing
Hydro-testing
Re-instatement
31
Hamdy Ahmed
ALPHA
Chemical cleaning
Pickling
Vacuum/air drying
32
Hamdy Ahmed
ALPHA
Example 1 Vessel
1Conformity with project documentation.
2Pressure, temperature, rating.
3Nozzles, sizes and orientation.
4Internals: types, dimensions, metallurgy and installation.
5Instrument nozzles and types.
6Ladders, platforms, walkways: Location, size and accessibility.
7Nameplate information/data.
8Grounding connections.
9Vents, drains, relief valves provided as specified.
33
Hamdy Ahmed
ALPHA
Example 2 Pipe
1
Size.
Flange bolting tightness: nuts, gaskets and bolts are properly installed.
34
Hamdy Ahmed
ALPHA
Non-destructive examination
35
Hamdy Ahmed
ALPHA
Small pieces of mill scale, weld rod stabs, weld spatter, insulation,
paper, wood and other debris are sometimes unavoidably left in
piping and equipment on completion of construction.
A systematic program for flushing with water or blowing with air will
eliminate most of the debris that might obstruct control valves and
orifice plates restriction orifices or damage machinery.
36
Hamdy Ahmed
ALPHA
Recommendations
Dirties and debris should be flushed from the unit and not into it.
The P&I Diagrams are used to prepare the flushing sequence and
to follow the progress of flushing. Finally, manual fine cleaning may
be necessary.
Hamdy Ahmed
ALPHA
Recommendations
38
Hamdy Ahmed
ALPHA
Recommendations
Hamdy Ahmed
ALPHA
Recommendations
Check that stroke movement; of any valve that was cut in during
the flushing, are free and complete.
40
Hamdy Ahmed
ALPHA
Recommendations
41
Hamdy Ahmed
ALPHA
Recommendations
42
Hamdy Ahmed
ALPHA
Pre-commissioning.
Pre-Commissioning means the System or Sub-System is:
1- Physically Complete
The System/Sub-System has been constructed, installed and tested
under power in accordance with the design documents, Vendor
documents and other applicable documents as required.
43
Hamdy Ahmed
ALPHA
Pre-commissioning.
2- Tight
There is no loss of pressure or leakage from equipment, piping, joints,
etc.. during running
3- Functional
Can operate and running as intended.
4- Tested
Equipment has been successfully energized and tested.
.
44
Hamdy Ahmed
ALPHA
Pre-commissioning.
5- Safe
The facilities are inherently safe and all systems for the protection of
personnel, environment and property are installed, operational and
documented
6- Complete
Everything is tested, in working order, lubricants are added to
machinery, equipment is aligned, operability checks have been
performed and the equipment is ready for Commissioning.
45
Hamdy Ahmed
ALPHA
Pre-commissioning.
Inspection and testing activities performed to achieve System/Sub
System Acceptance are:
All tests are documented on type "B" ITR's and the status of
completion recorded within and monitored by the Completions &
Certification Management System (CCMS).
46
Hamdy Ahmed
ALPHA
Pre-commissioning Items.
1- Electrical
Breaker operation
Motor runs
47
Hamdy Ahmed
ALPHA
Pre-commissioning Items.
1- Electrical
Test and calibration of all switch gear relays (using primary and Secondary injection as applicable),
metering, lights, indicators, space heater, and check proper coordination and setting.
11Functional checking of switchgear and MCC from remote locations such as Control Room.
12Energizing the substation for readiness of plant commissioning and start-up.
48
Hamdy Ahmed
ALPHA
Pre-commissioning Items.
2- Instrumentation / Control / Fire & Gas / ESD
Frequency tests
49
Hamdy Ahmed
ALPHA
Pre-commissioning Items.
2- Instrumentation / Control / Fire & Gas / ESD
Example
1Level DP transmitters.
2Pressure transmitters.
3Temperature transmitters.
4Transducers.
5Petitioners.
After completion of this work QA/QC stickers should
7be fixed on the instruments, then, the check form
shall be signed by all concerned parties.
50
Hamdy Ahmed
ALPHA
Pre-commissioning Items.
3- HVAC
Hamdy Ahmed
ALPHA
Pre-commissioning Items.
4- Mechanical/Piping
Installation of temporary strainers
Load testing of Lifting equipment
Pre-Commissioning of Lubrication, Cooling, Fuel, Seal Gas and
Hydraulic systems, including flushing, circulation, draining and refilling as required by the specification
Coupling of rotating equipment
52
Hamdy Ahmed
ALPHA
Pre-commissioning Items.
