BASIC WELL COMPLETION

Introduction

Introduction to
Well Completion

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes
Conductor

Surface
casing

Intermediate
casing

Production
casing

Production
liner
PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up

Depth reference
below derrick floor - bdf
roller kelly bushing - rkb
Main deck
Cellar deck
depth reference
PE Skill Group 10

Sea level

Conductor
May 2003

Introduction

BASIC WELL COMPLETION

Drilling Operations - Making Holes


Typical Sequence of Operations :
Rig up
Drill surface holes

Main deck
Cellar deck
Sea level

PE Skill Group 10

Conductor

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up
Drill surface holes
Run and set surface casing

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up
Drill surface holes
Run and set surface casing
Cement casing

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up
Drill surface holes
Run and set surface casing
Cement casing
Drill intermediate holes

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up
Drill surface holes
Run and set surface casing
Cement casing
Drill intermediate holes
Run and set intermediate casing

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up
Drill surface holes
Run and set surface casing
Cement casing
Drill intermediate holes
Run and set intermediate casing
Cement casing

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up
Drill surface holes
Run and set surface casing
Cement casing
Drill intermediate holes
Run and set intermediate casing
Cement casing
Drill production holes

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up
Drill surface holes
Run and set surface casing
Cement casing
Drill intermediate holes
Run and set intermediate casing
Cement casing
Drill production holes
Run and set production casing

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up
Drill surface holes
Run and set surface casing
Cement casing
Drill intermediate holes
Run and set intermediate casing
Cement casing
Drill production holes
Run and set production casing
Cement casing

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up
Drill surface holes
Run and set surface casing
Cement casing
Drill intermediate holes
Run and set intermediate casing
Cement casing
Drill production holes
Run and set production casing
Cement casing
Drill production holes

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up
Drill surface holes
Run and set surface casing
Cement casing
Drill intermediate holes
Run and set intermediate casing
Cement casing
Drill production holes
Run and set production casing
Cement casing
Drill production holes
Run and set liner

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Drilling Operations - Making Holes

Typical Sequence of Operations :


Rig up
Drill surface holes
Run and set surface casing
Cement casing
Drill intermediate holes
Run and set intermediate casing
Cement casing
Drill production holes
Run and set production casing
Cement casing
Drill production holes
Run and set liner
Cement liner
PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Casing Schemes

There are various casing


schemes depending on
drilling, completion and
reservoir considerations e.g.

PE Skill Group 10

Hole Size

Casing Size

Pile

26 conductor

20 1/4

18 5/8

17 1/2

13 3/8

12 1/4

9 5/8

8 1/2

May 2003

BASIC WELL COMPLETION

Introduction

What is well completion ?


What is the objective of well completion ?

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction

What is the objective of well completion ?


To provide communication between
reservoir and the surface
With subsurface and surface flow
control mechanisms

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction

Why well completion is so important ?

To effectively drain out the reservoir fluids to


the surface - increase productivity and recovery

To provide subsurface and surface flow control

Increase asset value through cost optimisation well completion cost represents one of the
major contributor to total wells expenditure in
field development

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction

Well Completion Communicate Reservoir


to Surface

reservoir

reservoir
PE Skill Group 10

reservoir

reservoir
May 2003

BASIC WELL COMPLETION

Introduction

Well Completion Communicate Reservoir to Surface


Typical Sequence of Operations :
Well clean out

reservoir

reservoir
PE Skill Group 10

Clean Out
Assembly

Bit and
Scraper
+
Cleanout
Fluid

reservoir

reservoir
May 2003

BASIC WELL COMPLETION

Introduction

Well Completion Communicate Reservoir to Surface

Perforating
gun
Assembly

Typical Sequence of Operations :


Well cleanout
Perforate
Kill well
(Sand exclusion - if required)

reservoir

reservoir
PE Skill Group 10

reservoir

reservoir
May 2003

BASIC WELL COMPLETION

Introduction

Well Completion Communicate Reservoir to Surface


Typical Sequence of Operations :
Well cleanout
Perforate
Kill well
(Sand exclusion - if required)
Run and set completion string
reservoir

reservoir
PE Skill Group 10

reservoir

reservoir
May 2003

BASIC WELL COMPLETION

Introduction

Well Completion Communicate Reservoir to Surface


Typical Sequence of Operations :
Well cleanout
Perforate
Kill well
(Sand exclusion - if required)
Run and set completion
string
Install X-mas tree
Depth reference - THF

well
PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction

Well Completion Communicate Reservoir to Surface


Typical Sequence of Operations :
Well cleanout
Perforate
Kill well
(Sand exclusion - if required)
Run and set completion
string
Install X-mas tree
Tie-in well

To
Production
system

well
Production
header
PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction

Well Completion Communicate Reservoir to Surface


Typical Sequence of Operations :
Well cleanout
Perforate
Kill well
(Sand exclusion - if required)
Run and set completion string
Install X-mas tree
Tie-in well
reservoir
Unload and produce well
Handover to production
reservoir
PE Skill Group 10

reservoir

reservoir
May 2003

BASIC WELL COMPLETION

Introduction
Typical Well
Completion

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction
Completion Tubing Sizes
Tubing size ranges from 2 3/8
2 7/8
3 1/2
4
4 1/2
5 1/2
7
To as large as 9 5/8

PE Skill Group 10

May 2003

BASIC WELL COMPLETION

Introduction

What can happen if completion not


optimal ?
Low rate due to restriction
in the reservoir - near wellbore (skin)
in the completion tubing
Early water or gas breakthrough
Faster production decline
Equipment failure e.g. surface choke cut
Frequent shutdown e.g. sand in separator
COST
PE Skill Group 10

REVENUE
May 2003

BASIC WELL COMPLETION

Introduction

Something we can observe at surface and


feel at surface

PE Skill Group 10

temperature
pressure
physical damage
sound
vibration
etc
May 2003

BASIC WELL COMPLETION

Introduction

Various Forms of of Wellbore Sketches

X
V

PE Skill Group 10

May 2003