4- Mechanical/Piping
Vibration and Noise testing
Mechanical seal integrity checks
Final inspection of vessels
Critical Valve Testing
Relief Valve re-setting
53
Hamdy Ahmed
ALPHA
Pre-commissioning Items.
6- Common
54
Hamdy Ahmed
ALPHA
commissioning
Commissioning means:
55
Hamdy Ahmed
ALPHA
commissioning
56
Hamdy Ahmed
ALPHA
Commissioning Items.
Vendor control
Cause and effect logic tests Control logic checks Safety Systems
testing DCS functional testing PLC Functional tests ESD
Functional testing
57
Hamdy Ahmed
ALPHA
Commissioning Items.
Punch Listing
Test Runs
Integrated Runs
Surveys
Operator Training
58
Hamdy Ahmed
ALPHA
Start-Up
Start-Up means:
59
Hamdy Ahmed
ALPHA
Start-Up Items.
Restart
Hamdy Ahmed
ALPHA
System Example
The following is an example of a system / sub-system breakdown
into system limits.
The primary system is 70A and is made up of sub-system 70A-1,
70A-2, 70A-3, 70A-4, 70A5 and 70A-6 as shown in the extract from
the Work Breakdown Structure below. PI&D's will be used to highlight
the System and Sub-system Limits
61
Hamdy Ahmed
ALPHA
62
Hamdy Ahmed
ALPHA
63
Hamdy Ahmed
ALPHA
64
Hamdy Ahmed
ALPHA
System Durations
Inspection and Testing man-hour can be allocated to each required
ITR thus giving a breakdown of the duration involved for the
Inspection and Testing of all system equipment.
This information is utilized for scheduling each phase of the
Construction and Commissioning activities.
The table below details each Inspection and Test required for the
sample Air Compressor System above.
65
Hamdy Ahmed
ITR
E01-2A
E02A
E09A
101A
103A
105A
106A
S01A
X03A
MOIA
M03-IA
M03-2A
M05A
M08-1A
M12A
M20A
M24A
M29A
M31A
M33A
M30A
ALPHA
66
Hamdy Ahmed
ITR
CW01A
CW02A
CW04A
CW05A
CW06A
CW07A
A03A
P01A
P02A
P03A
PO4A
P05A
E05B
E06B
101B
102B
105B
DESCRIPTION
COMPACTION TESTING
CONCRETE POUR
FOUND'N GROUTING
FOUNDATIONS
FOUND'T COATING
FOUND'N PRE-INSPECT
CLADDING / INSULATION
PIPING PKG INDEX
INSTALLATION CHECK
TEST EQUIP. CAL. CERT
FLUSH & TEST
RE-INSTATEMENT
CONTROLPANEL
ELECTRIC MOTORS
VALVES (ON/OFF/ESD)
CALIBRATION PSV
DIGITAL 110 CHECK
No. REQUIRED
2
2
2
2
2
2
1
1
1
1
1
1
1
3
2
4
10
ALPHA
MANHOURS PER
TOTAL
ITR
4
8
4
8
4
8
4
8
4
8
4
8
4
4
3
3
4
4
2
2
4
4
4
4
4
4
8
24
12
24
6
24
4
40
67
Hamdy Ahmed
ALPHA
ANALOGUE 110
106B CHECK
8
6
48
LOOP FUNCTION
107B
1
10
10
TEST
111B MOTOR CONTROL
3
24
72
M01 B PRESSURE VESSEL
2
12
24
TOTAL
1059
be estimated to be:
Electrical = 2
Instrument = 4
Mechanical = 2
Piping = 2
Civil = 1
Structural = 1
Painting = 1
Total = 14
Architectural = 1
68
Hamdy Ahmed
ALPHA
System Durations
The duration for Inspection and Testing activities for the above
system would be 8 days. The commissioning procedure including
vendor support would add a further 4 days to the overall duration
for this system.
Thus giving a total duration of 12 days, which does not include the
time required to complete the hand over process.
69
Hamdy Ahmed
ALPHA
70
Hamdy Ahmed
ALPHA
71
Hamdy Ahmed
ALPHA
72
Hamdy Ahmed
ALPHA
Commissioning Schedule
Examples of such key plant systems are the electrical system and
compressed air system.
73
Hamdy Ahmed
ALPHA
74
Hamdy Ahmed
ALPHA
?Any Questions